Activities Status and Plan for the week

Activities Status and Plan for the week. D. Giugni / INFN Milano. Harnesses Stacking Status. Set 6 General : Set assigned to A34 Status All HV-NTC stack are done Set 7 General : Set assigned to A12 Status All HV Harnesses are “prepared” Set 8 General :

red
Download Presentation

Activities Status and Plan for the week

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Activities Status and Plan for the week D. Giugni / INFN Milano Monday Meeting 2011-02-27

  2. Harnesses Stacking Status • Set 6 • General : • Set assigned to A34 • Status • All HV-NTC stack are done • Set 7 • General : • Set assigned to A12 • Status • All HV Harnesses are “prepared” • Set 8 • General : • Set assigned to A56 • Status • All HV Harnesses are “prepared” • Set 9 • General : • Set assigned to A78 • Status • All HV Harnesses are “prepared” • Open Issues • Need to terminate with LEMO connectors IPS-3 and OPS-5. • Set 1 C34 (X0)Done (final test pending on OSP LV) • Set 2 No change since last week • General • Keep using set as Harnesses “replacement” • Status • All usable Harnesses “Prepared” and tested • Open Issues • Need several repairs. Not started yet • Set 3 No changes since last week • General • Set assigned to C12 • Status • Almost done: OSP LV need to be stacked • Set 4 No changes since last week • General • Set assigned to C78 • Status • Almost done: OSP LV to be STACKED • Set 5 No changes since last week • General • Set assigned to C56 • Status • Almost done: OSP LV to be STACKED

  3. Mechanics and parts for soldering • Stiffened and bonded PP0 boards • ISP C-side: All done • ISP A-Side: A34 (ready for final test on Tuesday morning) • OSP: None • Production rate driving factor: Boards availability • Corrugated panels: • ISP: 6 out of 16 delivered • OSP: None out of 16 • Production rate driving factor: SLA parts delivery We have parts available for 2 more ISP’s before next batch (expected this week!!!) Monday Meeting 2011-02-27

  4. Soldering Sequence, Status and Planning: ISP: 10 cal days OSP: 14 cal days • ISP C34 (X0) completed • ISP C12 (X1) completion: Tuesday 28/2 (tomorrow) HV soldering 20% completed • ISP C78 (X2) completion: This week: Th 1/3 PS soldering 80% • ISP C56 (X3) completion:Next week: Tu 6/3 PS soldering 10% • ISP A34 (X4) start when ISP C12 is completed (completion on Fr. 9/3) • ISP A12 (X5) start when ISP C78 is completed (completion on Mo 12/3) • ISP A56 (X6) start when ISP C56 is completed (completion on Fri. 16/3) • ISP A78 (X8) start when ISP A34 is completed (completion on Mo 19/3) Monday Meeting 2011-02-27

  5. Soldering [cont’ed] • OSP C34 start when ISP A12 is completed (completion on Mo. 26/3) • OSP A34 start when ISP A56 is completed (completion on Fr. 30/3) • OSP A12 start when ISP A78 is completed (completion on Mo. 2/4) • OSP A56 start when OSP C34 is completed (completion on Mo. 9/4) • OSP A78 start when OSP A34 is completed (completion on Fr. 13/4) • OPS C12 start when OSP A12 is completed (completion on Mo. 16/4) • OSP C56 start when OSP A56 is completed (completion on Mo. 23/4) • OSP C78 start when OSP A78 is completed (completion on Mo. 27/4) Monday Meeting 2011-02-27

  6. PP0 boards delivery dates Boards are assumed to be delivered “tested” and ready to go for bonding. These are the required delivery dates: • ISP C34, C12, C56, C78: All done • ISP A34 : done • ISP A12: today Monday 27/2 • ISP A56: Th 1/3 • ISP A78: Mo 5/3 • OSP C34 Mo 5/3 • OSP A34 Mo 12/3 • OSP A12 Mo 12/3 • OSP A56 Mo 19/3 • OSP A78 Mo 26/3 • OPS C12 Mo 26/3 • OSP C56 Mo 2/4 • OSP C78 Mo 9/4 Monday Meeting 2011-02-27

  7. Schedule for this week • Stacking • Full speed on the stacking: OPS LV 3, 4, 5, 6 (OPS LV 1 is done now) • Keep going stacking SET 7, 8 and 9. Note Set 9 needs to mount LEMO connectors • Corrugated panel bonding: Produce the other 2 ISP corrugated panel with the remnant SLA parts. New (full SLA set will be available this week!!)  keep going with all the ISP’s • BackBone Not at high priority this week. It will restart when Valery is back next week • PP0 boards stiffening and Alu Block bonding • Continue to bond the rest of the ISP A side boards. • Soldering • Finish up ISP C12  Load A34 • Finish up ISP C78  Load A12 • Continue soldering on ISP C56 • Post Soldering Assembly Final Assembly Trial (X-1) • No activities this week Monday Meeting 2011-02-27