An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Market TrialsReal-Time Market / LFC Weekly Update July 2, 2010 http://nodal.ercot.com 1

  2. Antitrust Admonition ANTITRUST ADMONITION ERCOT strictly prohibits Market Participants and their employees who are participating in ERCOT activities from using their participation in ERCOT activities as a forum for engaging in practices or communications that violate the antitrust laws. The ERCOT Board has approved guidelines for members of ERCOT Committees, Subcommittees and Working Groups to be reviewed and followed by each Market Participant attending ERCOT meetings. If you have not received a copy of these Guidelines, copies are available at the Client Relations desk. Please remember your ongoing obligation to comply with all applicable laws, including the antitrust laws. DISCLAIMER All presentations and materials submitted by Market Participants or any other Entity to ERCOT staff for this meeting are received and posted with the acknowledgement that the information will be considered public in accordance with the ERCOT Websites Content Management Operating Procedure. http://nodal.ercot.com 2

  3. Agenda • Antitrust Admonition • Environment Report • Planned / unplanned outages • Known Issues • Standing Reports and Updates • General reminders / updates • RTM / LFC Update • LFC Testing Update • State Estimator Convergence Statistics • Question and Answers / General Discussion ERCOT asks that Market Participants log into the WebEx session using their company name and then their name. This will allow ERCOT to take roll-call offline http://nodal.ercot.com 3

  4. Market Trials 2010 Roadmap http://nodal.ercot.com 4

  5. Environment Report: Planned / Unplanned Nodal Outages Planned Outages • 07/02/2010 6:00 P.M. – 11:00 P.M. • Database maintenance activities are planned during this period and will affect availability of following application services: • EWS ( Web Services) • MM UI Unplanned Outages • 06/29/2010 12:10 P.M. – 12:45 P.M. • Users were unable to launch MM UI & CRR applications via the MIS portal due to a script failure. http://nodal.ercot.com 5

  6. Known Issues Recently Opened Issues • NP8-541-Monthly Responsive Reserve Performance Report (Certified Report) • Report is failing with the error message • Affects EDW • Hyperlink typos on MIS • MIS Other Binding Documents  QSE Application to Provide Balancing Energy Service Bids (need to add “Service Bids” to the hyperlink text) • MIS  Grid  Generation  Reliability Must Run  "Reliabilitiy Must Run Criteria“ (the word “Reliability” has an extra “i” in it) Recently Close Issues • NP4-159-Load Forecast Distribution Factors (MIS Secure Report) • Duplicate hours were in the report output for last day of the report range • This report provides hourly data for the next seven days—the hourly data is being duplicated for each hour of the seventh day • Affected CDR http://nodal.ercot.com 6

  7. Standing Reports and Updates: General Reminders / Updates Reminders/Updates • Network Model Update • The current system loaded from the model 07/01/10 • Next scheduled load is 07/14/10 • EMS Alerts • ERCOT will be testing EMS alerts on Tues. and Thurs. of each week, 10 – 11am • Submit any questions to markettrials@ercot.com • Full-System/LFC tests (see July 1 Market Notice) • ERCOT is updating the Market Trials Phase 5.0 test schedule to incorporate additional Full-System/LFC tests, as follows: • Week of July 19: 5-Hour Full-System/LFC Test (July 20 – 22) • Week of August 2: 24-Hour Full-System/LFC Test (August 3 – 5) • These tests will be conducted in lieu of the previously scheduled 48-Hour LFC Test http://nodal.ercot.com 7

  8. Standing Reports and Updates: General Reminders / Updates Reminders/Updates • 168-Hour Test Handbook • Posted on the Readiness Center at http://nodal.ercot.com/readiness/markettrials/index.html • No kick-off call on 7/05/10 • There will not be a Market Trials weekly kick-off call on 7/05/10 due to the holiday • 5-Hour LFC Workshop • Scheduled during the Friday Real-Time Market call on July 9 • Market Notice will go out to announce this later today • Majority of workshop will focus on a discussion of results from the 8-Hour LFC test • 8-Hour LFC Test Results • To be discussed during 5-Hour LFC Workshop on July 9 • Individual GREDP results to be distributed Week of July 05 http://nodal.ercot.com 8

