An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Texas Meat PackersHenderson Transition Plan September 2, 2008

  2. Employee Communication • Communicate to employees changes • Start-up of TMP-FW – Sept 8th • Transfer of chicken production • Keep beef production at TMP-H • There is a growth plan for TMP-H • Add additional products • Direct mail business • Retail store • Employment opportunities with TMP-FW • Conduct an employee meeting at TMP-H Friday, 9/5 • Meet with individual employee the following week

  3. Employee Review • TMP-H has a total of 35 (+/- 5) full time employees • Action: Lew to confirm and provide list – due 9/5 • Employee assessment • Action: Lew to provide an individual employee evaluation and recommendation – due 9/5 • Transfer opportunity to Ft. Worth • Action: Lew to provide a list of employees interested in possible transfer to TMP-FW – due 9/5

  4. Manning for Henderson • Develop manning requirements following transitioning • Transfer all chicken to TMP-FW • IQF capabilities fully functional Oct 15th • Beef processing to remain at TMP-H • Inside/Outside skirts • New business Brinker Int’l Flap meat fajita (Volume estimated at 12K per month) • Interim manning during transition • All beef • 4004 IQF • Thaw unit to support both TMP-H and TMP-FW • Actions: • Lew to provide transition manning for 1st shift/2nd shift Sept 8th - Oct 17th – due 9/5 • Lew to evaluate the possibilities of two 4/8 hour shifts in the interim – due 9/15 • Lew to provide manning for one shift (4/10’s or 5/8’s) – effective Oct 20th – due 9/5

  5. Products, Ingredients, Packaging • Transfer production of chicken items • Items – based on last three months • 08,110,123999, 38018, 48904, 5780, 5839, 5926, 7500, 7599, 7846, 7894, 9008, 9110, 9400, 9404, 9406, 9408, 9409, 9412 • Exclusive of 4004, 9410 and 7850 • Targets • Transfer 75% w/in first 30 days • Transfer 100% w/in first 60 days • Provide ingredient par values and inventory trigger levels • Provide box, film, bags, liner par values and inventory trigger levels • Pallets and spacer

  6. Equipment • Indentify equipment to be transferred • Sorter – date ____ • Carruthers – date ____ • One chamber vacuum machine – date ____ • Transfer conveyors – date ____ • Brine mixer – date ____ • Whizard knives (two) – date ____ • Scales – numbers and date ____ • Carts/Lugs/Gondolas – numbers and date ____ • Equipment in question • USA splitter • Required for Brinker Flap meat • TMP-FW has a skinner/splitter that needs to be tested for capabilities • Action: • John and Lew to provide numbers and dates – 9/5 • John to test the capabilities of the skinner splitter the week of 9/15

  7. Contracts • Review all long terms contracts for TMP-H to ensure no liabilities with transition • Cintas • Praxair • Kaiser • Stone-Smurfit • First Choice • Other • Action: • Paul and Lew to evaluate – Paul to report 9/5

  8. Notification • WARN Act notice not required • No need for public announcement or PR in Henderson • USDA • Action: Lew 9/19 • First Choice • Action: Paul 9/19 • Services • Action: Lew 9/19

  9. TMP-Henderson Proforma Provide a forecast proforma for TMP-H based on transitions plans, shift re-allocation and manning Action: Cliff, due 9/11

  10. Check List Employee communication Employee evaluation and requirement Product, ingredients and packaging Equipment transfer Notification Services Proforma Implementation

  11. Other considerations • Unemployment benefits if any full time TMP-H workers are affected • Action: Paul to evaluate – due 9/5 • Retail store management • Actions: Cliff to make recommendations – due 9/12 • Direct mail management • Actions: Cliff to make recommendations – due 9/12 • Asset inventory in Henderson • Actions: Lew to provide – due 9/30