1 / 11

Alternative ICAP Proposal

Alternative ICAP Proposal. NSTAR Strategy James Daly Director Electric and Gas Energy Supply (781) 441-8258. What problem are we trying to solve: Reliability. NEPOOL reliability standard is 1 day outage in 10 years Translates to Loss Of Load Expectation (LOLE) = 0.1day/year

norris
Download Presentation

Alternative ICAP Proposal

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Alternative ICAP Proposal NSTAR Strategy James Daly Director Electric and Gas Energy Supply (781) 441-8258

  2. What problem are we trying to solve: Reliability • NEPOOL reliability standard is 1 day outage in 10 years • Translates to Loss Of Load Expectation (LOLE) = 0.1day/year • NEPOOL Installed Reserve is 31% of peak load in 2004-2005 • NEPOOL Required Reserve is 12.4% of peak load in 2004-2005

  3. NEPOOL Load Growth & LOLE Source: ISO Staff “RTEP04 Resource Adequacy Analysis” presentation 03/18/2004

  4. NEPOOL Load Growth: Installed vs. Required Reserves Source: ISO Staff “RTEP04 Resource Adequacy Analysis” presentation 03/18/2004

  5. Boston Area LOLE: Meets criteria over 10 YearsSo does CT Source: ISO Staff “RTEP04 Resource Adequacy Analysis” presentation 03/18/2004

  6. It is not a capacity issue.We have plenty of capacity.It’s an operating reserves issue!

  7. Coalition Alternative Filed at FERC 03/22/2004 • Implement Locational Operating Reserve Market • Ensures that units needed for operating reserve are adequately compensated • Newly implemented region wide Forward Reserves Market cleared at $4.495/kW-month last January • Implement single region-wide ICAP market • NEPOOL historically planned for reliability on a pool wide basis • Integrates transmission planning and operating realities • Compensates all generators for comparable services • Demand curve key points set at: • 100% of Objective Capability, not 106.7% • X-intercept at 112% of Objective Capability, not 118% • Same as NYISO

  8. Coalition Alternative (continued) • Units compensated in the Locational Operating Reserve Market are units needed for: • 2nd contingency reserve coverage • Local voltage support • Or other local operating needs • Existing units receive a transitional payment under cost-of-service type (RMR) agreements • Contract forward for new resources needed for Locational Operating Reserve Market under RFP

  9. Coalition Alternative (Continued) • ISO/NEPOOL provides 3-year notice prior to changing the price signals established in the ICAP demand curve • Participating ICAP resources provide three-year commitment to remain on the system • No delisting allowed • Liquidated damages for failure to perform • ISO approval of maintenance schedule • New generation should be fully integrated into the grid

  10. ISO Vs Coalition Alternative Costs Total 5 Year Costs $M ISO No Cap $2,865 ISO W/ Cap $1,591 ISO Adjusted $597 Coalition Alternative $154

  11. Coalition March 22 filing in support at FERC: • Attorney General of Massachusetts • Attorney General of Rhode Island • Associated Industries of Massachusetts • Massachusetts Division of Energy Resources • New Hampshire Office of Consumer Advocate • NSTAR Electric And Gas Corporation • National Grid USA • Rhode Island Division of Public Utilities and Carriers • Strategic Energy LLC (in part) • Vermont Electric Power Company (in part) Filed separately but supporting in part: • Connecticut Department of Public Utility Control • Connecticut Office of Consumer Counsel

More Related