An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Welcome to Tonight’s  Louisiana DOTD  Public Information Open House

  2. Multimedia Presentation

  3. Initial Strategy (1 of 2) U.S. 90 from South of Ambassador Caffery Parkway to North of the BNSF Railway overpass

  4. Initial Strategy (2 of 2) U.S. 90 from the BNSF Railway overpass to North of Albertson Parkway

  5. Refinement of Initial Strategy (1 of 2) U.S. 90 from North of Ambassador Caffery Parkway to North of the BNSF Railway overpass

  6. Refinement of Initial Strategy (2 of 2) U.S. 90 from North of the BNSF Railway overpass to North of Albertson Parkway

  7. Advantages of Refined Strategy • Increases capacity. • Delivers transportation safety and mobility benefits. • Accommodates current and future commercial development. • Reduces negative impacts for drivers and adjacent properties. • Minimizes construction costs.

  8. Phase One of Construction (1 of 2) U.S. 90 from North of Ambassador Caffery Parkway to North of the BNSF Railway overpass

  9. Phase One of Construction (2 of 2) U.S. 90 from North of the BNSF Railway overpass to North of Albertson Parkway .

  10. Phase One Features • Widens U.S. 90 from four to six lanes. • Elevates U.S. 90 travel lanes above Albertson’s Parkway. • Replaces/widens bridges over BNSF Railway. • Constructs new North and Southbound service roads. • Eliminates J-Turns. • Optimizes access to adjacent properties.

  11. Design/Construction Timeline • Design activities begin in February 2014. • Construction work begins in mid-2014. • Estimated completion in mid-2017. • Access to private properties will be maintained • throughout the construction effort.  • Routine lane closures will be limited to off-peak travel times.

  12. For More Information Ms. Peggy Jo Paine, P.E. DOTD Construction Project Manager 1201 Capitol Access Road Baton Rouge, LA 70802 E-mail: DBI-49South@LA.gov Writtencomments may be submitted tonight using the form available at the welcome station.