  9. Standing Reports and Updates: General Reminders / Updates Reminders/Updates • Artifact Updates • The following updated artifacts will deploy overnight to the Readiness Center at http://nodal.ercot.com/readiness/markettrials/rtm/index.html: • Real-Time Known Issues List • SPP and RTRMPR Issues Tracking • Real-Time Market/LFC Market Trials Handbook • Will be updated week of 7/05/10 to reflect new Full-System/LFC testing dates • Full-System/LFC Testing Approach • The current battery of LFC Test Approach documents will be consolidated into a single approach document to be used for the Full-System/LFC tests that will be conducted through the end of Market Trials • The consolidated approach document is schedule to post to the Readiness Center the week of 7/05/10 • A Market Notice will be sent when this document becomes available for download http://nodal.ercot.com 9

  10. Real Time Market / LFC Update 11/11/2014 http://nodal.ercot.com 10

  11. Real Time Market / LFC Update • SCED Week 22 • SL at $2250 offer cap for 104 intervals • SL at $3001 power balance constraint SP for two intervals on 6/29 13:05 and 13:15 • During constraint transfer test • Wednesday (deconstructed zonal curves) looks good http://nodal.ercot.com 11

  12. Real Time Market / LFC Update • SCED Week 22 • System Lambda is LMP that would result if location does not affect any constraint • Generally between $30 and $60; 6/30 prices even lower • Lower Generation Requirement and Zonal equivalent EOC http://nodal.ercot.com 12

  13. Real Time Market / LFC Update SCED Week 22 Thursday Constraint 138_NAL_HAS_1, Contingency SMDOPHR5 (between 00:00 and 18:10 for 29 SCED runs) Constraint 931_C_1, Contingency DWTRWLV5 (between 09:30 and 14:30 for 34 SCED runs) Constraint N_SHARPE_PS1, Contingency DB_DAIR8 (between 13:00 and 23:45 for 32 SCED runs) Friday Constraint AIRLIN_CABANI1_1, Contingency DB_DAIR8 (between 12:05 and 12:25 for 5 SCED runs) Constraint ALAZAN_B_DAVI1_1, Contingency SLONN_S5 (between 12:55 and 13:10 for 4 SCED runs) Saturday Constraint 138_NAL_HAS_1, Contingency SMDOPHR5 (between 09:50 and 19:25 for 76 SCED runs) Constraint 1660__A, Contingency DAUSSND5 (between 01:25 and 09:50 for 84 SCED runs) Sunday Constraint 138_NAL_HAS_1, Contingency SMDOPHR5 (between 15:40 and 22:05 for 79 SCED runs) Constraint 6009__A, Contingency DGRSBNB5 (between 19:35 and 21:55 for 34 SCED runs) Constraint 930__A, Contingency SCDHDES8 (between 13:30 and 19:55 for 67 SCED runs) Monday Constraint 1660__A, Contingency DHUTGIL8 (between 18:00 and 23:40 for 32 SCED runs) Constraint N_SHARPE_PS1, Contingency SLONN_S5 (between 11:30 and 23:45 for 54 SCED runs) http://nodal.ercot.com 13

