1 / 17

Independent Living Programme 12 November 2015 Essex County Council

Independent Living Programme 12 November 2015 Essex County Council. Contents. INNER CIRCLE CONSULTING. BACKGROUND AND CONTEXT SIX FACTORS OUTCOMES AND NEXT STEPS. Situation. INNER CIRCLE CONSULTING. Summer 2014 360 existing Units – Extra Care No consistent model of delivery

loisj
Download Presentation

Independent Living Programme 12 November 2015 Essex County Council

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Independent Living Programme 12 November 2015 Essex County Council

  2. Contents INNER CIRCLE CONSULTING • BACKGROUND AND CONTEXT • SIX FACTORS • OUTCOMES AND NEXT STEPS

  3. Situation INNER CIRCLE CONSULTING • Summer 2014 • 360 existing Units – Extra Care • No consistent model of delivery • Target of 2,500 units • 200 in pipeline

  4. Complication INNER CIRCLE CONSULTING • Limited resources • Falling revenue funding • Increasing demographics • Care Act • Personalisation • Changes to housing benefit

  5. Question INNER CIRCLE CONSULTING • Why, given the accepted benefits to the service users and councils, wasn’t more extra care development coming forward? • What could ECC do to increase the amount of extra care development coming forward?

  6. Answer INNER CIRCLE CONSULTING • To answer these questions the Council commissioned an intensive eight month programme of activity, involving extensive engagement and consultation with the districts, developer/providers and other councils to develop an action plan. • A strategic business case was produced in Autumn 2014 setting out the barriers and challenges that needed to be overcome. • An outline business case was produced in Summer 2015 demonstrating how the barriers and challenges had been overcome and seeking endorsement for significant revenue and capital investment to deliver the programme.

  7. Six Key Factors to Accelerating Delivery INNER CIRCLE CONSULTING

  8. Definition INNER CIRCLE CONSULTING • For people aged 55+ • Attractive, self-contained housing . A mixture of 1 and 2 bed apartments • 24/7 care and support should be based on the site • Scheme size typically from 40-300 units • Ideally schemes would be in a large town or large village in close proximity to public transport links to access a larger urban centre. • Broadly, an even balance of low or no care need (0 – 9 hours/week), medium care need (10 – 15 hours/week) and high care need (15+ hours/week) should be maintained. • ECC will require a minimum of 6 hours/week of assessed care need for an individual to be eligible for a unit.

  9. Demographic Demand INNER CIRCLE CONSULTING

  10. Delivery Model(s) INNER CIRCLE CONSULTING • Delivery model is dependent on source of land • The grant funding model supports delivery of schemes being brought forward by developer/ providers on land that they have sourced • Where land is sourced by a public sector organisation ECC does not have an efficient way to access the developer/ provider expertise and capacity to turn that piece of land into an operational independent living scheme • Decision taken to set-up a developer/ provider framework that will be used to efficiently appoint developer/providers to take forward schemes on land owned by the public sector. • Still possible to undertake one-off procurements if schemes come forward quickly

  11. Viability of Independent Living per Unit #1 INNER CIRCLE CONSULTING • Delivery of an Independent Living scheme is dependent on both capital and revenue viability. • Capital viability is dependent upon land and build costs, tenure mix, rents and sales values. • A key factor specific to independent living schemes is whether or not the social rented properties qualify as exempt accommodation. Qualification as exempt accommodation means that the landlord can charge rents above the level of housing benefit which can in turn be claimed from Central Government from the District. Higher rents improve viability.

  12. Viability of Independent Living per Unit #2 INNER CIRCLE CONSULTING • Revenue viability is based upon how care is commissioned and how much the County pays for the care • A key factor specific to independent living schemes is who contracts with the provider on the provision of care and how this relates to personalisation. • If ECC contracts through a block care contract then the tenants have been denied an element of personal choice and that block contract will need to be tendered within 3-5 years. In the event that the developer/provider loses that contract another care provider could provide care services in the building owned by another provider; an issue highlighted by the market as a barrier to development • If the individuals contract with the care provider (receiving direct payments and support and guidance from ECC) then personal choice has been exercised and, whilst the developer/provider has to continue to deliver a high quality service or risk individuals changing provider, they do not have the medium term risk of the re-procurement of the block care contract

  13. Viability of Independent Living per Unit #3 INNER CIRCLE CONSULTING • Tools to bridge capital viability gap: • Land donation • HCA grant • ECC grant • Cross-subsidy from ownership units • Increase proportion of ownership units Development value £20k Development value £10k Development cost Development cost Development cost £80K-100K Development value Social rented unit Shared ownership unit Private sale unit

  14. Influencing Planning Policy INNER CIRCLE CONSULTING • In order to increase the pipeline of sites available on which IL housing can be built, work has been undertaken to influence emerging planning policy documents to recognise IL as a distinct housing type and land use • Currently planning policies do not reflect Independent Living, in that sites are not allocated for its use, and as demand isn’t specified, LPAs are not proactively seeking provision through either policy or development management • We are working with the ECC Spatial Planning and Infrastructure teams to embed Independent Living within the planning policy framework of each District

  15. Capital Investment and Revenue Savings INNER CIRCLE CONSULTING • Average capital cost to ECC is likely to remain at circa £30k per unit for affordable rented units • The projected annual net revenue saving per unit is £4,475.

  16. Outcomes and next steps INNER CIRCLE CONSULTING • ECC endorsed the programme Outline Business Case in July which included: • Circa £28m of capital investment over next 5-7 years • £1.8m revenue investment over next 3 years • The move to a system of direct payments • Work has continued on: • Refining and improving the way ECC manages IL schemes • Scoping the developer provider framework • Building the pipeline of schemes (currently at circa 2000 units) • Engagement with districts and the market • Working proactively with districts and developer/providers to take schemes quickly forward.

  17. Independent Living Programme 12 November 2015 Essex County Council

More Related