An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EIV Update April 2014

  2. EIV Reports • Previously the focus of reviewing EIV Reports was on the Income Discrepancy Report and the Deceased Tenant Report. • HQs EIV staff has changed their review • - No Income Discrepancy Report Monthly Review • - No Reviewing ALLDeceased Tenants on Report

  3. EIV Analysis Sheet • New Report HQs will be reviewing and making available for Field Offices • Includes both Public Housing units and Vouchers • Allows Field Office to update EIV staff on information that is not current in PIC.

  4. Procedure • The list will be generated every month with new high selection PHAs – Discrepancies are rated Low, Medium and High. • The list will be updated weekly based on Field Office and EIV staff updates.

  5. EIV Analysis Reports • In reviewing Deceased Tenant reports • Only Deceased Tenants that have been on the Report for longer than 3 months will be considered a discrepancy in this analysis, but doesn’t mean PHAs shouldn’t follow up on all deceased tenants in report. • The Income Discrepancy Report will not be used as an indictor in this analysis until a more accurate report can be created: • The time difference between recertification and the NDNH data causes a high percentage of false positives. • Identity theft causes a smaller percentage but some large dollar amount false positives.

  6. EIV Staff Actions • EIV staff will perform an analysis of a PHA before sending an email using the EIV and PIC system to determine: • Present status of EIV discrepancies • Possible reasons for the discrepancies • Possible solutions • EIV staff will send an email to the PHA email addresses listed in PIC. • The PIH Network Director and Field Office will be cc’d. • The email will be customized to that PHA’s specific discrepancies. • EIV staff will assist the PHA in eliminating the discrepancies. • The EIV staff will log each contact with the PHA and results of that contact.

  7. Common Problems • No EIV Access or Use • Small PHA whose actions are performed by a user ID not tied to the PHA. (consortium or consolidation) • New user needs to be assigned • EIV system error. (we need the user ID that is using EIV system) • Overdue Recertifications • Tenants that have moved out but no EOP 50058 was submitted. • Late Reexams • PHA staffing issue • SSA Identity Failure • 50058 data entry error of SSN, DOB or Surname • Maiden name – married name mismatch • Deceased Tenants • 50058 EOP needs to be submitted • PHA undergoing litigation with remaining non-qualified resident.

  8. EIV System Discrepancy Delay