1 / 11

WMS Report To TAC

WMS Report To TAC. February 2008. In Brief . One Working Group Report One Task Force Report Five Staff reports Other WMS action. Working Group Reports DSWG. Affirm Mary Anne Brelinsky as Chairman Lehman Brothers (REP/QSE) Affirm Nelson Nease as Co-Vice Chair

ritenour
Download Presentation

WMS Report To TAC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WMS Report To TAC February 2008

  2. In Brief • One Working Group Report • One Task Force Report • Five Staff reports • Other WMS action

  3. Working Group ReportsDSWG • Affirm Mary Anne Brelinsky as Chairman • Lehman Brothers (REP/QSE) • Affirm Nelson Nease as Co-Vice Chair • Nucor Steel (Industrial User) • Affirm Timothy Carter as Co-Vice Chair • Constellation New Energy (REP/QSE)

  4. Working Group ReportsDSWG • Established goals for the year • Demand Response Task Force update • Negative LaaR bids in Nodal • Reviewed LaaR events

  5. Task Force ReportsVCTF • Met five times • Identified Goals and Deliverables • Drafted list of “Principles” • Identified Issues under each VC Principle • Segregated voting and consensus issues • Final report for WMS vote in March

  6. ERCOT Staff Reports • Resource Node location • Update on DC tie operation • Report on System Congestion • Structure of Nodal Reports • EILS results

  7. EILS • All RFPs/bids back on Jan. 8 • More MW bids than previous RFPs • Selection committee of • SMEs • multiple departments management • Sorted by Business Hours/Non-Business Hours • Sorted by price • No history of past performance • Considered $50M cost cap

  8. EILS • Seasonal aspects • Business vs. Non-business hours • Relative value compared to other AS • what signals sent to the market • PUC desire to stimulate demand response • Logical break points in price

  9. EILS • Three Selection Cmty recommendations • Review and agreement from Kent S. • Review and agreement from Officers • Per subsequent Market Notice: • 262 MW business hours @ $9.73 • 185 MW non-business hours @ $7.86

  10. Other WMS activity • Increase the CSC Shadow Price cap to $5,600/MW • Apply price administration to limit any negative zonal price to a minimum of ($1,000)/MWh

  11. WMS Report To TAC

More Related