1 / 46

Network Planning Methods Example PERT & CPM

Network Planning Methods Example PERT & CPM. Terms Used in Project Management Activity : A certain amount of work or task required in the project

trisha
Download Presentation

Network Planning Methods Example PERT & CPM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Network Planning Methods Example PERT & CPM

  2. Terms Used in Project Management Activity : A certain amount of work or task required in the project Activity duration: In CPM the best estimate of time to complete an activity . In PERT the expected time or average time to complete an activity Critical activity : An activity that has no room for schedule slippages : if it slips the entire the entire project completion will slip. An activity with zero slack

  3. Critical path: The chain of critical activities for the project .The longest path through the network • Dummy activity :An activity that consumes no time but shows precedence among activities • Earliest finish (EF): The earliest that an activity can finish from the beginning of the project • Earliest start ( ES): The earliest that an activity can start from the beginning of the project

  4. Event :A beginning , a completion point ,or a milestone accomplishment within the project . An activity begins and ends with events • Latest finish (LF) : The latest that an activity can finish from the beginning of the project • Latest start (LS) :The latest that an activity can start from the beginning of the project • Most likely time ( t m) : The time for completing the activity that is is the consensus best estimate, used in PERT

  5. Optimistic Time (to): The time for completing an activity if all goes well : used in PERT • Pessimistic Time (tp): The time for completing an activity if bad luck is encountered : used in PERT • Predecessor activity : An activity that must occur before another activity . • Slack : The amount of time that an activity or group of activities can slip without causing a delay in the completion of the project • Successor activity : An activity that must occur after another activity

  6. Conventions used in drawing network diagrams (Arrows & Circles ) • Activity on Arrow (AOA) : The activities are denoted by Arrows and events are denoted by circles • Activity on Node(AON) : Activities are denoted by circles(or nodes) and the precedence relation ships between activities are indicated by arrows

  7. 3 Lay foundations Lay foundation Dummy Build house Build house Finish work 2 0 Finish work 1 2 4 7 6 5 3 3 1 1 2 4 6 7 3 3 2 1 1 1 1 3 1 Design house and obtain financing Order and receive materials Start 1 1 Select paint Select carpet 5 Design house and obtain financing Select carpet Order and receive materials Select paint AOA Project Network for House AON Project Network for House

  8. B A C A C B A C B A D B Dummy C D Situations in network diagram A must finish before either B or C can start both A and B must finish before C can start both A and C must finish before either of B or D can start A must finish before B can start both A and C must finish before D can start

  9. Forward Pass • Earliest Start Time (ES) • earliest time an activity can start • ES = maximum EF of immediate predecessors • Earliest finish time (EF) • earliest time an activity can finish • earliest start time plus activity time EF= ES + t Backward Pass • Latest Start Time (LS) Latest time an activity can start without delaying critical path time LS= LF - t • Latest finish time (LF) latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors

  10. CPM analysis • Draw the CPM network • Analyze the paths through the network • Determine the float for each activity • Compute the activity’s float float = LS - ES = LF - EF • Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project • Find the critical path is that the sequence of activities and events where there is no “slack” i.e.. Zero slack • Longest path through a network • Find the project duration is minimum project completion time

  11. PERT / CPMNetwork planning methods that generate: • Relationship between activities • Project duration • Critical path • Slack for non – critical activities • Crashing (cost / time trade-offs) • Resource usage

  12. St. Paul’s Hospital Immediate Activity Description Predecessor(s) A Select administrative and medical staff. B Select site and do site survey. C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview applicants and fill positions in nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the hospital. I Develop an information system. J Install the equipment. K Train nurses and support staff. — — A B B A C D A E,G,H F,I,J

  13. AON Network I A F K C G Start Finish D B H J E St. Paul’s Hospital Immediate Activity Description Predecessor(s) A Select administrative and medical staff. B Select site and do site survey. C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview applicants and fill positions in nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the hospital. I Develop an information system. J Install the equipment. K Train nurses and support staff. — — A B B A C D A E,G,H F,I,J

  14. Completion Time I 15 A 12 F 10 K 9 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Paul’s Hospital Immediate Activity Description Predecessor(s) A Select administrative and medical staff. B Select site and do site survey. C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview applicants and fill positions in nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the hospital. I Develop an information system. J Install the equipment. K Train nurses and support staff. — — A B B A C D A E,G,H F,I,J

