1 / 38

SP 7106-87 TH 169 Redefine Informational Meeting July 25, 2019

Join us for an informational meeting about the TH 169 Redefine project. Learn about project details, goals, and the CMGC RFP process. Get all the information you need to pursue contracting opportunities on this project.

sjenny
Download Presentation

SP 7106-87 TH 169 Redefine Informational Meeting July 25, 2019

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SP 7106-87 TH 169 Redefine Informational MeetingJuly 25, 2019 TH 169 Redefine Project

  2. Outline • Introductions • Disclaimers • Project Information • CMGC RFP • CMGC Processes • Questions TH 169 Redefine Project

  3. Introductions • MnDOT Project Manager: Darren Nelson • MnDOT Construction Project Manager: Tony Hughes • MnDOT CMGC Program Manager: Kevin Hagness • Our job is to ensure all proposers have the same information and to partner with the successful CMGC team and consultants. TH 169 Redefine Project

  4. Disclaimers • This presentation will be posted on-line at: http://www.dot.state.mn.us/const/tools/const-manager-general-contractor.html TH 169 Redefine Project

  5. Disclaimers What is discussed today is informational only, meant to assist proposers in pursuit of contracting opportunities on this project. The ultimate RFP requirements are included in the final posted documents. Proposers are responsible for following the final RFP(s) If there are any discrepancies, submit a clarification request. TH 169 Redefine Project

  6. Project History, Overview, and Goals • Project was proposed jointly by the City of Elk River and Sherburne County during the January 2018 Corridors of Commerce (CoC) solicitation period – rated #1 project among the 172 projects nominated • Project will improve safety and mobility by removing five signalized intersections on TH 169 in Elk River • TH 10/169/101 Interchange left turning movements, Main Street, School Street, 193rd Avenue, 197th Avenue • Cost Estimate at time of proposal was $177 M • Total Project Cost Awarded was $157 M (CoC) + $3 M District Funds for Bridge Replacement = $160 M TH 169 Redefine Project

  7. Project History, Overview, and Goals • The Project Team is tasked with minimizing footprint and maximizing savings and efficiencies • Original Layout and Environmental Document were developed back in the 2010-2013 timeframe. A new layout is currently being developed and an Early Notification Memo will be issued to “dust off” the original Document. • Project will be delivered utilizing CMGC in an effort to help evaluate constructability, maintenance of traffic, and provide earlier cost certainty TH 169 Redefine Project

  8. Project History, Overview, and Goals • SUE contract is in place and work has commenced • Several Additional Consultant Contracts to be issued in the future • Independent Cost Estimator (ICE) and Engineer’s Estimator (EE) • Final Roadway and Final Bridge Plans (on board Spring 2020) • Tentative Construction Bid Opening of March 2022 • Construction start in Fall 2022 • Construction completion in Fall 2024 TH 169 Redefine Project

  9. Project Overview TH 169 Redefine Project

  10. Remove left turning movements at TH 10 ramp heads and place dedicated left turn lanes on TH 10 to TH 169Replace NB TH 169 Bridge over TH 10Provide aux lanes between TH 10 ramps and Main Street TH 169 Redefine Project

  11. Remove signal controlled at-grade intersection and provide grade-separated SPUI at Main StreetProvide aux lanes between Main Street and School Street TH 169 Redefine Project

  12. Remove signal controlled at-grade intersection and provide grade-separated SPUI at School StreetProvide aux lanes between School Street and 193rd Ave TH 169 Redefine Project

  13. Remove signal controlled at-grade intersection and provide grade-separated SPUI at 193rdProvide aux lanes between 193rd and 197th Ave TH 169 Redefine Project

  14. Remove signal controlled at-grade intersection and provide a standard diamond interchange at 197th*Alternate design being looked at is a split-diamond between 193rd and 197th avenue to minimize footprint TH 169 Redefine Project

  15. Project Challenges • Maintenance of Traffic and Constructability • TH 169 grade will be dropped significantly to provide grade separation required for interchanges • Base assumption is to maintain at least one lane of traffic in each direction on TH 169 throughout construction • Must maintain east-west local movements across TH 169 • Major Utility Impacts and coordination • Must stay under the Total Project Cost of $160 M (construction, engineering, R/W, etc.) • Build a professional and collaborative project team among the owner, designer, and contractor using the CMGC delivery method TH 169 Redefine Project

  16. CMGC RFP TH 169 Redefine Project

  17. CMGC RFP • Final CMGC RFP is currently advertised on MnDOT’s Consultant Services website: http://www.dot.state.mn.us/consult/notices.html • Thank you to those who submitted comments on the Draft CMGC RFP TH 169 Redefine Project

  18. CMGC RFP • RFP Details: • One-Step Qualifications-Based Selection Process • Interviews • No Stipends • No TGB or Veteran-Owned Goal for CMGC Preconstruction Services Contract • TGB and Veteran-Owned Goals anticipated for CMGC Construction Services Contract(s) TH 169 Redefine Project

  19. CMGC RFP A notification to Proposers has been posted on MnDOT’s Consultant Services website to help Proposers identify what changed between the draft CMGC RFP and the final CMGC RFP. In the event of any discrepancies between this document and the final CMGC RFP, the final CMGC RFP shall take precedent. TH 169 Redefine Project

  20. CMGC RFP • Noteworthy changes from ‘Draft’ CMGC RFP • Section 1.3 – Updated to provide a little more information regarding the project. • Sections 1.6 & 1.8 – Total project funding is capped at $160 million. • Sections 2 & 5.5.1 – Proposal Due Date extended to October 8, 2019 and the interview date is now November 6, 2019. • Section 4.3 – Page limit increased to 20 pages. • Section 4.5 – Number of hardcopies has been reduced to 12. • Section 6.2 – The construction services fee, represented as a fixed markup percentage, has been increased to 12%. 20

  21. CMGC Draft RFP Comments Work Packages Question: Since federal funds are not being utilized for this project, can the “independent utility” and “severable” conditions be deleted for work packages? On this project, it may be advantageous to use work packages that do not meet one or both of these conditions. Answer: Regardless of the funding source, MnDOT believes these conditions are appropriate for work packages. Therefore, no changes were made.

