1 / 44

Mississippi Riverbank Project (Final Presentation) May 14, 1999

Mississippi Riverbank Project (Final Presentation) May 14, 1999. Architect: . . . . . . . . . . . . Steve GEORGALIS . . . . . . Georgia Institute of Technology Structural Engineer: . . . Tomo CEROVŠEK . . . . . . University of Ljubljana

Download Presentation

Mississippi Riverbank Project (Final Presentation) May 14, 1999

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mississippi Riverbank Project(Final Presentation)May 14, 1999 Architect: . . . . . . . . . . . . Steve GEORGALIS . . . . . . Georgia Institute of Technology Structural Engineer: . . . Tomo CEROVŠEK . . . . . . University of Ljubljana Construction Manager: . Jacky HO . . . . . . . . . . . . . . Stanford University Owner: . . . . . . . . . . . . . Ali AL-ALI . . . . . . . . . . . . .

  2. Agenda • Project Introduction • Four Preliminary Design Alternatives • Final Design - A / E / C Solutions and Interactions • Learning Experience

  3. Introduction • Building for Riverbank University in Sacramento • Virtual Project (Year 2010) • Produce 4 Alternatives and 1 Final Design • Practice A/E/C Interaction

  4. Requirements • Architectural Requirements • Maintain Footprint & Transportation / Circulation • Occupancy, Security, Environmental (3 stories, total height 35’) • Structural Requirements • Load: Earthquake and Total Height of 35’ • Construction Requirements • Budget : $5,500,000 (Structural $550,000) • Time Budget : 12 months (ready in May 2012)

  5. 4 Alternatives 1 2 3 4 $4,500,000 $4,900,000 $4,700,000 $4,100,000

  6. Building Site

  7. Alternative 1

  8. Alternative 1

  9. Alternative 2

  10. Alternative 2

  11. Alternative 3 3rd floor

  12. Alternative 3

  13. Alternative 4

  14. Reasons for choosing Alternative 2 • Owner’s Decision Aesthetic and Challenging Design • Team’s Preference Attracting Glass Atrium Challenging Structural Systems Feasible in Time and Cost

  15. Further Iterations and Evaluations A Meeting with Owner • Height Limit • Faculty Lounge • Atrium Design • Structural Materials Revised design Feedback on cost Revised design material choice Suggestions and changes E C Revised design Feedback on cost and constructibility

  16. Discussion on Faculty Lounge

  17. Discussion on Structural Materials • Prefab Steel Frame for Atrium • Cast-in-place Concrete Columns

  18. Final Design

  19. Final Design

  20. Architecture: 1st Floor

  21. Architecture: 2nd Floor

  22. Architecture: 3rd Floor

  23. Architecture: Section

  24. Architecture: Footage Evaluation

  25. Engineering: Structural Model

  26. Engineering: Structural Model

  27. Engineering: Loads • Live Loads: • Classrooms: 40 psf • Offices: 50 psf • Halls: 100 psf • Dead Loads: • Self weight, floor and partitions 30 psf • MEP 10 psf • Seismic Load: zone 3 (solid rock)

  28. Engineering:SAP2000 Model

  29. Engineering: Framing System

  30. Engineering: Moments of the Plate

  31. Engineering: Mode Shapes

  32. Engineering: Moment Diagram

  33. Typical members and connection • Beam spacing: 19’ • Typical column: 18’’x18’’ • Reinforcement: 3.5% • Typical beam: 16’’x20’’ • Foundations: 4’x4’

  34. Construction: Cost

  35. Construction: Cost Breakdown

  36. Construction: Cost Breakdown

  37. Construction: Schedule • Total Duration: 10 months • Milestone 1: Start of Concrete Superstructure • Milestone 2: Finish of Concrete Superstructure • Milestone 3: Finish of Glass Atrium

  38. Construction: Milestone 1 • June 20, 2011 • Completion of • Foundation and • Auditorium • Start Concrete • Frames

  39. Construction: Milestone 2 • Sept 20, 2011 • Completion of • Concrete Frame • Start Atrium

  40. Construction: Milestone 3 • Dec 10, 2011 • Completion of • Atrium • Continue Interior • Construction

  41. Construction: Site Layout

  42. Construction: Equipment Excavation • 90,000 CF of soil Excavator Dump truck Cast-in-place Concrete • 3,500 LF of Columns • and Beams Pumper Truck Concrete Mixer Atrium Steel Frame • Max height: 36 feet Crane Truck

  43. PUT A FINAL MODEL HERE FOR WRAP UP

  44. A C E A C E Learning from AEC • Roles of A / E / C • New communication technology • New team working environment • Using 3D Model

More Related