An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LEARNING FROM INCIDENTS • Learning from incidents: • Arley collision between OTM’s ES PICOP Version 2*

  2. Target Audience: ES & PICOP competence holders Method of delivery: Line Manager or Sponsor to arrange for individuals to briefed Recording Process: Briefing to be added as an event on Sentinel* Timescales: To be completed for all ES and PICOP competence holders and registered on Sentinel* by the end of September 2013 * For Network Rail staff, the briefing is to be registered as a Competence event in Oracle

  3. Collision between on-track machines near Arley, Warwickshire, on 10 August 2012

  4. During the night of 09/10 August 2012 engineering work was taking place on the line that runs between Nuneaton and Birmingham. The work activities were coming to a close when, at about 04:20 hrs, an on-track machine (Stoneblower 80212) collided with a stationary on-track machine (Ballast Regulator DR77002) within the work site, on the down Arley line. Ballast Regulator DR77002

  5. There were four members of staff on the ballast regulator, and three on the stoneblower. One person was taken to hospital and released later in the day. Others with minor injuries were treated on site by paramedics. The collision caused the leading bogie of the stoneblower to derail and damage was caused to both machines. Stoneblower 80212

  6. Learning points When controlling an engineering train, OTM or OTP movement instruct the driver to make the movement at a speed where they can stop within the distance they can see the line ahead to be clear, regardless of the conditions. All movements within a possession or a worksite must be made at no more than 5mph unless the ES/PICOP and driver/operator have held a safety conversation where appropriate alternative speeds in the journey have been agreed and authorised by the ES/PICOP. Only the ES/PICOP can authorise appropriate alternative speeds, which should be appropriate for the conditions such as darkness, fog, gradients, low adhesion, curvature of the line or anything else that may affect the driver’s ability to stop short of any obstruction. The maximum permitted speed that can be authorised is 40mph.

  7. Want to know more about PICOP and ES duties? GE/RT8000/HB11, Duties of the person in charge of the possession (PICOP) GE/RT8000/HB12, Duties of the Engineering Supervisor (ES) V2* *Version 2 is an updated version of the original Arley briefing that takes into account changes that came into force in the December 2013 Rule Book update; specifically the removal of the need to instruct drivers to proceed ‘at caution’. As the message and intent of both versions of the briefing are the same, there is no need to re-brief individuals who received the original briefing on Version 2. Rule Book updates should already have been briefed out to relevant staff locally.