  15. Path Expected Time (wks) A-I-K 36 A-F-K 31 A-C-G-J-K 70 B-D-H-J-K 72 B-E-J-K 46 Completion Time I 15 A 12 F 10 K 9 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Paul’s Hospital CriticalPath Immediate Activity Description Predecessor(s) A Select administrative and medical staff. B Select site and do site survey. C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview applicants and fill positions in nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the hospital. I Develop an information system. J Install the equipment. K Train nurses and support staff. — — A B B A C D A E,G,H F,I,J

  16. The longest path in the network • Defines the shortest time project can be completed • Critical path activity delay project delay Critical Path

  17. Activity Name ES EF LS LF Activity Duration Earliest Start and Earliest Finish • Begin at starting event and work forward • ES is earliest start • ES = 0 for starting activities • ES = Maximum EF of allpredecessors for non-starting activities • EF is earliest finish • EF = ES + Activity time

  18. Earliest Start / Earliest Finish I 15 F 10 A 12 K 9 C 10 G 35 Start Finish H 40 J 4 B 9 D 10 E 24

  19. Earliest Start / Earliest Finish I 15 12 27 Earliest finish time Earliest start time F 10 A 12 K 9 0 12 63 72 12 22 C 10 G 35 12 22 22 57 Start Finish Critical path H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 E 24 9 33

  20. Latest Start and Latest Finish • Begin at ending event and work backward • LF is latest finish • LF = Maximum EF for ending activities • LF = Minimum LS of all successors for non-ending activities • LS is latest start • LS = LF – Activity time Activity Name ES EF LS LF Activity Duration

  21. Latest Start / Latest Finish What do you notice about ES/LS & EF/LF? I 15 12 27 48 63 Latest start time Latest finish time F 10 A 12 K 9 0 12 63 72 12 22 63 72 53 63 2 14 C 10 G 35 12 22 22 57 Start Finish 24 59 14 24 Critical path H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59

  22. What do you notice about ES/LS & EF/LF? • For Activity A • ES = 0 • LS = 2 • Meaning: Due to some reason of if activity A is not started at 0 weeks but 1, 2 or 3 weeks, even then completion of project is not delayed • For Activity B • ES = 0 • LS = 0 • Meaning • Any delay in start would delay project completion.

  23. Activity Slack Analysis I 15 12 27 Slack = LS – ES or Slack = LF – EF 48 63 Latest start time Latest finish time F 10 A 12 K 9 0 12 63 72 12 22 63 72 53 63 2 14 C 10 G 35 12 22 22 57 Start Finish SlackK = 63 – 63 = 0 or SlackK = 72 – 72 = 0 24 59 14 24 Critical path H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59

  24. Activity Slack Analysis Node Duration ESLS Slack A 12 0 2 2 B 9 0 0 0 C 10 12 14 2 D 10 9 9 0 E 24 9 35 26 F 10 12 53 41 G 35 22 24 2 H 40 19 19 0 I 15 12 48 36 J 4 59 59 0 K 6 63 63 0 Activity slack = maximum delay time Critical path activities have zero slack I 15 12 27 48 63 Latest start time Latest finish time F 10 A 12 K 9 0 12 63 72 12 22 63 72 53 63 2 14 C 10 G 35 12 22 22 57 Start Finish 24 59 14 24 Critical path H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59

  25. A 5 0 5 0 5 C 15 5 20 10 25 B 20 D 10 25 35 5 25 Finish Start 25 35 5 25 Activity Slack How much would we like to reduce the time for activity B?

  26. tp + 4 tm + to 6 Mean (expected time): te = 2 tp - to 6 Variance: Vt =2 = PERT • PERT is based on the assumption that an activity’s duration follows a probability distribution instead of being a single value • Three time estimates are required to compute the parameters of an activity’s duration distribution: • pessimistic time (tp ) - the time the activity would take if things did not go well • most likely time (tm ) - the consensus best estimate of the activity’s duration • optimistic time (to ) - the time the activity would take if things did go well

  27. PERT analysis • Draw the network. • Analyze the paths through the network and find the critical path. • The length of the critical path is the mean of the project duration probability distribution which is assumed to be normal • The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum • Probability computations can now be made using the normal distribution table.