  14. Real Time Market / LFC Update SCED Week 22 Tuesday Constraint 138_NAL_HAS_1, Contingency SMDOPHR5 (between 11:05 and 19:15 for 34 SCED runs) Constraint 1660__A, Contingency SGILHUT8 (between 11:25 and 11:51 for 5 SCED runs) Constraint 203T260_1, Contingency DAUSSND5 (between 11:45 and 13:55 for 4 SCED runs) Constraint 260_A_1, Contingency DGIBSNG5 (between 11:25 and 11:51 for 7 SCED runs) Constraint 39T188_1, Contingency DFERCOR8 (at 12:10 for 1 SCED run), Constraint 95T302_1, Contingency DMARELM5 (between 13:50 and 14:00 for 4 SCED runs) Constraint ALAZAN_B_DAVI1_1, Contingency SLONWHI5 (between 12:25 and 12:45 for 5 SCED runs) Constraint FAYETT_6AT2, Contingency DAUSLOS5 (between 12:15 and 12:35 for 3 SCED runs) Constraint MARION_4AT2, Contingency DELMSKY5 (between 12:55 and 14:10 for 17 SCED runs) Constraint N_TO_H, Contingency BASECASE (between 11:15 and 17:05 for 75 SCED runs) Constraint N_TO_S, Contingency BASECASE (between 13:04 and 14:10 for 5 SCED runs) Constraint VALIMP, Contingency BASECASE (between 12:20 and 14:25 for 37 SCED runs), Constraint W_TO_N, Contingency BASECASE (between 14:40 and 15:00 for 7 SCED runs) Wednesday Constraint 138_ALV_NAL_1, Contingency SMDOPHR5 (between 11:40 and 16:15 for 25 SCED runs) Constraint 138_NAL_HAS_1, Contingency SMDOPHR5 (between 13:50 and 23:55 for 36 SCED runs) Constraint 1650_A_1, Contingency DFMRMNS5 (between 12:05 and 12:15 for 2 SCED runs) Constraint 1660__A, Contingency DJEWSNG5 (between 15:10 and 16:15 for 12 SCED runs) Constraint N_SHARPE_PS1, Contingency DB_DAIR8 (between 13:00 and 16:05 for 37 SCED runs) http://nodal.ercot.com 14

  15. LFC Testing Update http://nodal.ercot.com 15

  16. Results of the 8 Hour Test • ERCOT operational perspective • The switching of control between systems went smoothly • Frequency was controlled for duration of test by nodal systems • Planned operational scenarios were executed as planned • CPS1 scores were passing except for one hour • ERCOT Operators able to manage numerous active constraints with SCED

  17. Issues & Observations During the 8 Hour Test on June 17th

  18. Issues During the 8 Hour Test - ERCOT • Issue #1 – Missing Shift Factors for Electrical Busses affected SPP calculation • EMS integration did not properly provide electrical bus shift factors • Load Zone, Hub, and Electrical Bus LMPs/SPPs incorrect when constraints binding or violated • Issue introduced with EMS Bug Fix end of last year • Issue #2 – Missing Shift Factors for constraints in SCED for brief period • Shift Factor transfer from EMS to MMS from1320-1339 had issues • Constraints were ignored by SCED for 19 minutes • Dispatch closely monitored by Operators until resolved • Issue introduced with EMS Bug fix in mid-May • Issue #3 – Incorrect flag setting in EMS • ERCOT did not use load distributed bus as the reference bus • Telemetry changes created topology changes which lead to a bus in the west zone to be the reference bus • Having 3% shift factor cut off caused several WGRs to have no shift factors on the constraint causing WGRs to be marginal

  19. Issues During the 8 Hour Test – Market Participants • Issues during test for Market Participants • Telemetry: • Inconsistencies between JOU owners (e.g., telemetry, COP) • Incorrect Ancillary Service values in telemetry for Resource • Incorrect Resource Status Codes • Incorrect HSL/LSL values telemetered • Resource with nodal Output Schedule offering BES into zonal market • Resources not following their nodal Base Points • Resources not following regulation signals • Zonal Resource Plans not in agreement with Nodal

  20. Next Steps – LFC Tests • Migrate fix to views that will resolve the issue with the Shift Factors not being available (Code migrated, still monitoring) • Migrate fix to views that will resolve the issue with transferring an incomplete Shift Factor set (Code migrated, still monitoring) • Use Distributed Load Bus as the Reference Bus instead of Single Reference Bus • Set Shift Factor cut-off to a much smaller value such as .0001 • More closely monitor Resources in how they are following their Base Points and provide feedback • Confirm parameter settings prior to every test • Leave OC1 in Zonal during transition. Once 100% Nodal take out OC1 in Zonal. Bring the OC1 back at the start of transitioning back to Zonal • Specific time slots for tuning for both Market Participants and ERCOT

