DOE Review of the LCLS Project

DOE Review of the LCLS Project. LCLS Project Management M. Reichanadter / SLAC. Outline. PM Overview Costs, Obligations and Funding Schedule (Critical Path + Milestones) Project Staffing Procurements Project Performance Plans for next six months Summary

Download Presentation

DOE Review of the LCLS Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DOE Review of the LCLS Project LCLS Project Management M. Reichanadter / SLAC

  2. Outline • PM Overview • Costs, Obligations and Funding • Schedule (Critical Path + Milestones) • Project Staffing • Procurements • Project Performance • Plans for next six months • Summary • C & S Response to Recommendations

  3. Project Management Focus Create an ISMS organization Clarify roles/responsibilities, add key ES&H staff, ISMS plan, processes/procedures. Advance the Design Staffing Ramp-up, Technical/QA Specs, A/E Title I/II Procurements and procurement staffing/support Staffing in place, pushing out LL and Key procurements Risk identification (continuous over the life cycle) Risk Registry & Contingency allocation Conv Fac, Controls, XTOD, Undulators, Funding CR’s Configuration control. LCLS P3/COBRA database is the approved work plan. “Plan the work … Work the plan”. BCR’s used to changes to the “plan”. Tracking cost and schedule performance and contingency allocation. Preparation for construction (CD-3b) CM/GC RFP, ISMS, CSP CD-3B Approve Start of Construction – Scheduled (Feb06)

  4. Preparation for this Review • Website has all review relevant information; • http://www-ssrl.slac.stanford.edu/lcls/doe_reviews/2005-05/ • CD’s, hardcopy binders for plenary talks and system-specific documentation are also available. • Project Documentation; • L1, L2 and L3 Milestones & Dictionary – Contains milestone dates and start/completion description. • PEP, PMP – updated to reflect new cost, schedule and organization. • Schedules – broken out according to WBS, logically-driven work with sufficient float to meet CD-4. • CTG – Cost To Go + Contingency assessment on remaining work. • Detailed Cost Estimate – Cost estimate for Oct04 and beyond down to the resource level, fully burdened and escalated. More detailed than the CTG. • RMP and Registry – Identifies known risks to the LCLS and provides risk handling plans. • Responses to Recommendations – Aug04 and Nov04 DOE Reviews • March 2005 Monthly Report – Includes management and technical progress/issues, CPR, milestones, BCR Log. • WBS Dictionary - WBS organization and scope description.

  5. LCLS Total Project Cost (Mar05) Cost & Schedule Baseline ----------------- $315M TEC $379M TPC CD-4 Mar09 ------------------ TEC emphasis/yr FY05 – LLP’s, Staffing, PED, T2 & CM/GC FY06 – Inj, Lin, Und Proc’s & Int. Test, T3 FY07 – Linac, Und Assm, XTOD/XES Proc, 2-D Det, T3 FY08 – T3 BO’s, XTOD/XES Proc, May08 First Light FY09 – CD-4 Mar09 OPC emphasis/yr FY07-09 – expand 2.1 for comm/start-up & power. ~33.3% contingency on work remaining $5M MR to provide management agility in ‘endgame’.

  6. WBS Organization • LCLS is organized into fully integrated (design through commissioning) decoupled systems. • Decoupling allows each system to go as fast as technically possible. • Supports a phased installation & commissioning plan Management & Integration Product-based Components I&A – Components into subsystems Physics Commissioning • Controls is embedded in technical systems. • Improves controls / hardware interface. • Configuration management is easier. • Needs good coordination between Controls Manager and System/WBS Manager.

  7. LCLS Cum OBL, BCWS, BA (AY$) • BCWS & OBL optimized to funding profile and project milestones. • Phase fund multi-year contractor and construction contracts. • Adequate cont/year is retained to problem solve. • With good performance, we will exploit opportunities with “swing” procurements.

  8. Contingency Assessment @ L2 (Mar05) • Contingency on Remaining Work (33.3%), ~in line with contingency assessment, but; • LCLS will need to maintain good performance against baseline plan and watch scope creep. • Will know more after Jan-Feb ’06 with the CF bids.

