170 likes | 445 Views
Tank 85 Foundation . View of poured auger pile. Setting up for next pile. This process repeated itself 310. Tank 85 Foundation. Tying the cages for the poured piling. Auger pile boring in progress. New cage ready to place when gout is poured. Tank 85 Foundation.
E N D
Tank 85 Foundation • View of poured auger pile. • Setting up for next pile. • This process repeated itself 310.
Tank 85 Foundation • Tying the cages for the poured piling. • Auger pile boring in progress. • New cage ready to place when gout is poured.
Tank 85 Foundation • The grout in some piling settled and was repaired. Grout was chipped to a clean surface and re-poured. • Pouring the repair.
Tank 85 Foundation • Excavating to sub-grade for the mud slab. • Excavating continues while the mud slab is being poured.
Tank 85 Foundation • Mud slab complete and form setting in progress. Laying out support bars for re-bar work to begin. • Form setting for the slab well under way.
Tank 85 Foundation • First mat of re-bar placed Oct. 24/25,06 • Placing top mat Oct. 26/27,06
Tank 85 Foundation • Re-bar is complete and ready for concrete pour Oct. 28, 06.
Tank 85 Foundation • Tying wall dowels and support dowels Oct 27, 06. • Water-stop placed so it can be repositioned while the concrete is being poured
Tank 85 Foundation • 5AM Oct 28,06. First two loads of concrete. • Pouring with two pump trucks
Tank 85 Foundation • 5:45 AM, pour well under way.
Tank 85 Foundation • Grading in progress prior to setting panels Nov. 2,06. • Preparing to set inner ring wall.
Tank 85 Foundation • 7AM Sat. anchor bolts set and checked, re-bar complete, ready to pour. • Pour approximately 40 % at 9:30 AM
Tank 85 Foundation • Ring wall completely poured. • Ring wall stripped and grading for tank contractor started
Tank 85 Foundation • Liner installation well under way. • Liner nearly completed.
Tank 85 Foundation • Ramp in place for placing of sand and entrance of crane and materials. 11-13-06 • First of many loads of sand, 11-14-06
Tank 85 Foundation • Sand fill covered for the night. 11-15-06 • Compacting first lift of sand. Tested at 105-108.