1 / 36

An introduction to Project Cycle Management PCM

An introduction to Project Cycle Management PCM. Welcome + agenda Learning to know each other Locations of facilities (rooms) Role of trainer + participants Leonardo-Socrates examples/tasks Three parts Introduction to PCM - 30 min Logical Framework - 150 min

tracen
Download Presentation

An introduction to Project Cycle Management PCM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. An introductionto Project Cycle ManagementPCM Ton FARLA - ERI-SEE workshop

  2. Welcome + agenda Learning to know each other Locations of facilities (rooms) Role of trainer + participants Leonardo-Socrates examples/tasks Three parts Introduction to PCM - 30 min Logical Framework - 150 min Your work and PCM - 30 min Ton FARLA - ERI-SEE workshop

  3. Objectives Understand PCM as a tool for project planning, implementation and evaluation Perform a stakeholder/problem analysis Develop a problem/objective tree Define project elements, test the logic Prepare a draft Log frame matrix Relate PCM to your future/daily work Ton FARLA - ERI-SEE workshop

  4. Introduction EU Action programmes/projects Project management - features Expectations project manager Changing roles of managers See figure next slide Ton FARLA - ERI-SEE workshop

  5. Ton FARLA - ERI-SEE workshop

  6. Exercise 1: Introduction • Your management perspective • See hand-out - questionnaire • 5 minutes - individually • 10 minutes - plenary Ton FARLA - ERI-SEE workshop

  7. Introducing PCM – what it means • PCM describes management activities and • decision making procedures used during • the life time of a project. • (tasks, roles, responsibility, key doc’s, decision options) • The EC adopted PCM as its primary set of project design and management tool based upon the Logical Framework Approach. Ton FARLA - ERI-SEE workshop

  8. Key features of PCM – projects: • Support the EU policy objectives • Support the national strategies • Addresses relevant problems recipients • Have feasible, achievable objectives • Benefits are likely to be sustainable See figure next slide Ton FARLA - ERI-SEE workshop

  9. National & sector wise policies EC development policy & country strategies Governmentprogrammes Priorities and programmes of non-state actors Project Project Project Policies, programmes and projects Ton FARLA - ERI-SEE workshop

  10. PCM Requires: Active participation of key stakeholders Incorporation quality assessment (stage) Quality key doc’s for decision making Using the Logical Frame Work Ton FARLA - ERI-SEE workshop

  11. Project cycle Programming Evaluation Identification Financing decision Implementation Formulation Financing decision Ton FARLA - ERI-SEE workshop

  12. PCM - Three common principles • Decision making criteria defined at each phase • The phases in the cycle are progressive • Project identification part of structured feedback • LFW - Project management tool • Identification, analyse situation, investigate relevance and identify objectives and strategies; • Formulation, preparation project plan, objectives, measurable results, defined levels of management responsibility; • Implementation, support contracting, operational work planning and monitoring; and • Evaluation/audit, summary record of what was planned (objectives, indicators and key assumptions) Ton FARLA - ERI-SEE workshop

  13. Main stages of the log frame Ton FARLA - ERI-SEE workshop

  14. Whose views + experience are relevant? Who takes decisions about the project? Who will act on these decisions? Whose active support is essential who has a right to be involved? Who is likely to feel threatened See example next slide Step 1 The stakeholder analysis Ton FARLA - ERI-SEE workshop

  15. Example stakeholder analysis – setting up ITC Ton FARLA - ERI-SEE workshop

  16. Exercise 2 - stakeholder analysis • Identify general development problem/opportunity • Identify groups having an interest in the project; • Investigate their roles, interests, relative power and capacity to participate (strengths and weaknesses); • Identify the extent of cooperation or conflict in the relationships between stakeholders; and • Interpret the findings of the analysis and incorporate relevant information into project design. • Using the case of Socrates – hand-out • 30 minutes in small working groups • 15 minutes plenary Ton FARLA - ERI-SEE workshop

  17. Step 2 The problem analysis Problem analysis is an important part of the stakeholder workshop It involves two tasks: • Analysis of the identified problems faced by the stakeholders and • Development of a problem tree to establish causes and effects See example problem tree next slide Ton FARLA - ERI-SEE workshop

  18. An example of a problem tree Ton FARLA - ERI-SEE workshop

  19. Exercise 3 –Develop a problem tree • Agree on 1 focal problem paste it on the wall with 1 related problem (cause/effect) • If the problem is a cause it goes on the level below • If the problem is an effect it goes above • It is neither a cause nor an effect it goes on the same level • As the tree develops, remaining problems are attached in the same way. • Using the case of Socrates – hand-out • 30 minutes in small working groups • 15 minutes plenary Ton FARLA - ERI-SEE workshop