  9. LCLS Summary Schedule – Mar05 • Schedule • Highlights • Schedule Float • 216 days (10.5 mos.) • ~27% cont wrt CD-4 • Critical Path • Und B.O. - Und Inst to 1st Light • Near CP LTU - B.O./Inst • FY05 Shutdown • ~1 month • FY06 shutdown • ~ 4 months • FFTB Shutdown • July 2006. LCLS may request advancing this date but need to optimize detailed construction plans.

  10. LCLS L1 and L2 Milestones • 7 L1 DOE-SC1 Milestones • 28 L2 DOE-SSO Milestones • 134 L3 LCLS PO Milestones • L1-L2-L3 under CC thresholds & progress is reported in the LCLS MR • Additional L4’s tracked by System Managers

  11. LCLS Project Organization (Mar05) Excellent support from SLAC HR • Increase senior level expertise • Acc Team Ldr • Construction & ES&H Safety Professionals • Dedicated Procurement Group • E-Beam and X-Ray Systems Managers strengthen line management & provide better integration. • Laser Group Manager

  12. Actual Reported Staffing @ SLAC Additional contract staff; A/E (Jacobs) PMCS – AIM (5) Procure Grp (4) Consultants L. R. Dalesio E. Desaulniers CM/GC More as needed • SLAC can (and is) redeploying its resources as needed to support the LCLS. • LCLS adding staff as quickly as the project can assimilate. ~ on schedule. • CR impact: • Increased project cost (Interim A/E) • Less time for assimilation of new staff • Upcoming Hires (CF expertise, IT/RDB Mgr’s) 72.4 FTE’s (Mar05) FY05 funding @ SLAC Treading water. Year-long CR or full-funding? Award Title I

  13. FY05 Matrix SupportESD-LCLS & RF-LCLS MOU’s • LCLS Controls and RF Managers are members of LCLS Division and co-located in B280. • ESD matrix ~7.0 FTE’s in FY05 to LCLS. LCLS still plans 2 EE hires. • KD matrix ~3.0 FTE’s in FY05 to LCLS + mfg & RF Gun Support. • Metrology (Draft) • CEH MOU (TBD) • Accel Dept (TBD)

  14. LCLS FTE Estimates (Mar05) • LCLS resource estimate is derived from resource-loaded schedule. • LCLS Division @ SLAC • Adding key staff via; • Outside hires (Laser, Proc) • Formal transfers from other SLAC divisions (ES&H, ATL, QA, CF) • Contracts (Constr ES&H, Controls) • Matrix Staffing @ SLAC • Controls-MOU • RF-MOU • Metrology-draft MOU • CEF-planned MOU annualized

  15. LCLS Facilities @ SLAC B750 LCLS temporary staging/storage, permanent lab, testing and machine shop space. Share with other users, LSS?, EXO? Remove Mark II Detector? B280 A&B 2 floors, ~80 offices ~13,000sf S20-2,160sf facility Laser & Control Rm MMF-4,000sf facility used to tune, measure and store undulator magnets • LCLS CDG (co-located) in B280. Centrally located on the SLAC campus to enhance communication with Lab and DOE functions (Dir, BS, Engr, SSRL, DOE-SSO). • Lab space in B750 is opening up for staging and testing.

  16. LCLS Procured Materials and Services • LCLS uses decentralized three procurement groups at ANL, LLNL and SLAC • ANL – J. Ingraffia • LLNL – G. Otani • SLAC – D. McGiven • Manages all LCLS procurements using SLAC-LCLS Procurement Group • $2M Authority • Closely coordinates activities with SLAC Purchasing for less critical or commodity purchases • Two major procurements require prior DOE approval Phase fund GC, Und Assembly and PMCS ~$60M CM/GC requires DOE approval ~$12M undulator assembly requires DOE approval

  17. SLAC-LCLS Procurement Organization • Dedicated Procurement Cell (co-located with CDG) • LCLS Procurement Manager (D. McGiven) • Reporting to project on technical/procurement matters. Administratively to BIS AD. • Uses SLAC’s approved processes and procedures. • Signature Authority $2M • Technical Lead (B. Freeman, V. Villanueva) • Conv. Fac. Lead (Patten) • Administrative Aide (TBD) • Additional expert advice on ‘project-focused’ procurement activities. • Procurement Consultant • G. Desaulniers (APS, TJ-Lab) • Regular interaction with successful project-driven procurement groups. • (ORNL-SNS, LBL-MF, LLNL-NIF) • Training on writing SOW’s, specifications, acquisition planning and general contract management. • Dan Jacobs – Federal Market Group scheduled for June 6-10, 2005. • LCLS Procurement Team; • Provides procurement schedule and timeline • Signs off and executes APP’s • Participates as a member of Evaluation Board for all major procurement awards.

