1 / 29

SEMAINE DE L’INGENIEUR CIVIL CONGOLAIS

SEMAINE DE L’INGENIEUR CIVIL CONGOLAIS. (Grand Hôtel Kinshasa, 04 - 09 juin 2012). ETAT DES LIEUX DE LA SNEL ET PERSPECTIVES D’AVENIR A L’HORIZON 2025. par. Eric MBALA MUSANDA Administrateur Délégué. S O M M A I R E. PROFIL DE SNEL. 1.1 . Historique 1.2. Statut

olive
Download Presentation

SEMAINE DE L’INGENIEUR CIVIL CONGOLAIS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SEMAINE DE L’INGENIEUR CIVIL CONGOLAIS (Grand Hôtel Kinshasa, 04 - 09 juin 2012) ETAT DES LIEUX DE LA SNEL ET PERSPECTIVES D’AVENIR A L’HORIZON 2025 par Eric MBALA MUSANDA Administrateur Délégué

  2. S O M M A I R E PROFIL DE SNEL 1.1. Historique 1.2. Statut 1.3. Structure organique 1.4. Tableau de bord de 2005 à 2011 ETAT DES LIEUX 2.1. Centrales électriques 2.2. Lignes de transport 2.3. Réseaux de distribution 2.4. Commercial 2.5. Systèmes électriques PERSPECTIVES D’AVENIR 3.1. Secteur de l’ électricité 3.2. Perspectives d’avenir 3.3. Carte électrique de la RDC 3.4. Coûts des projets CONCLUSION

  3. I. PROFIL DE SNEL 1.1. HISTORIQUE INGA I COMECTRIC COGELIN FORCES DE L’EST SOGELEC 1972 FORCES DU BAS-CONGO SOGEFOR 2010 Décision du Gouvernement SNEL 1978 REGIDESO Eau Electricité SNEL sarl

  4. I. PROFIL DE SNEL 1.2. STATUT • Etablissement de droit public a caractère industriel • et commercial • Création le 16 mai 2012 (ordonnance n° 073/033) • Mandat : produire, transporter, distribuer • et commercialiser l’énergie électrique • 07 juillet 2008 : transformation des entreprises publiques • (dispositions générales fixées par la loi n° 08/007) • 24 avril 2009 : SNEL devenu société commerciale • (décret n° 09/11)

  5. I. PROFIL DE SNEL 1.3. STRUCTURE ORGANIQUE Conseil d’Administration Administrateur Délégué Délégué Général Adjoint Cabinet AD Secrétariat Général Dpt du Contrôle Général Dpt Etudes, Plan., Normes et Stand. Dpt de l’Organ. et Systèmes Info. Dpt de Production Dpt de Transport Dpt Distribution en Provinces Dpt Distribution de Kinshasa Dpt Commercial Dpt des Finances Dpt des Appro. et Marchés Dpt des Res. Humaines Dir. Equipement et Electr. Rurale

  6. I. PROFIL DE SNEL 1.4. TABLEAU DE BORD DE 2005 A 2011

  7. I. PROFIL DE SNEL 1.4. TABLEAU DE BORD DE 2005 A 2011 (suite) Evolution du chiffre d’affaires, production brute et nombre d’abonnés

  8. II. ETAT DES LIEUX 2.1. CENTRALES ELECTRIQUES Inga I Inga II

  9. II. ETAT DES LIEUX 2.1. CENTRALES ELECTRIQUES (suite)

  10. II. ETAT DES LIEUX CONTRAINTES • Absence de révision des machines malgré le dépassement • du nombre d’heures de marche requises • Erreurs de conception et de mise en œuvre des • équipements (Inga 2A) • Arrêt de près de 50% des groupes du parc de production • suite à la vétusté et au manque de maintenance • Ensablement du canal d’amenée (dans les centrales) du • fait du manque de dragage, ce qui réduit la production • disponible

  11. II. ETAT DES LIEUX CONTRAINTES (suite) • Difficulté d’approvisionnement en pièces de rechange et • produits pétroliers pour les centrales thermiques • Coût d’exploitation élevé des centrales thermiques, d’où • négociation entre partenaires (SNEL, gros consommateurs • et Etat) du tarif à appliquer • Contrainte climatique se traduisant par la baisse du débit • des cours d’eau, principalement dans le Katanga et le Sud • Kivu, avec un impact sur la production • Etc.

