1 / 17

Update on CTF3 installation and planning

Update on CTF3 installation and planning. L. Rinolfi. CTF3 layout. CLEX. TL2. Photo injector tests for PHIN. 30 GHz production (PETS line) and Test Stand for CLIC structures. TL1. CR = Combiner Ring (factor 4). DL = Delay Loop (factor 2). Injector with thermionic gun.

robbinsl
Download Presentation

Update on CTF3 installation and planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on CTF3 installation and planning L. Rinolfi L. Rinolfi

  2. CTF3 layout CLEX TL2 Photo injector tests for PHIN 30 GHz production (PETS line) and Test Stand for CLIC structures TL1 CR = Combiner Ring (factor 4) DL = Delay Loop (factor 2) Injector with thermionic gun Drive Beam Accelerator DL CR L. Rinolfi

  3. Conclusion of the 2nd meeting • Installation into the Injector, Drive Beam Linac, Delay Loop, Transfer Line TL1 and Combiner Ring => OK • Installation of the Transfer Line TL2 connected to the Combiner Ring for the end of June 2008 but: - Indian dipole magnets ? - Power supplies for dipolar correctors ? Magnetic measurements finished today Next slide • Installation into CLEX (Phase 0) will be finished for the end of June 2008 but: - Laser for CALIFES ? See K. Elsener talk - Strong request from CARE to finalize the test as deliverable for EU-FP6-JRA-PHIN Meeting with R. Aleksan (CARE coordinator) L. Rinolfi

  4. Power supplies for correctors Information provided by L. De Oliveira AB/PO to the TIC meeting yesterday 75 power supplies have been ordered (including spares) 67 power supplies should still be installed (due to delay from company) 12 power supplies should arrive at CERN next week Then batch of 20 power supplies should be delivered at CERN every 2 weeks => all power supplies at CERN ~ mid August 2008 All power supplies (TL2 and CLEX) operational for end of August 2008 L. Rinolfi

  5. Klystrons RF deflectors in CR RF deflector in CLEX PHIN RF gun in CTF2 Photo-injector RF deflectors 2 RF deflectors LIPS Combiner Ring MKL 02 MKS 03 MKS 11 MKS 05 MKS 07 MKS 12 MKS 13 MKS 14 MKS 15 MKS 02 MKS 06 50 Hz 50 Hz 50 Hz 50 Hz 10 Hz 50 Hz 50 Hz 10 Hz 50 Hz 50 Hz 50 Hz 20 MW 40 MW 40 MW 30 MW 30 MW 30 MW 30 MW 30 MW 30 MW 30 MW 40 MW 3 GHz 1.5 GHz 3 GHz 3 GHz 3 GHz 3 GHz 3 GHz 3 GHz 3 GHz 3 GHz 3 GHz SHB1 SHB2 LIPS LIPS LIPS BOC SHB3 BOC LIPS LIPS BOC Gun A12 A13 A14 A17 A18 A1 A2 A3 A4 A5 A6 A7 A8 A9 A10 A11 B1 PB2 TDS SICA TWT 02 TWT 03 TWT 01 40 kW 1.5 GHz BW 200 MHz 1 RF deflector CTF2 1 RF deflector Delay Loop L. Rinolfi CLEX

  6. Combiner Ring Beam current V- BPM H- BPM RF deflectors CR. HDS 0150 & CR.HDS 1050 In order to cure the vertical instabilities, two new (3 GHz) RF deflectors (in Al) have been designed by LNF (Frascati) and are under construction. L. Rinolfi

  7. RF deflectors Information provided yesterday by A. Ghigo / LNF All cells are ready to be assembled All feedthrough are expected end of June at Frascati Low level RF tests in July at Frascati Trieste is in shut-down with all klystrons until October 2008 => No RF power tests in Trieste (same as PSI) RF power tests to be planned at CERN Installation into the Combiner Ring => 2 weeks shut-down in October L. Rinolfi

  8. Transfer Line TL2 SLV 0255 KHC 0250 Collimator Tail Clipper 2008/2009 shut-down October 2008 ? Magnets Dipoles (Horizontal) 5 Dipoles (Vertical) 2 Quadrupoles 27 Sextupoles 4 Correctors 12 Instrumentation BPM 6 WCM 1 BPI 6 MTV 1 BPR 1 Vacuum VPI 9 VVS 2 QDD 0820 QFD 0840 BHG 0800 Combiner Ring QFL 0770 QDL 0750 QFL 0730 XLC 0720 XLA 0670 XLA 0630 QFL 0680 XLC 0580 QDL 0650 e- QFL 0570 QFL 0620 QDL 0550 QFL 0530 QFL 0450 BHH 0600 BHH 0700 QDL 0470 BVB 0400 QDL 0430 BHG 0500 BVA 0300 SHC 0120 SHD 0110 QFH 0350 QDH 0370 QFL 0270 QDH 0330 QDL 0280 QFH 0180 QDG 0160 QFG 0140 QFH 0210 QFH 0230 QDH 0220 BHH 0200 CLEX L. Rinolfi

  9. CTF3 - DL - CR - TL2 Schedule https://edms.cern.ch/document/862088/ L. Rinolfi

  10. CTF3 - DL - CR - TL2 Schedule L. Rinolfi

  11. CLEX Layout Drive Beam e- Test Beam Line (TBL) decelerator e- Two-Beam Test Stand (TBTS) e- Probe beam e- Space reserved for Instrumentation Test Beam line (ITB) TL2 RF gun TL2 ' CALIFES Space reserved for 16 PETS L. Rinolfi

  12. CLEX status • 1) TL2, TL2' • Installation of dumps • Alignment finished yesterday • Some vacuum chambers remains to be installed • 2) CALIFES => see F. Peauger talk • RF gun with water leak => See K. Elsener talk • Alignment done • RF wave guides still foreseen to be at CERN next week 3) TBL => see S. Doebert talk L. Rinolfi

  13. TBTS End of June R. Ruber Foreseen in October 2008 Foreseen in 2009 L. Rinolfi

  14. CTF3 - CLEX Schedule 2008 L. Rinolfi

  15. Work into CTF2 RF gun for PHIN A single klystron MKS 14 shared with RF reflectors into the Combiner Ring and the RF deflector of CALIFES Courtesy K. Elsener MKS 14 klystron would be used to test the 2 new Al RF deflectors coming from LNF before connecting wave guides to the PHIN RF gun ? ? L. Rinolfi

  16. CTF3 - CTF2 Schedule 2008 L. Rinolfi

  17. Conclusion • Installation of the Transfer Line TL2 will be finished and connected to the Combiner Ring for the 7 July 2008 without the Tail Clipper. • Installation into CLEX (Phase 0) will be finished for the 14 July 2008 • CALIFES RF gun ? Laser energy ? • Delay on correctors power supplies. • Installation into CTF2 (for PHIN) will depend upon the CALIFES RF gun and RF wave guides. • Tests of RF deflectors ? • Tests with beam foreseen for October 2008. • Holidays period !!! L. Rinolfi

More Related