  18. LCLS Key Procurements • Key LCLS procurements are well underway. • APP kicks off the procurement process. • LLP’s technical specs have been reviewed during LCLS TDR’s. • Laser and CF procurements are most critical to maintaining schedule.

  19. CM/GC Procurement Package • Modeled after a proven and successful procurement; • All documentation previously approved by DOE. • CM/GC model is being used for the LBL-MF. • High-quality CM/GC bidders have expressed interest. • CM/GC package vetted by internal and external experts, however it’s a large and complex package. Biggest procurement (~$60M) by far; • Must get it right before it goes up to Chicago & HQ. • Revise APP, Reformat RFP TOC and condense attachments from 25 to 5. • RFP documents to be checked by a technical writer. • Established a Proc/Legal review team to review T’s & C’s. • Meet with DOE-SSO with draft prior to formal resubmission. • Experienced advisory committee assembled and ready to advise internal evaluation committee. • CM Workaround; • Bring on an interim CM service at the 30% T2 point (~mid-June to end of Sep) • Conduct constructability reviews, construction management, value engineering, independent cost & schedule estimates to work with Jacobs. • Provides full CM coverage to the A/E from 30% T2 as originally planned. • Anticipate no cost/schedule impact, but need smooth transition to CM/GC.

  20. LCLS is under Configuration Control • Management Control • Project Management Plan • with Appendices • Advance Procurement Mgmt Plan • Quality Implementation Plan • Risk Management Plan • with Risk Registry Appendix • Technical/Scope Control • Technical Specifications Documents • GRD, PRDs, ESDs, RDSs, ICDs • WBS Dictionary • Cost/Schedule/Resource Control • P3/COBRA Cost & Schedule Database • With Baseline Change Requests • L1-L2-L3 Milestones & Dictionary • All LCLS Project documentation is available via the LCLS website

  21. LCLS Monthly Report - 21 months reporting • Technical Highlights • Issues and Assessments • Earned-Value Performance • Milestone Performance • Change Control Log

  22. Contingency Performance and Allocation Hold contingency/ETC ~30-35% A/E T2 CR, Interim support ~$500K CT consolidation, Staff additions Treading water. Year-long CR or full-funding? Performance: LCLS is earning value, Cont/ETC ~ constant, but it’s early. Sparse data on EV performance. No “divergent” trends. Allocation: Contingency allocation modest to date. ~ No scope added. No “divergent” trends.

  23. Plans for the Next Six Months • Advance the Design • Complete staffing and co-location of Central Design Group at 3 labs. • Continue to push ISMS into LCLS work processes. • Continue to define requirements, specifications, and interfaces via QA documentation. • Complete Title II on schedule (Nov30) • Put in place interim CM – maximize overlap between A/E T2 and CM. • Procurements and procurement staffing • Procurement staffing and organization in place • Laser, Injector components, Undulator Materials, S20 and MMF all well advanced. • CM/GC RFP up through DOE approval process, award CM/GC Sep30. • Preparations for Construction (CD-3b) Construction start is March 2006! • LCLS ISMS established, add ES&H staff to PO • Establish LCLS Construction Safety Plan • Making safety a ‘pre-condition’ of LCLS work. • SLAC ES&H and SOC on approval and review processes. • S20 and MMF construction projects. • Provide good feedback on processes and policies prior to main construction effort. • Start construction March 2006! • Watch contingency usage and maintain good cost and schedule control. • Make plans flexible for full FY06 funding (~$89M) or CR?

  24. Summary • LCLS is at CD-2b (Performance baseline approved). • Configuration control in place. • TEC = $315M, TPC = $379M, Mar09 CD-4. • Contingencies cost (~33%) and schedule (~27%) are adequate. • Critical and near critical paths are identified. • Staffing ramp-up is proceeding according to plan. • Management team strengthened. • SLAC staff shifting into LCLS. • Procurement staff is in place. • LLP and key procurements well advanced. • CM/GC is being given the highest procurement priority. • Preparing to bring on interim CM talent. • LCLS preparing for CD-3B and start of construction.