Plumas Lake Elementary School District ( 5 Year Plan )

Plumas Lake Elementary School District ( 5 Year Plan ). Rio Del Oro Riverside Meadows Cobblestone. Plumas Lake Elementary School District ( Maintenance Department ) Here’s the life cycle I use for our Deferred Maintenance plan, the “ industry standard “. Life cycles ( years )

Download Presentation

Plumas Lake Elementary School District ( 5 Year Plan )

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Plumas Lake Elementary School District( 5 Year Plan ) Rio Del Oro Riverside Meadows Cobblestone

  2. Plumas Lake Elementary School District ( Maintenance Department ) Here’s the life cycle I use for our Deferred Maintenance plan, the “ industry standard “. Life cycles ( years ) Paint Playgrounds 5 years Int. paint 5 years Ext. paint – Trim 5 years Seal coat – Blacktop 5 years Locks ( Keys ) 8 years Ext. painting 10 years Carpet 10 years VCT – Tile 15 years Clock / Intercom 15 years Security / Fire alarms 20 years Electrical 20 years HVAC 20 years Roofs 25 years Paving 25 years Main Plumbing 50 years Ray McKinney Director of F.M.O.T.

  3. Rio Del Oro ( 2012 – 2013 )Riverside Meadows ( 2013 – 2014 )Cobblestone ( 2014 – 2015 ) • Paint Outside Trim & Poles $ 7,600 • Paint Metal Doors $ 3,500 • Paint Portable Trim $ 1,000 • Paint Parking Lot Curb ( In – House ) • Paint Drinking Fountain Walls ( In – House ) • Paint Red Fire Poles ( In the works ) • Paint interior walls ( When Needed )

  4. Rio Del Oro ( 2013 – 2014 )Riverside Meadows ( 2014 – 2015 )Cobblestone ( 2015 – 2016 ) • Blacktop Sealcoat $ 15,000 • Paint Playground Stripes $ 5,000 • Paint Metal Fencing $ 1,000 • Paint Light poles $ 1,000 • Paint Lower Walls ( In – House ) • Paint Bus Curbs ( In – House )

  5. Rio Del Oro ( 2014 – 2015 )Riverside Meadows ( 2015 – 2016 )Cobblestone ( 2016 – 2017 ) • Paint Gutters & Downspouts $ 10,000 • Paint window seals $ 10,000 • Locks and Door Closers (Maintenance Budget) • And of course the up keep of grounds and maintenance.

  6. 2015 – 2016 Rio Del Oro hits the 10 year mark: This could mean we need over the next 3 years for each school: • Paint Exterior School Building $ 100,000 • Replace Carpet per room $ 3,000 • Paint Parking Lots (In–house) • Continue up keep with grounds and maintenance.

  7. Costs of Long Term Deferred Maintenance Plan

  8. Costs of Long Term Deferred Maintenance Plan

  9. Closing Statements&Questions & Answers