1 / 26

Review: Implementation of Smart Cities Mission Maharashtra Date of Review – March 24, 2017

Review: Implementation of Smart Cities Mission Maharashtra Date of Review – March 24, 2017. SPV& PMC. * Additional Commissioner, NMC is holding additional charge of CEO * M/s Parag Dasarvar & Company appointed as consultancy firm to provide services related to Company Secretary.

pamelaabel
Download Presentation

Review: Implementation of Smart Cities Mission Maharashtra Date of Review – March 24, 2017

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Review: Implementation of Smart Cities Mission Maharashtra Date of Review– March 24, 2017

  2. SPV& PMC * Additional Commissioner, NMC is holding additional charge of CEO * M/s ParagDasarvar & Company appointed as consultancy firm to provide services related to Company Secretary.

  3. Fund’s etc * GoI has issued GR, funds yet to be received by SPV

  4. Projects- Core infrastructure

  5. Visible, Feel, Experience projects * Smart Road is not proposed as part of ABD proposal but has been included in ICT based Nagpur Smart & Safe City Project (PAN City)

  6. Project - Smart Solution * Separate extra slides (Annexure A) attached capturing details on all the ICT led Smart Solutions

  7. Project – ABD * Consultancy firm has been selected for preparation of Town Planning Scheme for identified ABD Area

  8. Convergence- GoI, State Government, Others Name of City: NAGPUR

  9. Projects- Modules, packages Prepared from separate project

  10. Finance- Projects Pipeline • Creation of pipeline of projects (nos.)- 1 -JICA- Nag River Pollution Abetment Project

  11. Finance-Bond

  12. Finance- PPPs and JVs

  13. MIS- Excel Worksheet, Gantt Charts • No. of Gantt Worksheet (Refer Annexure ‘A’) - Nagpur - No (it is being prepared and will be submitted soon) • Smartnet- http://smartnet.niua.org/ - Nagpur (Registered)

  14. CBUD Progress

  15. Milestone for 25 June 2017(City Wise) • No. Of Projects likely to be started- 2 (ABD & Smart Solution) • No. of Projects likely to be Completed- Nil • List of Visible & felt outcomes for people- • CCTV based City Surveillance (approx. 350 locations (approx. 2000 cameras) out of proposed 700 locations) • Fibre based City Network (approx. 600 km out of proposed 1200 km) • City WiFi Services (approx. 119 locations) • City Kiosks (approx. 50 locations) • Smart Strip (5.8 Km with smart solutions like smart light, smart traffic, smart transport, environment sensors, smart solid waste, public address system etc.)

  16. Fast Track & Round 2 Cities (City Wise)

  17. Issues for discussion with MOUD • Considering the roles of various Central and State Govt. agencies, a coordination committee for effective implementation of the Smart City Proposals, is required to be constituted. The committee should consists of • Divisional Railway Manager or his representative • Nagpur Metro Rail Corporation • Bharat Sanchar Nigam Limited / Post and Telegraph Department • National Highway Authority of India • State Public Works Department • MAHADISCOM - Maharashtra State Electricity Distribution Co. Ltd.

  18. Annexure A - Smart Solution Implementation Status -

  19. Annexure A - Smart Solution Implementation Status -

  20. Annexure A - Smart Solution Implementation Status -

  21. Annexure A - Smart Solution Implementation Status -

  22. Annexure A - Smart Solution Implementation Status -

  23. ADDITIONAL SLIDES

  24. Details of Utilization and Unspent Balance as on December 31, 2016

  25. Quarterly / Monthly Expenditure Plan for ABD ProjectsExpenditure plan for Town Planning Scheme for Retrofitting of the Areas of Pardi-Bharatwada-Punapur • Shall be submitted later in consultation with Directorate of Information Technology, Government of Maharashtra

  26. Quarterly / Monthly Expenditure Plan for Smart Solution ProjectsExpenditure plan for Implementation of ICT based Nagpur Smart City Solutions