An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lift Design Example • The following notes give an example for design of lifts

  2. Traffic Design - Nos. and Size of Lifts • • Estimation of population • • Quality of service required • – The up-peak interval of an office tower: • 20s or less – excellent system • 30s – satisfactory system • • Quantity of service required • – The handling capacity within 5 minutes • • Estimation of arrival rate • Handling capacity = (5minx60x0.8xLift Car Capacity in nos. of persons)/(up peak interval x population above terminal floor of zone)

  3. (cont.) • Round Trip Time (RTT) by up peak model RTT = 2Htv+ (S +1)ts+ 2Ptp Where, RTT = round trip time in seconds H = highest call reversal floor S = average no. of stops tv= time to transit 2 adjacent floors at rated speed in seconds ts = time consumed when making a stop in seconds tp= passenger transfer time for entering or exiting the lift car in seconds P = 0.8xlift car capacity in person

  4. Question: Lift Traffic Design • Design Input: • An office building of 10 floors above the main terminal is to be built, each floor of 1200 sqm of net space. • The inter-floor distance is 3.3m. • The required up peak interval is 30s (i.e. satisfactory grade) • Estimation of population: assume 12sqm per person per floor, • Assume 12.5% population peak arrival rate • Assumed lift rated speed = 1.6m/s • Given that: • • ts=7.7s (from code) • • tp=1.2s (assumed) • • H=9.5, S=6.7 (from code)

  5. Design Output: Determine the following information: i) Persons per floor ii) Number of persons per arrival iii) Nos. of lift trips per 5 minutes iv) Car size required (person car) v) Total travel distance per lift vi) Transit time between 2 floors vii) RTT (Round Trip Time) viii) Nos. of car required ix) Handling Capacity (persons per 5 mins) x) What is the difference between quantity of service and quality of service

  6. Results: i.e. Pop=1200/12=100 persons per floor •, i.e. 0.125x0.8x100x10flr=100 persons • Qty of service: Nos of trip in 5 minutes = 5minx60/30s=10 • Nos. of person per trip = 100/10 = 10 • The required car size is 10/0.8 = 13-person car • Total travel distance = 3.3x10=33m • Assumed rated speed = 1.6m/s • tv=3.3/1.6=2.1s • ts=7.7s (from code) • tp=1.2s (assumed) • P=13x0.8=10.4 persons • H=9.5, S=6.7 (from code) • RTT=(2x9.5x2.1)+(6.7+1)7.7+(2x10.4x1.2)=124.2s • Since up peak interval required is 30s, i.e. 4 cars are required • The up peak interval is 124.2/4 = 31.1s • The up peak handling capacity is (300/124.2)x10.4x4 = 100.5 persons / 5min