US LHC Accelerator Project Completion Jim Kerby

US LHC ACCELERATOR PROJECT. brookhaven - fermilab - berkeley. US LHC Accelerator Project Completion Jim Kerby. 19 March 2007. US-LHC Accelerator Project. Complete…beyond design ’stuff’ on the dock included… 27 Inner Triplet Quad Assemblies 8 DFBX 20 Steering Dipoles 8 TAN / TAS

posy
Download Presentation

US LHC Accelerator Project Completion Jim Kerby

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. US LHC ACCELERATOR PROJECT brookhaven - fermilab - berkeley US LHC Accelerator Project CompletionJim Kerby 19 March 2007

  2. US-LHC Accelerator Project • Complete…beyond design ’stuff’ on the dock included… • 27 Inner Triplet Quad Assemblies • 8 DFBX • 20 Steering Dipoles • 8 TAN / TAS • Several thousand cable qualification tests “It ain’t over ‘til it’s over…” J. Kerby - US LHC Accelerator Project

  3. Sector 7-8 Cooldownhttp://lhc.web.cern.ch/lhc/ J. Kerby - US LHC Accelerator Project

  4. Sector 7-8 Cooldown Prep • January 07 • 7-8 Cooldown started • November 06 • Final warm electrical and mechanical tests of 7-8 • 9AM 25 Nov 06 • phone call from Peter Limon on problem in inner triplet region • Boroscope view of interior of corrugation in 7-8 • Piece extracted from 7-8 in December J. Kerby - US LHC Accelerator Project

  5. Inner Triplet Heat Exchanger • IP1/5 secondaries at nominal luminosity deposit ~200W in 30m of Inner Triplet in LHC • -energy deposition models of optics, aperture, liners 1995-1999 • Static heat load per assembly on order of 2W • -much higher than typ of cold iron magnet • Inner triplet has three magnet designs of sizable diameter in cryostats, integration an issue • moved external of cold mass J. Kerby - US LHC Accelerator Project

  6. Inner Triplet Heat Exchanger J. Kerby - US LHC Accelerator Project

  7. Corrugation & End Fittings • Tests Dec 06 @FNAL and CERN show failure mode systematic • -Heat affected zone of ~25cm next at each end of assembly (10 locations per triplet, 5pcs) • Failure mode is due to out of roundness of corrugation and yield of copper at the tight radius • -0.25mm on ~90mm diameter • -HAZ lowers yield by 3+ • Tests Dec 06/Jan07 @FNAL & CERN confirm outside HAZ corrugation OK to 37-39bar J. Kerby - US LHC Accelerator Project

  8. Fix • Start of 07 plan has two paths • a) Procure new, thicker corrugation, w/ ends • -appears to only 1 potential vendor, Nexans (Germany, purchased Kabelmetal) • -timescale is ~4 months, too late for 4-5 • b) Procure threaded inserts • -more difficult for tunnel logistics • -OK for tests, cycle tests also showed no degradation • In late January Nexans says they have a window starting 29 Jan / 5 Feb (as opposed to 4 months) if they can get copper • -iterations w/ Nexans/CERN on thickness • -found vendor in Rhode Island, visited, air shipped1-2 Feb • -corrugation run; tested (84 bar external); first delivery to CERN 5 Mar; installed in 5L 15 Mar (morning); remainder arrives this week & next J. Kerby - US LHC Accelerator Project

  9. Upcoming Schedule / Comments • This has not been the only problem in sector 7-8 • CERN has great capacity at this point to react • CERN staff have been terrific • FNAL staff, vendors have done a great job • Sector 4-5 triplet pressure test 24 March • 4-5 Global pressure test 7 Apr • 4-5 Cooldown starts ~end April (vacuum check, scrubbing, cooldown…) • Sector 8-1 to follow • The triplets will be included J. Kerby - US LHC Accelerator Project

  10. Timeline • January 98 tests are run to prove the design under external pressure, OK including end fitting to 33bar (no failure). • -industrial corrugation, end pieces from FNAL shops, assembly FNAL • A full scale HXTU is constructed (98-99) and assembled in SM18 in 2000 to prove the design—passes safety & performance checks • -same corrugation, end pieces vendor1, assembly at vendor1 • Prototype magnet is constructed and tested (00-01) • -same corrugation, end pieces (final design) vendor2, assembly FNAL • -safety & magnet performance tests OK (MTF relief at 7bar) • Production magnets are constructed and tested (order late 01/early 02) • -same corrugation, end pieces vendor3, assembly vendor3 • -safety & magnet performance tests OK (MTF relief at 7bar) • Warm fit up full inner triplet at CERN Spring 05 • -pressure test deferred due to schedule • -tunnel schedule also changed w/ QRL J. Kerby - US LHC Accelerator Project