答案:. 1 . (1) 事件 1 1) 自有机械索赔要求不合理。因合同规定业主应按自有机械使用费的 60% 补偿。 2) 租赁机械索赔要求不合理。因合同规定租赁机械业主按租赁费补偿。 3) 现场管理费、企业管理费索赔要求不合理 , 因分项工程窝工没有造成全工地的停工。 4) 利润索赔要求不合理,因机械窝工并未造成利润的减少。. (2) 造价工程师核定的索赔费用为: 3720 元* 60 % =2232 元 (18000 — 300*12) 元 =14400 元 12000 元* 60 % =7200 元 (7200 — 140*12) 元 =5520 元

wyatt-witt
Download Presentation

答案:

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 答案: 1.(1)事件1 1)自有机械索赔要求不合理。因合同规定业主应按自有机械使用费的60%补偿。 2)租赁机械索赔要求不合理。因合同规定租赁机械业主按租赁费补偿。 3)现场管理费、企业管理费索赔要求不合理,因分项工程窝工没有造成全工地的停工。 4)利润索赔要求不合理,因机械窝工并未造成利润的减少。

  2. (2)造价工程师核定的索赔费用为: 3720元*60%=2232元 (18000—300*12)元=14400元 12000元*60%=7200元 (7200—140*12)元=5520元 2232元+14400元+7200元+5520元=29352元 2.(1)事件2: 1)可索赔额外增加的排水设施费。 2)可索赔额外增加的排水工作劳务费。 (2)核定的索赔费用应为:15900元+8650元=24550元

  3. 3.(1)事件3: 应同意40天工期延长,因地下文物处理是有经验的承包商不可预见的(或:地下文物处理是业主应承担的风险)。 (2)现场管理费应补偿额为: 1)现场管理费: [8600万÷(1.15*1.08*1.05)*O.15]=9891879.46元 2)每天的现场管理费: 9891879.46元÷730=13550.52元:

  4. 3) 应补偿的现场管理费:13550.52元*40=542020.80元 或:合同价中的8600万元减去5%的利润为: 8600万元*0.05÷1.05=4095238.10元 8600万元-4095238.10=81904761.90元 减去8%的企业管理费: 81904761.90元*0.08÷1.08=606701.94元 81904761.90元-606701.94元=75837742.50元 现场管理费为:75837742.50*0.15÷1.15=9891879.46元 每天的现场管理费为:9891879.46元÷730=13550.52元 应补偿的现场管理费为:13550.52元*40=542020.80元