320 likes | 1.07k Views
29 th September 2005. Control of Early Cracking of Concrete Bridge Decks (Compaction and Durability of Concrete). Presenter: Taha Ahmed, Project Engineer, Bridge Maintenance & Rehabilitation Methods RTA Bridge Technology Section. Australian Small Bridges Conference 2005.
E N D
29th September 2005 Control of Early Cracking of Concrete Bridge Decks (Compaction and Durability of Concrete) Presenter: Taha Ahmed, Project Engineer, Bridge Maintenance & Rehabilitation Methods RTA Bridge Technology Section Australian Small Bridges Conference 2005
Control of Early Cracking of Concrete Bridge Decks - A Case Study Contents • Background • Concrete cracking – causes and consequences • Early cracking – mitigation strategies • Case study – Four Mile Creek Bridge • Description of the bridge • Construction practices adopted • Instrumentation and data logging • Data analysis and deck inspections • Conclusions
Control of Early Cracking of Concrete Bridge Decks - A Case Study Background Bridge Over Plain Creek, 22 km NE Dubbo, Golden HWY
Control of Early Cracking of Concrete Bridge Decks - A Case Study Background Macksville Bridge Over Nambucca River 52.49 km N Kempsey
Control of Early Cracking of Concrete Bridge Decks - A Case Study Background • Cracks diminish durability & structural integrity • Cracking commences within first few days • Visible cracks in concrete decks within first year • Early cracking is the single most prevalent problem • Many RTA controlled bridges suffer deck cracking • 100,000 bridges suffer early deck cracking in USA • RTA requires deck waterproofing & surfacing
Control of Early Cracking of Concrete Bridge Decks - A Case Study Concrete Cracking • Main causes of cracking • Physical changes (temperature and moisture) • Structural loadings • Chemical reactions • Main components of early cracking : • Plastic settlement • Plastic shrinkage • Thermal shrinkage
Control of Early Cracking of Concrete Bridge Decks - A Case Study Early Cracking – Mitigation Strategies • Concrete mix design (mix engineer) • W/c and cement content/type • Aggregate type and size • Supplementary cementitious materials • Structural design (design engineer) • End restraint and support stiffness • Deck reinforcement and thickness • Bridge articulation • Construction practices (contractor/ project manager) • Compaction/ finishing/curing • Control of rates of heating/cooling & evaporation
Control of Early Cracking of Concrete Bridge Decks - A Case Study Description of the 4 Mile Creek Bridge
Control of Early Cracking of Concrete Bridge Decks - A Case Study Construction Practices - 4Mile Creek Bridge • Control concrete placement and compaction • Prior placement and curing of shear keys • Attention to construction joints • Use of vibrating screed • Continuous steel bull floating before broom finish • Protection of fresh concrete from evaporation • Wet-cure deck by soaker hoses over hessian • Apply thermal insulation • 60 mm Glasswool Anticon roofing blanket (foil side upward) • Two 0.3 mm black polyethylene sheets
Control of Early Cracking of Concrete Bridge Decks - A Case Study Construction Practices - 4Mile Creek Bridge • Four Mile Creek Bridge
Control of Early Cracking of Concrete Bridge Decks - A Case Study Instrumentation - 4Mile Creek Bridge • Thermocouples • 22 k-type wire thermocouples (+/- 1C) • 6 locations, top & bottom reo • Two locations with temperature profile • Strain gauges • 12 Vishay EGP-120 wire resistance (+/-10ms) • 6 locations, top & bottom reo • Dataloggers • 2 Series 3 DataTakers • Instrumentation box
Control of Early Cracking of Concrete Bridge Decks - A Case Study Instrumentation - 4Mile Creek Bridge
Control of Early Cracking of Concrete Bridge Decks - A Case Study Data Analysis - 4Mile Creek Bridge • Temperature monitoring • Placement temp. was 11C ( 20/5.5C max/min) • RH 77%, no wind speed recorded (calm) • Following two days temps were 20/4.5 C &17/8C • Average temp over 7 days was 17/6.5C. • Max rise in deck temp 11C at 12 hrs • Max temp difference in deck 4C at 12 hrs • Deck temp almost uniform, 19C at 7 days • Max gradient in planks 14C at 12hrs, 6C at 48hrs almost zero at 7 days
Control of Early Cracking of Concrete Bridge Decks - A Case Study Temperature monitoring
Control of Early Cracking of Concrete Bridge Decks - A Case Study Temperature monitoring
Control of Early Cracking of Concrete Bridge Decks - A Case Study Temperature monitoring
Control of Early Cracking of Concrete Bridge Decks - A Case Study Temperature monitoring
Data Analysis - 4Mile Creek Bridge • Strain monitoring • Strains recorded at top and bottom reo only • Strains were negative, i.e. shrinkage • Strains peaked to 150 ms at 24 hrs • Successive peaks at noon gradually decreasing • Max strain of 80 ms at 7days • Strain gradient, top and bottom, 30 ms at 48hrs • Strain gradient insignificant at 7 days
Control of Early Cracking of Concrete Bridge Decks - A Case Study Strain monitoring
Control of Early Cracking of Concrete Bridge Decks - A Case Study Strain monitoring
Control of Early Cracking of Concrete Bridge Decks - A Case Study Strain monitoring
Control of Early Cracking of Concrete Bridge Decks - A Case Study Strain monitoring
Data Analysis - 4Mile Creek Bridge • Crack monitoring • No visible cracks at 7 days • No visible cracks at “28” days • Link slab cracks of 0.12 mm at 4 months • <0.025 cracks in deck outside link slabs
Control of Early Cracking of Concrete Bridge Decks - A Case Study Crack monitoring – 7 Days
Control of Early Cracking of Concrete Bridge Decks - A Case Study Crack monitoring – 28 Days
Control of Early Cracking of Concrete Bridge Decks - A Case Study Crack monitoring – 28 Days
Control of Early Cracking of Concrete Bridge Decks - A Case Study Crack monitoring – 28 Days
Control of Early Cracking of Concrete Bridge Decks - A Case Study Crack monitoring – 4 Months Crazing in Span 1 < 0.025 mm Longitudinal crack 0.05 – 0.075 mm in Span1-Span2 Infill Longitudinal Crack 0.025 mm in Span1
Control of Early Cracking of Concrete Bridge Decks - A Case Study Crack monitoring – 4 Months Longitudinal Crack 0.05 – 0.075 mm in Span2-Span3 Infill Longitudinal Crack <0.025 mm in Span 2 Longitudinal Crack 0.1 – 0.12 mm in Span2 –Span 3 Infill
Control of Early Cracking of Concrete Bridge Decks - A Case Study Conclusions • Bridge Technology’s construction practices adopted have alleviated early deck cracking. • Further refinement of construction practices is required especially the way link slabs are constructed. • Further refinement of bridge design is required