STF421 ITS G5 Testing – An overview –

STF421 ITS G5 Testing – An overview –. CEN DSRC – ITS G5 Coexistence Workshop - . Presented by Friedbert Berens , in Ispra , Italy . Overview. Scope Members of STF421 Deliverables Status and planning. Scope of STF421.

pancho
Download Presentation

STF421 ITS G5 Testing – An overview –

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STF421 ITS G5 Testing – An overview – CEN DSRC – ITS G5 Coexistence Workshop - Presented by FriedbertBerens, in Ispra, Italy STF421 – An Overview -

  2. Overview • Scope • Members of STF421 • Deliverables • Status and planning STF421 overview

  3. Scope of STF421 • The STF421 develops a set of specifications for the certification test of the CEN DSRC - ITS G5 coexistence mechanisms and the ITS – G5 Dynamic Congestion Control (DCC) mechanisms. STF421 overview

  4. Resources of STF421 • 220 Person Days from 01.06.2011 to 30.6.2012 • STF 421 Member: • Paul Alexander (not on photo) • Friedbert Berens (STF Leader) • Madalina Tepelmann • Peter Schmitting • Dieter Smely • With support from the ETSI CTI (Sebastian Müller) • Photo with Christoph Wöste (TC ITS WG4 Chairman) STF421 overview

  5. Schedule and planning of STF421 • Initial interims report to EC: • 30. September • Ready for ETSI 1. September • Stable draft of coexistence deliverables until Q4/2011 • Early draft of DCC deliverables until Q4/2011 • Final draft of deliverables for TC approval end Q1/2012 • Final report EC: • 30. June 2012 • Ready for ETSI approval in 1. June 2012 STF421 overview

  6. Milestones of STF421 2011 • Milestone A: ITSWG4#15 (21 June), ETSI • Progress Report #1 and first draft of DTS/ITS-0040022 (PICS), DTS/ITS-0040023 (TSS&TPs), DTS/ITS-0040024 (ATS). • Milestone B: 1st September 2011 • Interim Report to be approved by EC/EFTA.   • The Interim Report must be delivered by the STF Leader to the ETSI Secretariat before 1st September 2011. The deadline for delivery to EC/EFTA by the ETSI Secretariat is 30 September; EC/EFTA approval is expected mid-November • Milestone C: ITS#9, ETSI (October 2011) • Progress Report #2 and stable drafts of DTS/ITS-0040022, 023, 025 • First drafts of DTS/ITS-0040025 (PICS), DTS/ITS-0040026 (TSS&TPs), DTS/ITS-0040027 (ATS) STF421 overview

  7. Status of STF421 • Preparatory meeting: 17. February 2011 in Sophia Antipolis • First Technical Meeting 31.5. and 1.6.2011 • Milestone A achieved 21.06.2011 • Activities is dependent on initial work in STF420 and ITSWG4 Coexistence AdHoc group STF421 overview

  8. Deliverables • 1. Coexistence of cooperative ITS G5 with RTTT DSRC • DTS/ITS-0040022 (PICS) • DTS/ITS-0040023 (TSS&TPs) • DTS/ITS-0040024 (ATS) • 2. Channel congestion control algorithms operating in the 5.9GHz range • DTS/ITS-0040025 (PICS) • DTS/ITS-0040026 (TSS&TPs) • DTS/ITS-0040027 (ATS) STF421 overview

  9. Document schedule 1. Phase • DTS/ITS-0040022 (PICS): DSRC/G5 Radio Test • TS 102 916 – 1 • First version early draft: 21.June • Stable draft: October 2011 • DTS/ITS-0040023 (TSS & TPs) : DSRC/G5 Radio Test • TS 102 916 – 2 • First version early draft: 21. June • Stable draft: October 2011 • DTS/ITS-0040024 (ATS) : DSRC/G5 Radio Test • TS 102 916 -3 • First version early draft: 21. June • Stable draft: October 2011 STF421 overview

  10. Document schedule 1. Phase • DTS/ITS-0040025 (PICS): G5 Radio Test • TS 102 917 – 1 • First version early draft: October 2011 • Stable draft: Q1/2012 • DTS/ITS-0040026 (TSS & TPs): G5 Radio Test • TS 102 917 – 2 • First version early draft: October 2011 • Stable draft: Q1/2012 • DTS/ITS-0040027 (ATS): G5 Radio Test • TS 102 917 -3 • First version early draft: October 2011 • Stable draft: Q1/2012 STF421 overview

  11. End Comments and Inputs Thank you for your attention For more Information friedbert.berens@me.com STF421: overview