  22. CMGC Draft RFP Comments Construction Services Fee Question: We request the fixed-markup percentage be increased from 11.0 to 12.5 percent to appropriately address the scope and complexity of the project and current market conditions. Answer: Per MnDOT’s CMGC procurement process, an analysis is performed to determine a fair and reasonable construction services fee (profit and home office overhead), represented as a fixed-markup percentage, to specify in the CMGC RFP. At the time the ‘Draft’ CMGC RFP was advertised, the analysis was not complete. The CM/GC RFP has now been updated to reflect the results of that analysis. The fixed-markup percentage is now 12.0 percent. 22

  23. CMGC Draft RFP Comments Total Project Cost Estimate Question: With an estimated total project cost of $177 million, why do the Project Goals identify a $157 million budget. Answer: The funding for the 2018 Corridors of Commerce program was capped at an amount that was lower than the estimated total project costs. This was based on the belief there were opportunities to reduce cost for each project. One of the reasons CMGC was selected for the TH 169 Redefine Project is because it provides earlier cost certainty in the project development, thus better enabling MnDOT to scope the project to the fixed budget.

  24. CMGC RFP Communications Darren Nelson, Project Manager, is the sole MnDOT contact person for clarification requests, communications about the project, the RFP, and Proposal submittals. Email: Darren.Nelson@state.mn.us TH 169 Redefine Project 24

  25. CMGC RFP Communications CMGC programmatic questions shall be directed to Kevin Hagness, CMGC Program Manager: Email: Kevin.Hagness@state.mn.us TH 169 Redefine Project 25

  26. CMGC RFP • Proposal Delivery, Content, Format • Proposals shall not exceed 20 pages; not including cover letter, table of contents, section dividers, appendices, and required forms • Resumes for Key Personnel shall not exceed two pages per position • 2-11x17 pages allowed for Project Experience Table TH 169 Redefine Project 26

  27. CMGC RFP Addendums and Clarifications Proposers need to acknowledge all addendums and clarifications issued in their Proposals. RFP Clarification Request Forms can be found on MnDOT’s CMGC website: http://www.dot.state.mn.us/const/tools/const-manager-general-contractor.html TH 169 Redefine Project 27

  28. CMGC RFP • Mandatory Technical Interviews • Approximately one hour in length • No handouts or formal presentations • Will consist of set questions for all Proposers and clarification questions for each Proposer based on their Proposal • Will not be scored separately – will be used as additional information in support of, and to clarify, the information contained in the proposal • Questions will not be provided to Proposers in advance of the interview • Up to five representatives from Proposer’s team – must include PM, CM, and Lead Cost Estimator • Proposers must email CMGC PM to schedule an interview time • Interviews will take place at MnDOT’s District Three Office in St. Cloud, MN TH 169 Redefine Project 28

  29. CMGC RFP CMGC Estimating Process Formal workshops for design review, risk, and cost estimating are anticipated to occur at the 30%, 60%, and 90% design milestones. For each of these milestones, the cost estimates will include an Independent Cost Estimate (ICE), Owner’s/Engineer’s Estimate and the CMGC’s Opinion of Probable Construction Cost (OPCC). TH 169 Redefine Project 29

  30. CMGC RFP CMGC Price Proposal Validation The Independent Cost Estimate (ICE) and Engineer’s Estimate (EE) will be used by MnDOT to validate the CMGC Contractor’s price proposal/bid. TH 169 Redefine Project 30

  31. CMGC RFP MnDOT CMGC Processes & CMGC Conflict of Interest Policy Further information available on MnDOT’s CMGC website: http://www.dot.state.mn.us/const/tools/const-manager-general-contractor.html TH 169 Redefine Project 31

  32. ICE/EE Procurements There will be one RFP advertised for two separate contracts for the ICE and the Owner’s/Engineer’s Estimating services. TH 169 Redefine Project

  33. ICE/EE Procurements • Scope of work for both contracts is very similar • production-based, contractor-style estimates at each of the design milestones and at the price proposal/bid • schedule analysis and development at each of the design milestones and at the price proposal/bid TH 169 Redefine Project 33

  34. ICE/EE Procurements • Desired Skills • production-based, contractor-style estimating for projects of similar size, scope and complexity • schedule analysis and development for projects of similar size, scope and complexity • Relevant CMGC experience and an understanding of the CMGC process TH 169 Redefine Project 34

  35. ICE/EE Procurements Responder’s submission of a proposal is acknowledgement that Responder may be assigned, at MnDOT’s discretion, the ICE or the EE services contract. TH 169 Redefine Project

  36. ICE/EE Procurements • Procurements Schedule • RFP scheduled to be advertised fall 2019 • 4-week advertisement planned • ICE and EE under contract soon after the CMGC Contractor TH 169 Redefine Project 36

  37. CMGC/ICE/EE Procurements Continue to watch the MnDOT Consultant Services website for procurement updates, clarifications, and addendums: http://www.dot.state.mn.us/consult/notices.html TH 169 Redefine Project 37

  38. Thank you! Darren Nelson, Project Manager Darren.Nelson@state.mn.us TH 169 Redefine Project

More Related