  20. Step 3 Objectives analysis • Analysis of objectives involves reformulation of problems into objectives. Objectives should be: • Realistic - achievable within given financial and physical resources, and the time-frame envisaged • Specific -so that any progress towards objective can be attributed to the project and not to some other cause • Measurable - at acceptable cost and acceptable effort, so project's performance can be measured Ton FARLA - ERI-SEE workshop

  21. An example of an Objective tree Ton FARLA - ERI-SEE workshop

  22. Exercise 4- develop an objective tree • Develop an objective tree using the results of the problem tree in exercise 3 • Positively mirroring the problem tree. • Using the case of Socrates – hand-out • 15 minutes in small working groups • 5 minutes plenary Ton FARLA - ERI-SEE workshop

  23. Step 4–Defining the intervention logic • Distinguish the LFA from the LFM (matrix) • LFA is a way of thinking, not a process of mechanical engineering • LFM is an analytical coherent project design • LFM is a stakeholder presentational tool. • LFM helps to make visible the logical relationships between activities, outcomes, specific objectives and overall objective Ton FARLA - ERI-SEE workshop

  24. Structure of the LFM – 4 columns, 4 rows The vertical logic identifies: • what the project intends to do, • clarifies the causal relationships and • Specifies the assumptions and uncertainties Ton FARLA - ERI-SEE workshop

  25. Structure of the LFM – 4 columns, 4 rows • The horizontal logic relates to: • the measurement of the effects of, • the resources used by, • the project, specification of key indicators • the means how measurement will be verified. Ton FARLA - ERI-SEE workshop

  26. Step 5-Specify assumptions + risks • External factors affect project implementation outside control • Conditions to be met if the project succeed • Mechanisms to deal with them or to monitor the effect • Once assumptions identified, state in terms of desired situation. Ton FARLA - ERI-SEE workshop

  27. Step 6-Specify the indicators • Define indicator - e.g. Educational degrees • Set quality - e.g. Nr of graduates in subject X • Set quantity - e.g. Nr graduates increased from 500-1000 • Set time -e.g. Nr graduates increased 500-1000 by 2007 Ton FARLA - ERI-SEE workshop

  28. Step 6 Specify the measurement • the format - e.g. progress reports, project records, statistics) • who - whoshould provide the information • how often - e.g. monthly, quarterly, annually etc. Ton FARLA - ERI-SEE workshop

  29. Step 7. Prepare activity schedule • List the main activities • Break activities down into manageable tasks • Determine activity sequence /dependencies • Estimate the start-up, duration and completion • Identify process indicators or milestones • Define expertise required to undertake activities • Allocate tasks among the project team Ton FARLA - ERI-SEE workshop

  30. Example -work breakdown activities Ton FARLA - ERI-SEE workshop

  31. Step 8 - Specifying the inputs Checklist for Preparing a Cost Schedule • List means required to undertake each activity • Put means into cost categories • Specify units, quantity and unit costs • Specify funding source • Allocate cost codes • Schedule costs • Estimate recurrent costs • Prepare cost summary tables Ton FARLA - ERI-SEE workshop

  32. Ton FARLA - ERI-SEE workshop

  33. Exercise 5 – Prepare a draft LFM • Start preparing the LFM using the results of the previous exercises and Socrates case • Process information by working vertically down the first column, once first column is sound, complete the fourth column • The second and third columns should then be completed. Next - find the activities to be carried in order to produce the outcomes. • List – for later discussion with your superiors and your absent colleague – 5-7 important project elements or assumptions that you feel are perhaps doubt full, if not wholly unjustified, unnecessary or even dangerous for the successful implementation of the project. • 45 minutes in small working groups • 20 minutes plenary Ton FARLA - ERI-SEE workshop

  34. Exercise 6 – PCM to your future work • List the strength • List the weakness Ton FARLA - ERI-SEE workshop

  35. Strength and weaknesses LFA The strength: • LFA encourages people to consider expectations and how to achieve the objectives • Checks internal logic of the plan ensuring activities, outcomes and objectives are linked. • It forces planners to identify critical assumptions /risks affecting project success, • Indicators of achievements/progress, planners think about how to monitor and evaluate Ton FARLA - ERI-SEE workshop

  36. Strength and weaknesses LFA • The weakness • Powerful tool; but not a comprehensive tool for either planning-management • Time consuming, requires a thorough understanding of logic and concept of LFA. • Problems can be compounded by too rigid application of the LF (changing environment) • LFA should be supported by technical, economic, social and environmental analysis Ton FARLA - ERI-SEE workshop

More Related