1 / 10

WCCUSD Bond Program Construction Update

WCCUSD Bond Program Construction Update. Edward Downer Elementary School Playfield Renovation Status Update 06/10/14. Construction Manager: Gabriel Fortich (SGI) Project Engineer: Shawn Fitzgibbons (SGI) Inspector of Record: Man Wah Cheng

zihna
Download Presentation

WCCUSD Bond Program Construction Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WCCUSD Bond ProgramConstruction Update Edward Downer Elementary School Playfield Renovation Status Update 06/10/14

  2. Construction Manager: Gabriel Fortich (SGI) Project Engineer: Shawn Fitzgibbons (SGI) Inspector of Record: Man Wah Cheng Architect of Record: Rod Sepulvida (BCA Architects) General Contractor: Maggiora & Ghilotti, Inc. Edward Downer Elementary SchoolPlayfield RenovationProjectProject Team

  3. DEMOLITION OF EXISTING ASPHALT PAVING AND MISCELLANEOUS ITEMS TO BUILD A NEW GRASS FIELD INCLUDING ROUGH AND FINISH SITE GRADING, IRRIGATION, PLANTING, AND FIELD DRAINAGE. ELECTRICAL SCOPE CONSISTING OF POWER AND DATA CONNECTION TO NEW IRRIGATION CONTROLLER AND PROVISION OF CONDUIT AND FULL BOXES FOR FUTURE LOW VOLTAGE SYSTEMS. Edward Downer Elementary SchoolPlayfield RenovationPROJECT SUMMARY

  4. Edward Downer Elementary SchoolPlayfield RenovationProjectProject Summary

  5. Project Duration: 180 (Calendar Days) • Notice To Proceed Date: May 19, 2014 • Completion Date: Nov 15, 2014 • Percent Complete:18% • Base Contract Amount: $563,226.00 Edward Downer Elementary SchoolPlayfield RenovationProjectGeneral Information

  6. Edward Downer Elementary SchoolPlayfield RenovationProject Site Demolition

  7. Edward Downer Elementary SchoolPlayfield RenovationProject Clear and Grubbing

  8. Edward Downer Elementary SchoolPlayfield RenovationProject Utility Trenching

  9. Edward Downer Elementary SchoolPlayfield RenovationProject Electrical and Signal Conduit

  10. Edward Downer Elementary SchoolPlayfield RenovationProject Sub-Grade Preparation

More Related