  21. Next Steps – LFC Test Schedule • Tentatively schedule 6 LFC tests through September • 5 Hour LFC test scheduled the week of July 19th • 24 Hour LFC (noon to noon) scheduled the week of the August 2nd • 2 additional tests in August • 2 tests in September (after 168-Hour Test)

  22. State Estimator Convergence http://nodal.ercot.com 22

  23. State Estimator Convergence Update http://nodal.ercot.com 23

  24. State Estimator Convergence Update http://nodal.ercot.com 24

  25. Q&A Q&A / Open Forum http://nodal.ercot.com 25

  26. Appendix http://nodal.ercot.com 26

  27. URLS and EMAIL ADDRESS FOR SUPPORT • URLs for accessing the Nodal Production systems • MIS: https://mis.ercot.com/pps/tibco/mis/ • Market Manager: https://mis.ercot.com/pps/tibco/mis/Click the ‘Applications’ tab in the upper menu. Link is in the ERCOT Applications portlet • CRR: https://mis.ercot.com/pps/tibco/mis/Click the ‘Markets’ Link in the upper menu. Click CRR in the Market sub menu • EWS: https://misapi.ercot.com/2007-08/Nodal/eEDS/EWS http://nodal.ercot.com 27

  28. Market Trials Handbooks • Market Trials Handbooks • Available on the Readiness Center at the following links • Real Time Market / LFC covering Phase http://nodal.ercot.com/readiness/markettrials/rtm/index.html • Outage Scheduler covering Phase http://nodal.ercot.com/readiness/markettrials/os/index.html • CRR covering release Phase http://nodal.ercot.com/readiness/markettrials/crr/index.html • Settlements / COMs covering Phase http://nodal.ercot.com/readiness/markettrials/coms/index.html • Day Ahead Market http://nodal.ercot.com/readiness/markettrials/dam/index.html http://nodal.ercot.com 28

  29. LFC – Test Overview & Setup: Quick Start Resources • Deployment of Balancing Energy Service (BES) Capable NSRS for Quick Start resources during the LFC test • Prior to the resource being asked to come online in Zonal, the QSE should: • telemeter a Non-Spin Schedule and Responsibility (NSSC and NSRS) of 0 • telemeter a resource status showing the resource as offline; and • telemeter an LSL of 0 • If the QSE receives an energy deployment in Zonal, the QSE should start that resource and telemeter a resource status of online (ON) as soon as they are capable • Once the resource is “ON” with net MW > 0, the resource will be available for SCED dispatch and the resource will be dispatched based on the energy offer curve • After the resource reaches it’s physical LSL, the QSE should reflect that value through the telemetered LSL and should leave it at that value • Once Zonal indicates that the resource should go offline, the resource should begin ramping down • When the resource goes offline, the QSE should update the telemetered resource status to offline and then change the telemetered LSL to 0 • The QSE also has the option to not provide BES-Capable NSRS during the hours of the test

  30. LFC – Test Overview & Setup: Congestion Management • Manual dispatch instructions during the LFC test • Beginning two hours prior to the LFC test, ERCOT will stop using OC1s and OOMEs and plans to use OC3s to manage congestion • The one exception to this is that ERCOT will continue to use OC1s for the W-N stability limit (non-thermal IROL for NERC) • ERCOT has created and tested a constraint for this limit in the Nodal system which can be activated for SCED as needed and should provide similar dispatch to the OC1s • ERCOT may be required to use Zonal manual dispatch instructions to solve congestion • ERCOT will set the Nodal Base-Point to match the Zonal manual dispatch instruction • The QSE will continue to follow the Nodal Base Point if they are still under Nodal control