  12. II. ETAT DES LIEUX 2.2. LIGNES DE TRANSPORT Longueur des lignes (km) Transformateurs par réseau

  13. II. ETAT DES LIEUX CONTRAINTES • actes de vandalismes: vols intempestifs des • cornières des lignes HT de transport et des • conducteurs surtout dans le réseau Sud; • saturation des lignes notamment la ligne 220 kV • Inga-Kinshasa; • surcharge de certains postes HT utilisés à plus de • 100% de leur capacité suite à l’accroissement de • la demande; • etc.

  14. II. ETAT DES LIEUX 2.3. RESEAUX DE DISTRIBUTION • Nombre de postes MT/MT • Longueur des réseaux MT • Nombre de cabines MT/BT • Longueur des réseaux BT : 49 : 4.470 km : 2.866 : 17.433 km CONTRAINTES • vétusté des installations et équipements; • surcharge des transformateurs dans les • cabines de distribution et des canalisations • MT et BT; • aménagement des routes ayant conduit à • la destruction des câbles;

  15. II. ETAT DES LIEUX CONTRAINTES • présence au sol des conducteurs dénudés sur • le réseau cause d’électrocution de la population ; • actes de vandalisme: vols des conducteurs et • d’huile des transformateurs; • application de l’alimentation rotative des clients • suite à l’insuffisance de l’offre • etc.

  16. II. ETAT DES LIEUX 2.4. COMMERCIAL Des chiffres Illustration SEGMENTATION DE LA CONSOMMATION EN MWH DU KATANGA • Nombre d’abonnés enregistré • dans la base des donné • Export : 10 • HT : 30 • MT : 1 669 • BT : 689 214 • Nombre des CVS : 58 • Faible taux de desserte + 9%. CONTRAINTES • tarifs moins rémunérateurs fixés par l’Etat • tarifs préférentiels appliqués à certains • gros consommateurs; • difficulté de recouvrer ses créances auprès • des instances officielles, des sociétés • étatiques et paraétatiques • etc. STRUCTURE DES VENTES INTERIEURES EN 2011 16

  17. II. ETAT DES LIEUX 2.4. COMMERCIAL TARIF DANS LA SOUS-REGION SADC

  18. Légende Lignes de transport 220 kV existantes Lignes de transport 110 -132 kV existantes Lignes en projet Ligne THTCC Inga - Kolwezi Centrales Hydro existantes Centrales Hydro en projet Centrales thermiques existantes Kilometers 0 100 200 300 400 500 Bosobolo Mobayi Ango Zongo Bondo Faradje Niangara Gbadolite M’zoro Dingila Libenge Gemena Businga Rungu Bambesa Aru Buta Poko Watsa Isiro Budjala Kungu Lepudungu Aketi Bumba Bumba Lisala Mahagi Wamba Djugu 2.5. SYSTEMES ELECTRIQUES Nepoko Soleniama Bomongo Mambasa Banalia Bunia Irumu Basoko Bongandanga Yahuma Bengamisa Yangambi Budana Bafwasende Babeba Basankusu Bolomba Isangi Djolu Beni Tshopo Wagenia Befale Semliki Kisangani Equateur Kisalala Wanie-Rukula Mbandaka Butembo Boende Ruki Ingende Bokungu Ubundu Mugombe Opala Bikoro Rutshuru Ikela Kiri Goma Monkoto Kalehe Inongo Inongo Inongo Lulingu Kabare Bukavu Moga Ruzizi Kutu Walungu Shabunda Shabunda Mushie Mwenga Kindu Katako- Mungombe Pangi Dekese Kombe Lodja Bandundu Uvira Kamimbi Oshwe Bagata Kampene Kole Mangembe Kibombo Ilebo Kasongo Kinshasa Masi- Bulungu Fizi manimba Lubefu Lusambo Luozi Tshela Zongo Kikwit Kenge Mweka Seke- Luebo Idiofa Sanga Banza Kongolo Lubao Kitona Kyimbi Demba Lukula Mbanza- Kakobola Dimbelenge Inga Bamba Gungu Ngungu Mpozo Kananga Kimvula Popokabaka Mbuji Mayi Moanda Boma Kabinda Matadi Kalemie Kabalo Nyunzu Tshala Kasanza Feshi Katende Tshikapa Mani Lubilanji Kasongo- Kazumba Lungudi Lunda Manono Luiza Moba Kabongo Mwene- Ditu Kahemba Kaniama Tembo Malemba- Nkulu Piana Mwanga Kilubi Kapanga Kamina Mitwaba Bukama Sandoa Kasenga Nseke Nzilo M´sha Koni Dilolo Kolwezi Likasi Lubumbashi Kipushi Sakania

