Comprehensive Sidewalk Program Overview

Comprehensive Sidewalk Program Overview. March 13, 2018 Vancouver Planning Commission Workshop Ryan Lopossa, Streets/Transportation Manager. Presentation Overview. Background Phase 1 – Existing Conditions Inventory Phase 2 – Analysis & Prioritization Phase 3 – Field Data Collection

meppinger
Download Presentation

Comprehensive Sidewalk Program Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Comprehensive Sidewalk Program Overview March 13, 2018 Vancouver Planning Commission Workshop Ryan Lopossa, Streets/Transportation Manager

  2. Presentation Overview • Background • Phase 1 – Existing Conditions Inventory • Phase 2 – Analysis & Prioritization • Phase 3 – Field Data Collection • Phase 4 – Program Development • Next Steps City of Vancouver Sidewalk Program Overview - 2

  3. Background • City constructs new sidewalks & ADA ramps through Transportation Improvement Program (TIP) • Pavement Management resurfacing projects include & require funding for constructing ADA-compliant ramps • City reconstructed nearly 600 ADA curb ramps between 2014-2017 City of Vancouver Sidewalk Program Overview - 3

  4. Background • New developments & site expansions require new or reconstructed ADA-compliant sidewalks & ramps (over 14 miles of new sidewalks added in 2017) • As with many other municipalities, maintenance of sidewalks in Vancouver are typically responsibility of adjacent property owner • Deficient sidewalks addressed via complaint-driven process • Pedestrian accessibility through work zones remains a challenge City of Vancouver Sidewalk Program Overview - 4

  5. Background – Estimated Costs & Revenues Estimated Costs: • Curb ramp improvements: approx. $77 million • Upgrade existing sidewalks throughout City: approx. $40 – 60 Million • Fill in missing sidewalk gaps throughout the City: approx. $130 – 200 Million • Additional Available Revenues: • Street Funding Strategy (SFS) provides $500,000 annually for multimodal, safety & accessibility projects • Provisions for upgrades also included in funding for new TIP projects (approx. $3.5 million annually) and increased Pavement Management budget (additional SFS funding) City of Vancouver Sidewalk Program Overview - 5

  6. Background − Challenges & Opportunities Challenges: • Limited resources for accessibility projects • Parks maintenance backlog includes ADA improvements • Street network deficiencies • Non-compliance implications • Opportunities: • Street Funding Strategy includes resources for multimodal, safety & accessibility projects. • Initiating internal grant pilot program • Strategic Plan includes ADA needs • Vancouver Strong community engagement effort City of Vancouver Sidewalk Program Overview - 6

  7. Phase 1 (Summer 2015) Inventory of sidewalks & curb ramps 7

  8. Phase 1: Inventory of Sidewalks & Curb Ramps • Desktop process using geographic information system (GIS) layers • Sidewalks & curb ramps inventoried: • Sidewalks Exist • Sidewalks Don’t Exist • Curb Ramps Exist • Curb Ramps Don’t Exist City of Vancouver Sidewalk Program Overview - 8

  9. Phase 1: Inventory Results (w/ Annexation) • 636 miles:Existing sidewalks • 494miles: Missing sidewalk segments • 10,374: Total curb ramps • 5,029: Intersection corners without curb ramps City of Vancouver Sidewalk Program Overview - 9

  10. Phase 2 (Spring 2016) Analysis & Prioritization 10

  11. Phase 2: Analysis & Prioritization • Sidewalk/curb ramp demand analysis to determine priority focus areas • Analysis criteria includes safety, equity, street classification & pedestrian demand to identify priorities • Identified additional field data collection needs & attributes for Phase 3 field work City of Vancouver Sidewalk Program Overview - 11

  12. Phase 3 (2016 – 2017) Field data collection 12

  13. Phase 3: Field Data Collection • 14-month effort, start to finish • 3 Key layers • Curb ramps • Sidewalks • Deficiencies City of Vancouver Sidewalk Program Overview - 13

  14. Phase 3: Field Data Collection – Curb Ramps • Ramp type • Dimensions • Truncated domes • Obstructions • Slopes • Landings • Ramp photo City of Vancouver Sidewalk Program Overview - 14

  15. Phase 3: Field Data Collection – Sidewalks • Sidewalk type • Material • Width City of Vancouver Sidewalk Program Overview - 15

  16. Phase 3: Field Data Collection – Deficiencies • Barriers/blockages • Cracking/separation • Slopes • Driveways (w/cross-slope) • Heaves & dips • Surface condition • Others… City of Vancouver Sidewalk Program Overview - 16

  17. Phase 3: Field Data Collection – Results • Approximately 177,000 defect points • 636 miles of existing sidewalk • Data & photos for 10,374 curb ramps • 23 miles of sidewalk adjacent to City property • 16 miles of missing sidewalk segments adjacent to City property City of Vancouver Sidewalk Program Overview - 17

  18. Phase 4 (Current Phase – 2017/18) Program Development 18

  19. Phase 4 – Program Development • Sidewalk inspector Position • Data Analysis • Maintenance responsibility & ADA • Sidewalk deficiency prioritization • Homeowner sidewalk repair grant program • Formalized enforcement program • Revised VMC language City of Vancouver Sidewalk Program Overview - 19

  20. Phase 4 – Program Development • Sidewalk Inspector Position • FTE assigned to deal with all issues related to sidewalks • Work with property owners on needed repairs/replacements • Provide customer focused outreach and education • Administer homeowner grant program • Work with downtown business on sidewalk café seating • Monitor work zone activities that impact sidewalks • Inspection of City sidewalk and curb ramp projects City of Vancouver Sidewalk Program Overview - 20

  21. Phase 4: Data Analysis – Calculating Condition • Determine segment conditions • Determine ramp conditions • Estimate repair cost per defect City of Vancouver Sidewalk Program Overview - 21

  22. Phase 4 – Program Development Data Analysis – Priority Mapping City of Vancouver Sidewalk Program Overview - 22

  23. Phase 4 – Program Development • Homeowner sidewalk repair grant program • Would provide assistance to low-income property owners who are faced with costly sidewalk repairs/replacements • Eligibility would be similar to CDBG criteria (earning up to 80% of AMI) • Potential 50:50 split with total reimbursable costs capped at $1,500 City of Vancouver Sidewalk Program Overview - 23

  24. Phase 4 – Program Development • Enforcement program • Based on RCW 35.68/69 • Tiered process to bring deficient sidewalks into compliance • Combination of education/outreach and correspondence • When all else fails, City would make required repairs and seek reimbursement from property owner • Property liens City of Vancouver Sidewalk Program Overview - 24

  25. Phase 4 – Program Development • Revised VMC language • Look at additional opportunities where development can provide sidewalk improvements • Strengthen code language related to pedestrian circulation through construction zones • Required code language to support enforcement program City of Vancouver Sidewalk Program Overview - 25

  26. Next Steps • Completion of data analysis • Phase 4 deliverables • VMC revisions • City Council Work Session (Spring 2018 • Program rollout (Summer 2018) City of Vancouver ADA Program Overview - 26

  27. Questions Ryan Lopossa, Streets & Transportation Manager Ryan Miles, Operations Program Manager Jennifer Campos, Senior Planner