1 / 34

Project Overview

Integrated Waterfront Cleanup and Marina Development in Bellingham, WA Tom Wang, P.E. WEDA Pacific Chapter – San Diego 2009. Project Overview. Port of Bellingham is managing an integrated cleanup, new marina construction and waterfront re-development project within the Whatcom Waterway

marge
Download Presentation

Project Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Integrated Waterfront Cleanup and Marina Development in Bellingham, WATom Wang, P.E. WEDA Pacific Chapter – San Diego 2009

  2. Project Overview • Port of Bellingham is managing an integrated cleanup, new marina construction and waterfront re-development project within the Whatcom Waterway • Cleanup Whatcom Waterway contaminated sediments • Cleanup ASB sludges • Establish new shoreline face for future development • Construct new small boat marina • Improve marine habitat and public access

  3. Project Team • Anchor QEA • KPFF Consulting Engineers • Coast and Harbor Engineering • Wilson Engineering • BST & Associates

  4. Project Site Key Areas Cornwall Landfill Port Terminal (BST) Log Pond (ASB) GP Pulp & Tissue Mill (GP West) GP Dock Whatcom Waterway Central Waterfront

  5. Whatcom Waterway Consent Decree Dredging Capping • Dredge Areas • ASB • Outer Waterway • Cap Areas • Inner Waterway • ASB Shoulder • Chemical Dock • Log Pond Deep-Draft Sludges Removed Dredging & Capping of Multi-Purpose Waterway Central Waterfront Shoreline Cleanup

  6. Waterfront District Framework Plan(4/20/09)* • Joint planning effort by Port and City • Upland development by Western Washington University • Focus on sustainable design, community needs and working waterfront * Plan is subject to modification based on continued technical evaluations and public input.

  7. Key Integration Challenges ASB Cleanup • ASB dredge prism • Sludge dewatering method • Water and stockpile management Outer Waterway • Dredge prism design • BST underpier area and Log Pond transition • Residual management Inner Waterway • Engineered cap design (coastal modeling and propwash) • Shoreline transition areas Disposal • Landfill competition and escalating costs

  8. Key Integration Challenges Marina Development • ASB berm design incorporates public access and habitat • Float layout • Landside development • ASB landside stormwater improvements Other Key Project Challenges • Coordinating nearshore and upland uses and infrastructure • Multiple stakeholders (WWU, City, Port, Existing Tenants) • Site stormwater temporary improvements • GP Mill Site development timing • Rail access and stockpile management • Need to significantly raise grades at GP Mill Site

  9. Project Quantity Summary

  10. ASB Typical Profile • Defining native layer (i.e., clean surface) difficult • Geophysical methods unsuccessful • Several direct measurement methods used and correlated against boring logs

  11. Sludge Dewatering • Hazco and Boskalis conducted independent pilot studies • Centrifuge • Filter press • Belt Press • Geotubes • Stabilization • Elutriate and leachate testing

  12. Waterway Areas with Special Issues BST Wharf Log Pond Transition Clarifier Bulkhead Area Maple Street

  13. BST Underpier Area

  14. BST Underpier Area

  15. BST Underpier Area Partially-armored slope Current design concept Diver-assisted hydraulic dredging Thickness Est. Avg. 5 ft Backfill removal area Residuals Management Maintain wharf design condition

  16. BST – Log Pond Transition Area Current conditions Wharf Condition Berthing Uses

  17. BST – Log Pond Transition Area Design issues High subsurface concentrations Propwash and windwave exposure Need for larger armoring Steep slope complicates placement Armor placement constraints Overhead structures Impacts of placement to structure

  18. Inner Waterway • Main channel area to be capped • Propwash is the critical design factor • Gravel layer as armor • Inner waterway slopes to be armored • Windwaves are critical design factor • Armor stone required in wave breaking zone

  19. Inner Waterway Steep-Slope Areas • Design issues • Existing structures • Shoreline integration • Existing upland use • Waterway and upland future uses • Impacts of sloping fill to navigation • Narrow channel • Potential future maritime uses • Boat haul-out

  20. Maple Street Bulkhead • Issues • Phasing of cleanup and upland improvements • Land and navigation uses Condition at -3 ft MLLW

  21. Clarifier Bulkhead Condition at -3 ft MLLW • Issues • Clarifier structure remains for temporary construction use • Phasing of cleanup and upland improvements • Land and navigation uses

  22. ASB Berm Reconfiguration

  23. ASB Armor Stone Reuse Analysis Good Long-Term Stone Quality Unsuitable for Armor Reuse

  24. ASB Armor Stone Reuse Analysis Good Long-Term Stone Quality Unsuitable for Armor Reuse

  25. ASB Armor Stone Reuse Analysis

  26. Public Access and Habitat Opportunities

  27. Marina Pathway Area

  28. Marina Habitat Areas Notes: *Slopes will vary depending on location.

  29. Numerical Modeling • Numerical modeling is critical to effectively assess constantly changing alternatives from Port and Stakeholder input • Base model set up to cover both remediation and development purposes • Wind wave impacts • Tidal circulation • Whatcom Creek discharge impacts • Propwash impacts • Sea level rise and tsunami effects

  30. Wave Modeling (25 Yr)

  31. Stormwater Transitioning • Existing stormwater systems inadequate for future development • More than 80 acres require upgrades • Currently plumbed to discharge to ASB • Upgrades to be phased for future development • Stormwater design to transition to City responsibility in long term

  32. Current Status and Schedule 30% design to be completed Spring 2010 Permit applications ~mid-year 2010 Bid advertisement ~mid-year 2011 Construction duration 3-4 years Consent Decree cost estimate Remediation $55 million Marina $23 million

  33. Questions?

More Related