  19. 2.5. SYSTEMES ELECTRIQUES (suite) • Réseaux interconnectés • Réseau Ouest : Bas-Congo, Kinshasa, Bandundu et interconnexion avec Brazzaville • Réseau Sud : Katanga et interconnexion avec la Zambie (SAPP) • Réseau Est : Bukavu, Goma, Uvira et interconnexion avec Burundi et Rwanda • Liaison THTCC Inga - Kolwezi entre réseaux Ouest et Sud • Réseaux hydroél. isolés : Gbadolite, Kalemie, Kamina, Kindu • Réseaux thermiques : Mbuji-Mayi, Kananga, Kikwit • Mbandaka, Moanda, etc.

  20. III. PERSPECTIVES D’AVENIR 3.1. SECTEUR DE L’ELECTRICITE • Secteur ouvert aux privés (EDC), SNEL n’est plus seul opérateur. • Les textes sur la réforme du secteur et le code de l’électricité • discutés au parlement attendent leur promulgation. 3.2. PERSPECTIVES D’AVENIR A court terme • Alimentation sélective des abonnés • Exigence de récupération de puissance ou d’apport • en génération en contrepartie de la signature de • nouveaux contrats avec les sociétés minières

  21. III. PERSPECTIVES D’AVENIR A court terme • Sensibilisation à l’efficacité énergétique • avec appui de l’Etat + partenaires publics et privés • utilisation des lampes CFL pouvant procurer; de 2012 • à 2025, des gains respectifs de 65 à 187 MW au réseau • Ouest) et de 12 à 73 MW au réseau Sud • éclairage public par lampes solaires (250 W/luminaire) • recours aux lampes à faible consommation pour • tout nouveau projet • généralisation des compteurs à prépaiement

  22. III. PERSPECTIVES D’AVENIR A MOYEN ET LONG TERME Actions en cours • Réhabilitation et récupération de puissance • du parc de production d’Inga (cofinancement • BM, BAD et KFW) : • Programme PMEDE (BM) • Programme FRIPT : - réhabilitation de 2 groupes d’Inga 2 (356 MW) - à terme : (1775 MW) totalité de la puissance installée

  23. III. PERSPECTIVES D’AVENIR Actions en cours (suite) • Programme SAPMP : - réhabilitation du système de transport d’Inga à Kasumbalesa - renforcement du transit Inga - Kolwezi de 560 MW à 1.120 MW impliquant, notamment, la réparation des compensateurs synchrones (financements BM et KCC) • Construction des centrales de : • - Zongo 2 (150 MW) par Sinohydro • - Busanga (240 MW) par Sicomines • sur financement de la Chine • Réhabilitation des groupes de Nseke (partenariat TFM)

