1 / 29

PASEO CARIBE

ARCHITECTURAL ENGINEERING THE PENNSYLVANIA STATE UNIVERISITY THESIS PROJECT. PASEO CARIBE CONDOMINIUM TOWER & PARKING. Coupled Shear Wall Systems in High Seismic Zones. PASEO CARIBE. CONDOMINIUM TOWER & PARKING. N. American Plate. Caribbean Plate. S. American Plate. BACKGROUND. LOCATION

shenita
Download Presentation

PASEO CARIBE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ARCHITECTURAL ENGINEERING THE PENNSYLVANIA STATE UNIVERISITY THESIS PROJECT PASEO CARIBECONDOMINIUM TOWER & PARKING Coupled Shear Wall Systems in High Seismic Zones PASEO CARIBE CONDOMINIUM TOWER & PARKING

  2. N. American Plate Caribbean Plate S. American Plate BACKGROUND • LOCATION • San Juan, Puerto Rico • Bordered by the Caribbean & South American Plates • UBC 1997 • Seismic Zone 3 INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  3. BACKGROUND • Project Overview • IV Phase Development Project INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION • Project Overview • Parking Garage: Phase II • 10 stories, 1700 parking spaces • Condominium Tower: Phase III • Add. 14 stories • 4 – 3,500 ft2 aparts / floor

  4. EXISTING STRUCTURE • Gravity System • Cast-in-Place Bearing Wall • 9” Post-Tensioned Flat Slab • 36 – 12” Walls: 620 LF / Floor • Typical Open Span: 17’ E-W • Lateral System • Bearing Walls act as Shear Walls • Very Stiff 10’ x 160’ Core • 4 Elevator Shafts • 3 Sets of Stairs INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  5. PROBLEM STATEMENT INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION • Lateral Discontinuity • Transition of Occupancy at 8th Floor • Vertical Irregularity: UBC Table 16L • Type 1: Soft Story – Transfer Girders • Type 2: Weight Mass – Doubled Slab Area • Type 3: Vertical Geometry > 1.3L • Type 4: In plane Discontinuity

  6. PROBLEM STATEMENT • Multiple Lateral Discontinuities • Large Self Weight = 92,000k • Low R Bearing Wall Value = 4.5 VERY LARGE SEISMIC FORCES V = 8400 KIPS INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  7. PROBLEM STATEMENT • Non-Structural Issues • In plan, no open space > 22’ E-W • Material and Labor Intensive Design • Concrete: 11200 cy • Formwork: 520,000 ft2 • Rebar: 560 tons INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  8. DESIGN GOALS • Efficient Lateral System: • Reduce No. Lateral Elements to 4 in each direction • Limit No. Irregularities • Has a Predictable and Clean Failure Mechanism • Does not interfere with the Architecture & Assigned Use of Space INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  9. KEY ELELEMENTS • Reduce Vase Shear: • Use a frame gravity system with a higher R: 5.5 • Reduce the Weight with a lighter Steel Frame • Improved Capacity: • Higher f’c = 5ksi • Thicker 24” walls • Diagonally Reinforced Coupled Walls • Higher T to increase participation of coupled beam • Limit discontinuity and use symmetry to keep a low ρ factor INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  10. FRAME SYSTEM • Method • Take advantage of the Existing 27’x30’ Parking Grid • Requirements • Existing Height w/ 9” P/T Slab: 230 ft • UBC Overall Height Restriction: 240 ft • Clear Story Height Required: 9 ft • Max Story Height Increase: 8 in INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  11. FRAME SYSTEM • Results – Apartments INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION • Spacing: 7.5’ • Max Span: 27’ • Apartments: W10 x 26 Corridor: W14 x 30 • ∆Hstory = 5” • ∆Htotal = 70”

  12. FRAME SYSTEM • Results – Parking Garage INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION CIRCULATION

  13. A6 15’ FRAME SYSTEM • Results – Transition Level, 8th INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION W40x183 Girder

  14. FRAME SYSTEM • Results – Connection INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  15. COUPLED WALLS • Proposed Layout • Method • Direct Shear – ETABS • Axial Dead & Live – RAM • Steel System W = 62,000 kips • 25% Reduction • Torsion • Eccentric Loading • Accidental Torsion, Ax = 2 • Load Combinations • ρ = 1.1 • Ca = 0.33 • 0.8D + 1.2E (Load Case 1) • 1.48D + 1.2E + 0.55L (Load Case 2) INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  16. COUPLED WALLS • ETABS MODEL INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  17. COUPLED WALLS • Summary Results INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  18. COUPLED WALLS • Coupled Beams • CR Ratio = 27% • Results • Details • Vertical: #4@6” • Horizontal: #6@9” • Diagonal Ties: #4@4” INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  19. COUPLED WALLS • Flexure ФMn • 1st Level • L = 33 ft • B.Z: 39 #11 • Web: #10@9” • ФMn = 146337 ft-k > 144233 ft-k INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  20. COUPLED WALLS • Flexure, ФMn • Cut-Off Requirements – 0.8*L • Vertical Reinforcement INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION ∆ = 12.8 ft ∆ = 12.8ft

  21. COUPLED WALLS • Ductility & Plastic Hinge Development INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION Virtual Work ∆ Preferred Plastic Hinge at Base: Minimize Impact on Non-Structural Systems Θ1 < θ9 θ9 θ1

  22. COUPLED WALLS • Minimum Shear and Magnified Shear Demand INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  23. COUPLED WALLS • Boundary Zones • Requirements • Length Ties: #5@6” INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  24. COUPLED WALLS • Final Design INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  25. COMMODITIES • Architecture • Saved 160 ft2 / Floor • Flexible and Open Plan for: • Architect • Owner • Future Tenants • Larger Open Areas of up to 50’ INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  26. COMMODITIES • Acoustics • Vibrations INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION Living Areas: W10X15 TO W10X26

  27. CONSTRUCTION • U.S Cost • $1,000,000 Savings • Formwork  450,000 sfca • Rebar Placement  100 tons • Puerto Rico • $400,000 Deficit • Concrete Labor Market  12% • Finishes & Partitions  323% INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  28. CONCLUSION • Current design reflects the labor practices and situation of the country • Designers applied the best and most economical design to a complicated structure • Coupled wall systems proved to be an effective resisting system, allowed for increased floor area and architectural freedom • Reduced the amount of material and labor required for the project • Overall: Good design when the resources are available INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

  29. THANK YOU INTRODUCTION BACKGROUND EXISTING STRUCTURE PROBLEM STATEMENT DESIGN GOALS KEY ELEMENTS FRAME SYSTEM COUPLED WALLS COMMODITIES CONSTRUCTION&COST CONCLUSION

More Related