An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Contract C Work As of June 2010 • Precast items: • Sound Barrier 300,000 SF 40% complete • Pipe 48" or smaller 32,600 LF 64% complete • Manholes and Inlets 210 Ea 70% complete • Box Culvert Crossings 1,000 LF 80% complete • MSE Walls 60,000 SF 70% complete • 113 Girders 11,270 LF 54% complete Cast-in-place items: • Sound Barrier Footings 12,000 LF 45% complete • Bridge Decks 465,000 SF 35% complete • Parapets 18,800 LF 31% complete • Special Piers 105 Ea 98% complete • Total Concrete Placed 54,100 CY 61% complete Steel Girders: • 83 Girders 40,779 LF 83% complete (18,800,000 LBS) Paving items: • Hot mix asphalt (HMA) 431,000 TN 9% complete 1

  2. Final Overall Facts For ICC • Precast items: • Sound Barrier 1,218,000 SF 19 football fields • Pipe 48" or smaller 186,492 LF 33 miles long • Manholes and Inlets 2,180 Ea • MSE Walls 185,686 SF 3 football fields • 731 Girders 178,670 LF 34 miles long Cast-in-place items: • Sound Barrier Footings 151,260 LF 29 miles long • Bridge Decks* 1,462,000 SF 25 football fields • Parapets 52,550 LF 10 miles long • Special Piers 187 Ea • Total Concrete Placed 179,100 CY 1 field – 8 stories tall Steel Girders: • 202 Girders 77,533 LF (35,188,000 LBS) Paving items: • Hot mix asphalt (HMA) 1,440,000 TN *Includes 81,900 SF for Deckover 2

  3. Project (Program) Management Plan

  4. PMP Table of Contents Quality Project Organization Contract Administration Cost Control Schedule Control Design and Construction Oversight

  5. PMP Table of Contents 2 Environmental Controls Safety Traffic Media / Public Relations Civil Rights Project Closeout Project Administration

  6. Escalation Process (delegation)

  7. Org Chart (upside down vs Escalation)

  8. EVCPs and DCVs

  9. ICC Overall QA Program Manual

  10. Quality Assurance Results

  11. QAO Trend Analysis

  12. Material Quality Analysis

  13. Construction Quality Control Plan

  14. CQCP Table of Contents QC Inspection QA Oversight Organization

  15. DBE/EEO/OJT Compliance Report

  16. N ICC Project Management Office Beltsville, Maryland IC’s Hub A Office Rockville, Maryland IC3’s Hub C Office Beltsville, Maryland Questions and Answers Mark CoblentzConstruction ManagerOffice of the Intercounty Connector301-586-9267mcoblentz@iccproject.com info@iccproject.comwww.iccproject.com 1-866-462-0020 16