  24. III. PERSPECTIVES D’AVENIR A moyen et long terme

  25. III. PERSPECTIVES D’AVENIR A moyen et long terme

  26. Zongo III. PERSPECTIVES D’AVENIR Mobayi Ango Bondo Bosobolo Faradje Niangara Dingila Gbadolite Zulu- M’zoro Dungu Libenge Gemena Karawa Bambesa Businga Aru Rungu Watsa Poko Isiro Aketi Kungu Mahagi Lepudungu Buta Budjala Lisala Djugu Wamba 3.3. CARTE ELECTRIQUE DE LA RDC Nepoko Bumba Soleniama I-II Bomongo Mambasa Banalia Irumu Bunia Basoko Basankusu Bongandanga Budana Bengamisa Bafwasende Yahuma Tshopo Bolomba Isangi Beni Semliki Befale Butuhe Djolu Kisangani Kisalala Mbandaka Wanie-Rukula Boende Lubero Butembo Lutunguru Bokungu Opala Lubutu Ingende Ubundu Mugomba Kilima Bikoro Nyabiondo Rutshuru Punia Ikela Ruanguba Kiri Masisi Walikale Katale Monkoto Belia Goma Kalehe Inongo Lulingu Lomela Katana Ambwe Moga Kabare Ruzizi I Bukavu Nioki Kalima Ruzizi II-III (EGL) Lutshurukuru I-II Walungu Kutu Mushie Shabunda Gombo Mwenga Kindu Dekese Lukenie Kiliba Pangi Lodja Mungombe Bandundu Kamimbi Uvira Oshwe Bagata Kole Katakokombe Kampene Mangembe Kibombo Ilebo Kinshasa Zongo II Masi- Fizi Kasongo Zongo Bulungu manimba Gd Inga Lubefu Piopio Lusambo Tshela Luozi Kikwit Seke- Mweka Kenge Sanga Idiofa Banza Kongolo Lubao Luebo Kyimbi Inga I-II Demba Lukula Dimbelenge Mbanza- Kakobola Kimvula Kitona Kananga Ngungu Nyunzu Popokabaka Gungu Kabinda Bamba Mbuji Mayi Boma Moanda Matadi Mpozo Kabalo Kalemie Tshala Katende Tshikapa Mani Kasanza Feshi Lubilanji I-II Kasongo-Lunda Kazumba Manono Lungudi Gandajika Mwene- Shakahamba Moba Ditu Kabongo Tshilomba Luiza Kahemba Moba Kaniama Tembo L E G E N D E Tembo Kilubi Piana Mwanga Luba Malemba-Nkulu Pweto Kapanga Mitwaba Existant Kibula Kamina Centrale hydroélectrique SNEL Mitwaba Centrale hydroélectrique privée Bukama Centrale thermique Luena Sandoa Dikolongo Ligne HT ou MT Lubudi Kalule Poste HT ca Kilomètres Kasenga Nseke Koni 0 100 200 300 400 500 Fungurume Dilolo Poste de conversion Nzilo Kisenge Mwadingusha Tenke Kolwezi Poste de manœuvre Likasi En projet Kambove Lubumbashi Ligne HT primaire Kipushi Kasumbalesa Ligne HT secondaire Musoshi Mokambo En construction Sakania Poste HT Centrale hydroélectrique Site hydroélectrique inventorié

  27. III. PERSPECTIVES D’AVENIR 3.4. Coût des projets (*) Financement à rechercher

  28. IV. CONCLUSION • Constat de déficit énergétique lié : • au boom minier • à l’explosion démographique • au délabrement des installations électriques • Nécessité d’une action rapide pour résorber le déficit • Projets identifiés dont certains en cours d’exécution • Recherche de financement à entreprendre • pour les projets dépourvus de financement • Solutions rapides : • Importation d’énergie (Congo et Zambie) • Centrale thermique à gaz de Moanda • Centrale thermique à charbon de Luena • Promotion de l’efficacité énergétique • Campagne anti gaspillage d’énergie

  29. Merci pour votre attention