1 / 11

SFOBB West Approach Seismic Retrofit Contract Advertising & Award Process Overview

SFOBB West Approach Seismic Retrofit Contract Advertising & Award Process Overview. Presented by; Kris Kuhl & Phyllis Thompson July 18, 2002.

varsha
Download Presentation

SFOBB West Approach Seismic Retrofit Contract Advertising & Award Process Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SFOBB West Approach Seismic Retrofit Contract Advertising &Award Process Overview Presented by; Kris Kuhl & Phyllis Thompson July 18, 2002

  2. Provide you with information about Caltrans contract advertising and award process for the San Francisco/Oakland Bay Bridge West Approach Seismic Retrofit Project Answer your questions Purpose of this Presentation

  3. Our mission is to improve mobility across California The Office Engineer contributes to Caltrans mission by providing construction contracts that are: Complete, biddable and buildable Competitively bid Meeting legal requirements Open to all licensed contractors Caltrans Mission

  4. 3% Disabled Veterans Business Enterprise (DVBE) goal Project Goals

  5. Project Advertising to Award Timeframe Advertised Release Date 7/15/02 Advance Advertising 4 Weeks Prior to Releasing Bid Documents Distribute Bid Documents to Bidders (13 weeks) Open Bids 10/22/02 Award Process Award (30-60 days)

  6. Bids for this project will be opened and read in a public forum On Tuesday, October 22 at 2 PM in Sacramento in Room 100 at 1120 N Street Immediately Following Bid Opening: Bid amounts will be verified Preliminary bid results posted at (916) 654-5500 and on the Internet (http://www.dot.ca.gov/hq/esc/oe/bidsopened.html) Bid summaries will be mailed to all bidders Public Bid Opening

  7. Award Process • Due to project size, this project may take more than 30 days to award • Before awarding a contract, we verify: • Bid is responsive and complete • Bid security is provided and correct • All forms are complete and correct • Contractor is properly licensed • Verify Compliance with DVBE requirements • All protests addressed

  8. Escrow of Bid Documents Submitted by first Tuesday after Bid Opening See Special Provisions Other Requirements

  9. After Contract Award Contractor has 8 days to sign and return contract for Caltrans approval Executed Documents (returned) Contract signature page signed Payment and Performance bonds included & signed Signed/Approved by Caltrans Contract Execution & Approval

  10. Internet Services Provided • http://www.dot.ca.gov/hq/esc/oe/ • Information on Projects Released for Bid • Weekly Advertisements for Bids • Electronic copies of project plans & specifications • Bidder Assistance • Bid Opening and Award Information

  11. Conclusion • We thank you for your time and interest. • If you have any questions or suggestions, we would like to hear them We look forward to doing business with you soon!

More Related