1 / 20

Case 10-1 Integrating Activity-Based Costing and the Theory of Constraints

Case 10-1 Integrating Activity-Based Costing and the Theory of Constraints. Aftab Usmani Alex Derevin Carla Daniels Shantanu Singh. Shortfalls of ABC. Activity-Based Costing system is a powerful tool for strategic management.

quincy
Download Presentation

Case 10-1 Integrating Activity-Based Costing and the Theory of Constraints

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Case 10-1 Integrating Activity-Based Costing and the Theory of Constraints Aftab Usmani Alex Derevin Carla Daniels Shantanu Singh

  2. Shortfalls of ABC • Activity-Based Costing system is a powerful tool for strategic management. • However, ABC does not take into account that resources can be finite

  3. Enter Theory of Constraints • Theory of Constraints goes deeper than ABC by examining the SUPPLY of resources. • This is especially important when supply does not directly mirror firm’s changes in demand.

  4. “In-Case” vs. “As-Needed” • “As-Needed” contracts for acquisition of resources let the firm buy as it goes. • Resource will be supplied at the level it’s used by the firm. • Usage = Supply • Costs related to this input are variable • ABC Profitability Maps apply

  5. “In-Case” vs. “As-Needed” • “In-Case” basis contracts provide a certain amount of resource. • Supply at a certain level • Usage <= supply • Supply costs fixed until usage > supply • Costs rise by a fixed, contractually agreed-upon amount once capacity is reached.

  6. Managing Capacity Limits • Accept the limit and try to maximize revenue (and, thus, profit) given the constraint. • Must optimize around the bottlenecks • Change level of resource supply, and, therefore, the capacity limit

  7. Bottleneck • Regular ABC assumes that supply will change fluidly to meet demand. • Therefore, there are no bottlenecks in ABC • ABC doesn’t take into account products that take up a lot of bottleneck capacity, which can lead to poor decisions. • Maximum profits require bottlenecks to be optimally utilized.

  8. A Short Example of ToC

  9. What Would YOU make? • Highest per-unit (ABC) profit is $42 for Product A. However, as the obvious answer, it’s wrong.

  10. ToC Approach • Split resources into categories • Resources purchased on “as-needed” basis vary in cost directly with production. • Cost of resources purchased on “in-case” basis will be incurred irrespective of their usage. • Since these costs are always incurred, don’t consider them in analysis

  11. ToC Objective • Maximize “throughput” • “Throughput”: Revenues minus cost of “as-needed” resources. • Only cost subtracted is material. • On the surface, A has the highest “throughput” • However, it consumes twice as much of the “machining” resource. • In a given amount of time, firm can manufacture two units of product B or C instead of one A

  12. Per-Unit Throughput ABC and TOC agree!

  13. Not Quite!

  14. What Happened?! • If you look at Table 1, you will see that only resources USED are accounted for as costs • Fixed capacity paid for, but not used is not charged • Under TOC the costs of underutilized bottlenecks are charged to the products

  15. Bringing ABC and ToC together

  16. Long-Term Management • ToC accounts for bottlenecks present, and, therefore, performs better. • Drawback: Managing expenses over the long term. • Example: ABC shows product C only half as profitable as A and B. • Study indicates “Inspection” resource is dedicated to product C • Maybe C should be discontinued? • Avoid $50 inspection costs!

  17. Let’s Try it Out…

  18. Conclusion • ToC and ABC are complimentary techniques • Used together to identify short-term and long-term product mixes • ToC: Assumes cost structure is a given • Optimizes throughput for short-term profits • ABC: Supply of resources can be managed over long term. • Identifies long-term product mix

  19. Conclusion • ToC: Formal on-going special study designed to make ABC profitability maps more effective for one class of decisions • Decisions associated with short-term capacity use optimization

  20. Questions ?

More Related