  28. x -  Z =  Probability computation Determine probability that project is completed within specified time where  = tp = project mean time  = project standard mean time x = (proposed ) specified time

  29. Probability Z  = tp x Time Normal Distribution of Project Time

  30. PERT Example Immed. Optimistic Most Likely Pessimistic ActivityPredec.Time (Hr.) Time (Hr.)Time (Hr.) A -- 4 6 8 B -- 1 4.5 5 C A 3 3 3 D A 4 5 6 E A 0.5 1 1.5 F B,C 3 4 5 G B,C 1 1.5 5 H E,F 5 6 7 I E,F 2 5 8 J D,H 2.5 2.75 4.5 K G,I 3 5 7

  31. PERT Example PERT Network D A E H J C B I K F G

  32. PERT Example ActivityExpected TimeVariance A 6 4/9 B 4 4/9 C 3 0 D 5 1/9 E 1 1/36 F 4 1/9 G 2 4/9 H 6 1/9 I 5 1 J 3 1/9 K 5 4/9

  33. PERT Example ActivityESEFLSLFSlack A 0 6 0 6 0 *critical B 0 4 5 9 5 C 6 9 6 9 0 * D 6 11 15 20 9 E 6 7 12 13 6 F 9 13 9 13 0 * G 9 11 16 18 7 H 13 19 14 20 1 I 13 18 13 18 0 * J 19 22 20 23 1 K 18 23 18 23 0 *

  34. PERT Example Vpath = VA + VC + VF + VI + VK = 4/9 + 0 + 1/9 + 1 + 4/9 = 2 path = 1.414 z = (24 - 23)/(24-23)/1.414 = .71 From the Standard Normal Distribution table: P(z < .71) = .5 + .2612 = .7612

  35. PROJECT COST

  36. Cost consideration in project • Project managers may have the option or requirement to crash the project, or accelerate the completion of the project. • This is accomplished by reducing the length of the critical path(s). • The length of the critical path is reduced by reducing the duration of the activities on the critical path. • If each activity requires the expenditure of an amount of money to reduce its duration by one unit of time, then the project manager selects the least cost critical activity, reduces it by one time unit, and traces that change through the remainder of the network. • When there is more than one critical path, each of the critical paths must be reduced. • If the length of the project needs to be reduced further, the process is repeated.

  37. Project Crashing • Crashing • reducing project time by expending additional resources • Reduction in activity duration by any change in its resources, resource use, method or material is referred to as crashing of the activity • Crash time • an amount of time an activity is reduced • Crash cost • cost of reducing activity time • Goal • reduce project duration at minimum cost

  38. Crash cost Crashing activity Activity cost Normal Activity Normal cost Normal time Crash time Activity time Activity crashing Slope = crash cost per unit time

  39. Min total cost = optimal project time Total project cost Indirect cost cost Direct cost time Time-Cost Relationship • Crashing costs increase as project duration decreases • Indirect costs increase as project duration increases • Reduce project length as long as crashing costs are less than indirect costs Time-Cost Tradeoff

  40. 1 2 4 3 5 6 7 12 8 12 4 4 4 4 Project Crashing example

  41. Time Cost data

  42. Project duration = 36 12 12 4 4 1 1 12 7 3 2 2 5 5 3 6 7 6 7 4 8 4 4 4 8 4 4 4 4 Project duration = 31 Additional cost = R2000 R400 From….. To…..

  43. GANTT CHART

  44. Gantt Chart Gantt Chart was developed by… • Henry Laurence Gantt (1861-1919) was a mechanical engineer and management consultant who is most famous for developing the ‘Gantt chart’ in the 1910s. These Gantt charts were employed on major infrastructure projects including the Hoover Dam and Interstate highway system. He refined production control and cost control techniques.

  45. Month 0 2 4 6 8 10 | | | | | Activity Design house and obtain financing Lay foundation Order and receive materials Build house Select paint Select carpet Finish work 1 3 5 7 9 Month Example of Gantt Chart

  46. Gantt ChartActivities in Buy a House

More Related