1 / 22

January – March 2011/12 Fourth Quarter Financial Report

January – March 2011/12 Fourth Quarter Financial Report. Civilian Secretariat for Police. Presentation to Portfolio Committee on Police (18 th September 2012). VISION AND MISSION. Vision A transformed & accountable Police Service that reflects the values of our developmental State Mission

lpope
Download Presentation

January – March 2011/12 Fourth Quarter Financial Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. January – March 2011/12 Fourth Quarter Financial Report Civilian Secretariat for Police Presentation to Portfolio Committee on Police (18th September 2012)

  2. VISION AND MISSION Vision A transformed & accountable Police Service that reflects the values of our developmental State Mission To provide efficient and effective civilian oversight over the SAPS & enhance the role of the Minister of Police.

  3. INTRODUCTION • The Secretariat is for the first time looking at proper planning process & budget spending • Lack of staff capacity in terms of training before M & E visits, had its operational expenditure spent only in the last quarter • The result in slow capacitating of Secretariat related to the approved organogram, led to new staff to be trained, reorganization & streamlining of programmes • Under spending over the last two years was reduced significantly • Over spending in Corporate Services (HR) were mainly related to posts advertised • Under spending in M & E were due to delayed tender process of data base • Despite all these, the Secretariat were still able to spent its total budget evenly

  4. ORGANISATIONAL OVERVIEW The following are the key programmes: • Administration • Police & Research • Monitoring & Evaluation • Partnerships

  5. 2011/12 BUDGET ALLOCATION

  6. Monthly Expenditure January – March 2012

  7. OFFICE OF SECRETARY OF POLICE • Purpose of the programme: The purpose of the programme is to ensure that staff of the Civilian Secretariat for Police are supported to operate in a conducive work environment and ensure improved service delivery • The Office of the Secretary as of 31 March 2012 consisted of the following: • The Secretary of Police (DDG) and PA • Director Strategic Management • Assistant Director: Information • Senior Administration Officer • Senior Admin Clerk

  8. 2011/12 BUDGET ALLOCATION & EXPENDITURE

  9. EXPLANATION FOR OVER/UNDER EXPENDITURE • The following resulted in over spending this quarter: • Funds budgeted for planning was only spent in the last quarter • Budget for legislation related to enactment of Secretariat Bill in December 2011 spent in last quarter • Late charges related to Forensic trip • Restructuring of the Office of the Secretary

  10. CHIEF DIRECTORATE: PARTNERSHIP Purpose: The purpose of the programme is to mobilize role-players, stakeholders and other partners in the fight against crime Sub – Programmes • Civil Society Partnerships • Intergovernmental Partnerships • Community Outreach Programmes • Community Safety Forums • Crime Prevention Private-Public partnerships

  11. 2011/12 BUDGET ALLOCATION & EXPENDITURE

  12. EXPLANATION FOR OVER/UNDER EXPENDITURE • Changes in project execution and expenditure were significant in the fourth quarter of the financial year which was effected due to the following: • Stock theft strategy was replaced by the macro rural safety strategy, which meant a change in planning/project execution • CPF workshop to prepare CPF Guidelines took place in 2nd & 3rd Quarters • CSF Training programme procurement process delayed • Targets for public participation engagements were exceeded during the third quarter

  13. CHIEF DIRECTORATE: POLICY AND RESEARCH Purpose: The purpose of the programme is to provide quality research, policy & legislative advice to the Secretary • Sub – Programmes • Policy and Research • Legislation

  14. 2011/12 BUDGET ALLOCATION & EXPENDITURE

  15. EXPLANATION FOR OVER/UNDER EXPENDITURE • The over spending was due to the following reasons: • Budget funds was spent on the legislation process. • Budget funds was spent on the Small Business Robbery Strategy. This project was transferred from the Partnership unit to Policy unit • Budget funds on fieldwork for basic training was spent • Capacitating of Policy unit only started to take effect in 3rd Quarter • Budget spent on a book detection system and accessories for the Resource Centre. This system was purchased in the third quarter but payment was made in the last quarter

  16. CHIEF DIRECTORATE: MONITORING AND EVALUATION • Purpose: To provide efficient and effective oversight over the SAPS through monitoring and evaluation • Sub – Programmes • Service Delivery and Performance Audit • Policy Compliance • Provincial Coordination

  17. 2011/12 BUDGET ALLOCATION & EXPENDITURE

  18. EXPLANATION FOR OVER/UNDER EXPENDITURE • Monitoring & Evaluation Chief Directorate under spent due to SITA not developing the database because of capacity constraints within SITA. • Terms of Reference for an open tender process in 2012/13 Financial Year have been developed

  19. CORPORATESERVICES • Purpose: To provide efficient and effective administrative and financial support services to the Secretariat • Sub – Programmes • Finance • Human Resources • Supply Chain • Auxiliary Services

  20. 2011/12 BUDGET ALLOCATION & EXPENDITURE

  21. EXPLANATION FOR OVER/UNDER EXPENDITURE • The over expenditure were a result of: • Advertisements for the bulk of posts that were for the new organogram • Training that took place in the third quarter and fourth Quarter were paid • Appointment of new staff

  22. THANK YOU ENKOSI DANKIE