An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HOOVER DAM By Project Monsters Presenters: Nazimah Abdul Rahim Hakki Isik

  2. HOOVER DAM • Concrete dam in Black Canyon, on the border between Arizona and Nevada • Named after Herbert Hoover, who played an important role in its construction • Built by Six-Companies, Inc. • Operated by Bureau of Reclamation of the US Dept. of the Interior • Lake Mead is the reservoir constructed behind the dam

  3. The Need for a Dam • Turbulent Colorado River periodically flood vast areas of California and Arizona • The flood destroyed canals built for irrigation and drinkable water • Herbert Hoover proposed construction of the high dam to solve the problems

  4. Who is Herbert Hoover? • Was Secretary of Commerce under President Coolidge • Graduated from Stanford University • A successful mining engineer, humanitarian • Elected as the 31st President of the United States

  5. Questions That Were Raised • What would be the location of the dam? • Who would build the dam? • How would the dam going to be financed? • Which states would get the water and electricity?

  6. Scope • Construction of the high dam would control the periodic floods, store water for irrigation, municipal and industrial use • The customers would be the people getting water, electricity from the dam

  7. Resources • 5200 workers on the construction with 3 shifts/day • 5 millions barrel of cement used in the concrete • 9,000 tons of structured steel components • 44,000 tons of large steel pipe and fittings • Giant cooling towers

  8. Time Management • Hoover met with the 7 state governors (AZ,CA,CO,NV,NM,UT,WO) to work out suitable arrangement for their states’ use • November 1922, Colorado River Compact was signed • In 1928, the Congress passed the Boulder Canyon Act, allocating $175 million for the dam construction

  9. Time Management • Composite bid was accepted for $50 mil by Six Companies in March 6 1931 • Construction began in April 20 1931 • June 1931, sufficient housing facilities were in place • Construction was completed in March 1, 1936 • The construction was completed 2 years ahead of schedule

  10. Cost Management • The most difficult part of the project – period of Great Depression • It cost a total of $165 million - $49 million to build the Hoover Dam • Unskilled labor paid $4/day and minimum wage cost was <$6/hr • Paid back over a period of 50 years to Federal Treasury by selling electricity

  11. Project Management • One of the biggest engineering project at that time - also the greatest testimony to functional organizations and old fashioned management control techniques • Active management was left in 4 hands: Henry J. Kaiser, Charles A. Shea, Felix Kahn and S.D. Bechtel

  12. Project Management

  13. Project Management • Frank Crowe (a.k.a Hurry Up) worked under Shea – acted as the man point between Board of Directors and the operations personnel • It was Shea’s responsibility to carry out the construction on time and budget • Each department was headed by a manager and held accountable for their work

  14. Project Management • Dam construction was divided into 3 areas: * Diversion tunnels and penstocks * Concrete arched structure * Power plant

  15. Problems • Workers’ strike (August 1931) – triggered by deaths of many of the workers’ wives and children due to extreme heat and lack of sanitation in the campsite area • Huge dam size required a lot of cement and engineers predicted it would take 125 years to dry and cure • Heat generated in the chemical rxns in the drying process would physically alter the landscape

  16. Solutions to the Problem • Housing facilities were built, known as Boulder City • Giant cooling tower/plant built to cool the entire dam – pumped ice water (37oF) at 1000 gal/min as the concrete was poured • With this approach, the dam was cooled in 20 months

  17. FAQs • Height : 726.4 ft • Weight: 6.6 million tons • Total storage capacity : 30.5 million acre ft • Power generating capacity: 2.8 million kW • Has 17 generators • Part of a system that provides water to over 25 million people in Southwest United States