1 / 1

Restoring One-Piece Flow To Lincoln Industries

Restoring One-Piece Flow To Lincoln Industries. Stephen Hassler, Jeffrey Troester. Description & Benefits. Company Profile, Project Field, Problems, & Objective. Analysis Method & Findings. Department of Industrial & Management Systems Engineering. University of Nebraska - Lincoln.

marek
Download Presentation

Restoring One-Piece Flow To Lincoln Industries

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RestoringOne-Piece Flow To Lincoln Industries Stephen Hassler, Jeffrey Troester Description & Benefits Company Profile, Project Field, Problems, & Objective Analysis Method & Findings Department of Industrial & Management Systems Engineering University of Nebraska - Lincoln “More Value with Less Work” – Philosophy of Lean Manufacturing Introduction Study Details Proposal Details Description Company Profile Four Step Analysis Method Wash Operation Photographs • Power Wash Cabinet Suggested Settings • Batch Size: 5 Tubes • Wash Phase: 120 s • Dry Phase: 60 s • Unload Phase: 50 s • Key Assumptions • Saw Operation Unit Time Increases (5 s) for Added Material Handling.Bend Operation UnitTime Increases (10 s) for Added Material Handling. • In 1952, Lincoln Industries was founded in Lincoln, NE as a small job shop for custom electroplating. • The company has grown to become Lincoln’s largest water user and North America’s largest metal finisher. • In its 500,000 square feet of production and warehouse space, approximately 500 people are employed. • Annual revenues have grown rapidly over the past decade and now exceed $100 million. • Understand Problem and Magnitude • Visual Aids, Quality Inspection, Time Studies • Develop Alternatives • Seek Expert Opinions, Creative Brainstorming • Verify Feasibility of Alternatives • Examine Attributes and Costs, Design Experiments • Evaluate Alternatives • Economic Analysis, Discuss Qualitative Factors • Time Study Results • Unit Times = 36 s (for 25) / 43 s (for 15) RAW MATERIAL LOADING SAW SAW BEND Understand Problem and Magnitude Project Field • Key Observations • Excessive Idle Time • Frequently Congested Workstation • Operator Sets Operation Pace • Potentially the Bottleneck Operation DEBURR WASH • Visual Aids • The team developed a simple facility layout diagram to convey the problematic nature of the current arrangement. • Photographs and video were taken to document the process and highlight production issues. DEBURR MACHINE SAW WASH • Lincoln Industries (LI) is best known as North America’s largest metal finisher.  However, the company’s operations are diverse and our team took a look at their fabrication activities.  At a facility in Air Park (Lincoln, NE), LI fabricates exhaust stacks for semi-trailer trucks. CARTS CHIPS ≈ 10 FT Develop Alternatives Labor Savings Current Layout • Key Assumptions • Labor Expense (Hourly) = $15 • Source of Labor Savings • Labor Reduction at Wash Operation (1 Operator) • Idle Time Avoidance at Wash Operation (3 Operators) • Projected Labor Savings • Labor Reduction per Wash = 13 min = $3.35 • Idle Time per Wash = 6 min * 3 = 18 min = $4.50 • Total per Wash = $7.85 • Total per Day = $7.85 * 5 = $39.25 • Payback Period = 334 Workdays = 16 Months • Salvage Value Not Considered, Likely Substantial • Seek Expert Opinion – Idea List • Power Washing Cabinet • Power Washing Conveyor System • Laser Cutting (No Chips) • Water Jet Cutting (No Chips) • Precision Saw (No Chips) • Creative Brainstorming – Idea List • Vacuum (Handheld or Fixed) • Magnets (Handheld or Fixed) • Water Bath with Drying Fans SAW BEND DEBURR Original Problem WASH CARTS • Unfortunately, after the production line was designed, installed, and operating, quality issues arose.  A set of operations occurring early in the production sequence was causing damage to the parts. EMPTY AREA (90 FT2) WASH CARTS Labor Savings Robustness Verify Feasibility of Alternatives • Calculated Savings are Intentionally Conservative • Using 6 Washes per Day or Idle Time Avoidance of 10 min Significantly Improves Expected Payback Period ≈ 100 FT Lean Issues Original Remedy VACUUM EXPERIMENT • Four of the Seven Wastes of the Toyota Production System (TPS) were glaringly obvious as a result of the current layout. • Waste of Transportation • Waste of Waiting • Waste of Inventory • Waste of Motion • A quick solution was developed by LI and another operation was added to the production process, though it occurred on a workstation off of the main production line. BEND MACHINE Evaluate Alternatives Other Benefits Consequential Problem • Economic Analysis • Cost savings are likely to result from reduced labor (drying tubes), reduced overall processing time (from elimination of idle time), reduced WIP, potentially improved quality, and a cleaner, more orderly work space. • Will the savings from the installation of a power washing cabinet justify its expense? Understand Problem and Magnitude • Added Washing Capacity • Liberated Wash Station Operator • One Year Warranty on Washer • Less Consumables (Gloves, Rags) • Less Material Handling Equipment (Carts) • Cleaner, More Orderly Facility • By locating the workstation off of the main line, one-piece flow was disrupted.  As a result, material handling became excessive, processing time increased, and quality control declined. • Quality Inspection • Though inefficient, the current wash operation sufficiently removes chips from the tubes. • Chips are being introduced from various sources such as material handling carts, gloves, rags, and tools. Proposal – InstallHotsy Model 7663 UNLOADING BENDER Project Objective Rationale Understand Problem and Magnitude • Purchase Cost • $10, 650 • Tube Fixtures (5) • $1,250 • Consumables • $1,200 / Year • TOTAL – YEAR 1 • $13,100 Contributors • Moving water seems to remove chips from the tubes better than other methods. For a relatively low cost, the team believes that LI can achieve significant savings with the installation of a power washing cabinet. However, the efficiency of the machine is dependent upon some batching. Therefore, pure one-piece flow will not be achieved. • It is the goal of the investigating team to develop a cost-effective proposal that remedies these undesirable byproducts and restores one-piece flow to the production line. • Time Studies • Surprisingly, the inefficient wash operation is not typically the bottleneck of the production line. • However, when the wash operation becomes congested, it definitely has the ability to function as the bottleneck. • Hotsy Equipment Co. (NE) • Roy Gage – Sales Representative • Dennis Klingemann – Sales Representative • Lincoln Industries (NE) • Bill Hancock – Area Leader, Fabrication • Eric Jacobs – Development Engineer Image Sources: www.adventureinmetals.com, www.franeklaser.com, www.hotsy.com, www.lincolnchrome.com, www.lincolnindustries.com

More Related