An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RECOGNITION OF NEW TRANSMISSION FACILITIES IN FRM REQUIREMENTS Marc D. Montalvo Presented to NEPOOL Markets Committee 12 September 2006

  2. Assumptions • A historical-data driven approach providing some period of operating experience with a new facility is desirable • A balance must be struck between the need for in-service certainty and unrealized expectations of performance • 5-6 weeks are needed to perform the analysis required to develop auction assumptions • The FRM auction timeline milestones already defined should not be altered. Recognition of New Transmission Facilities in LFRM Assumptions

  3. Proposal • To be considered in service for the purpose calculating FRM auction requirements, a new transmission facility must: • For the summer delivery period, be made available for ISO dispatch prior to midnight on December 31 of the prior year (analysis to develop summer assumptions begins February 1) • For the winter delivery period, be made available for ISO dispatch prior to midnight on April 30 of the same year (analysis to develop winter assumptions begins June 1) • Operate at at least 95% availability during the month immediately following the above deadlines Recognition of New Transmission Facilities in LFRM Assumptions

  4. Proposal Highlights • Does not alter existing timeline milestones • Provides one month of actual operations data • Provides 5-6 weeks necessary for development of auction assumptions • One month in-service requirement coupled with 95% availability requirement provides necessary balance between in-service certainty and untested predictions of performance Recognition of New Transmission Facilities in LFRM Assumptions

  5. Timeline for Summer 2007 In-Service Deadline for New Facilities to be include in Auction Assumptions Dec 31 Begin Auction Assumption Development Feb 1 Post Auction Assumptions March 19 Quoting Period Begins April 17 Quoting Period Ends April 23 Auction Results Posted April 30 Delivery Period Begins 6/1 Dec 1 Jan 1 Feb 1 March 1 April 1 May 1 June 1 Recognition of New Transmission Facilities in LFRM Assumptions