Warwick Boulevard Townhall Meeting May 21, 2007

Warwick Boulevard Townhall Meeting May 21, 2007. Thomas A. Druhot, P.E. VDOT Hampton Roads District Peninsula Area Construction Engineer. Agenda. General Overview of Project Project 1 Status Project 2 Status Project 3 Status Contact Information and Updates. Lauren Hansen

zubeda
Download Presentation

Warwick Boulevard Townhall Meeting May 21, 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Warwick Boulevard Townhall Meeting May 21, 2007 Thomas A. Druhot, P.E.VDOT Hampton Roads District Peninsula Area Construction Engineer

  2. Agenda • General Overview of Project • Project 1 Status • Project 2 Status • Project 3 Status • Contact Information and Updates

  3. Lauren Hansen VDOT Public Relations Specialist W 757-925-2583 / F 757-925-1558 / C 757-619-4163 Lauren.Hansen@VDOT.Virginia.gov Introductions to Players • Thomas A. Druhot, P.E. • VDOT Peninsula Area Construction Engineer • W 757-253-4832 / F 757-253-5148 / C 757-592-6068 • Thomas.Druhot@VDOT.Virginia.gov

  4. Thomas Slaughter, P.E. Special Projects Engineer W 757-926-8611 tslaughter@nngov.com Introductions to Players • Everett Skipper P.E. • Assistant Director of Engineer • W (757) 926-3778 • eskipper@nngov.com

  5. Aerial Photo Prior to Construction Rte 60 CNU Rte 17 • Current Traffic Levels at 47,000 ADT • With Annual Growth Less Than 1% = 54,000 in 2026 • PROJECT SCOPE • Remove Roadway Lights / Install New Lights • PROJECT SCOPE • Relocate Utilities and Improve Storm Drainage System Hospital Mariner’s Museum

  6. January 2007 May 2007 Hospital CNU Mariner’s Museum

  7. Completion Late Summer 2007

  8. Project 2 Status • Construction Began in October 2006 • Upgrade all underground utilities throughout the 2.1 mile project DEEP CREEK PRINCE DREW UNIVERSITY HIDEN CULPEPPER MINTON WELLESLEY SWEETBRIAR NUTMEG GLENDALE WHITTIER PENNINGTON ALPINE NETTLES TURLINGTON MIDDLESEX/HIDENWOOD MELLON

  9. Building Under Building Over

  10. Change, Adapt, Overcome

  11. Change, Adapt, Overcome

  12. Phase 2 18 in Ø 24 in Ø 30 in Ø 42 in Ø 48 in Ø 54 in Ø 60 in Ø 72 in Ø Completed to Date Scheduled for Summer 2007

  13. Phase 2 18 in Ø 24 in Ø 30 in Ø 42 in Ø 48 in Ø 54 in Ø 60 in Ø 72 in Ø Requested NN Sewer Repair Loc

  14. Warwick Blvd WideningProject 3 • Widen Warwick Boulevard to three lanes in each direction • Replace the median barriers • Repave old lanes • Bid Date September 2007 • Construction for this phase is expected to take about 2 years.

  15. Warwick Blvd WideningProjects • Update Information available at: • www.warwickboulevard.org • Contacts • VDOT Construction Project Manager • Tom Druhot, P.E. • Thomas.Druhot@VDOT.Virginia.gov • 757-253-4832 • Public Affairs • Lauren Hansen • Lauren.Hansen@VDOT.Virginia.gov • 757-925-2583