1 / 2

MGT 640 Topic 2 Assignment GCU

MGT 640 Topic 2 Assignment GCU<br>Just Click on Below Link To Download This Course:<br>https://dodohelp.com/MGT-640-Final-Guide/MGT-640-Topic-2-Assignment-GCU<br>MGT 640 Topic 2 Assignment GCU<br>MGT 640 Topic 2 Project Schedule Problems<br>Details:<br>As a project management professional, it is important for you to be able to review numbers and report on what they are saying. It is also important for you to be able to use software that helps you keep timelines and projects running on time and smoothly. This assignment will continue to help prepare you for your responsibilities.As the project manager, you have been asked to create an <br>

DodoHelp1
Download Presentation

MGT 640 Topic 2 Assignment GCU

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MGT 640 Topic 2 Assignment GCU Just Click on Below Link To Download This Course: https://dodohelp.com/MGT-640-Final-Guide/MGT-640-Topic-2-Assignment-GCU Or Email us on care@dodohelp.com MGT 640 Topic 2 Assignment GCU MGT 640 Topic 2 Project Schedule Problems Details: As a project management professional, it is important for you to be able to review numbers and report on what they are saying. It is also important for you to be able to use software that helps you keep timelines and projects running on time and smoothly. This assignment will continue to help prepare you for your responsibilities.As the project manager, you have been asked to create an initial project schedule for a project known as the “Technology Refresh Project.” The prior project manager assembled the project information and put it onto a spreadsheet. Based on this information, you are to create an initial project schedule using Microsoft Project.Open “Topic 2 Project Durations TEMPLATE” (a Microsoft Excel file). You will notice a series of project tasks; optimistic, most likely, and pessimistic durations for each lowest-level task; and predecessor information. Do not alter this information.In the “PERT Expected Duration (days)” column, calculate the PERT Expected Duration for each lowest-level task using the formula discussed in the Topic 2 Lecture. Round the duration entries to the nearest integer. Open “Topic 2 Initial Project Schedule TEMPLATE” (a Microsoft Project file). Enter the tasks shown in “Topic 2 Project Durations TEMPLATE” (a Microsoft Excel file) into “Topic 2, Initial Project Schedule TEMPLATE” (a Microsoft Project file). Based on the task hierarchy in “Topic 2 Project Durations TEMPLATE” (a Microsoft Excel file), demote the appropriate tasks using the green indent and outdent arrows in the TASK Ribbon, SCHEDULE group. Notice how the WBS field is automatically updated as tasks are indented and outdented. Be sure that your Microsoft Project task hierarchy exactly matches the task hierarchy in “Topic 2 Project Durations TEMPLATE” (a Microsoft Excel file). Based on your computed PERT Expected Durations from above, enter these durations in the “Duration” field in the Microsoft Project file. Note the following:

  2. 1. Be sure that you do not directly enter durations into Microsoft Project summary tasks (i.e., the bold tasks). Note that the Microsoft Project summary task durations and dates are automatically updated as durations are entered into the lowest-level tasks. 2. Be sure that lowest-level task durations are entered as whole numbers. Based on the predecessor information in “Topic 2, Project Durations TEMPLATE” Microsoft Excel file, update the “Predecessor” column in “Topic 2 Initial Project Schedule TEMPLATE” (a Microsoft Project file). Note the following: 1. The “Successor” column updates automatically, as predecessors are entered. Thus there is no need to enter any information in the Successor column. 2. Be sure that the summary tasks (i.e., the bold tasks) do not contain predecessors or successors. Predecessors and successors are only entered at the lowest-level task level. 3. Ensure that lowest-level tasks have at least one predecessor (except the first task) and at least one successor (except the last task). Display the critical path. Go to the FORMAT ribbon and check the “Critical Tasks” box in the BAR STYLES group. Note that the critical path task bars will turn red. Also, take note that the Total Slack column contains 0 days for the critical path tasks. Submit the following completed files by the end of Week 2: 1. “Topic 2 Project Durations TEMPLATE” (a Microsoft Excel file). Ensure that your last name is in the file name. 2. “Topic 2, Initial Project Schedule TEMPLATE” (a Microsoft Project file). Ensure that your last name is in the file name. You are not required to submit this assignment to Turnitin. MGT 640 Topic 2 Project Durations TEMPLATE.xls MGT 640 Topic 2 Initial Project Schedule TEMPLATE.mpp Download Now

More Related