670 likes | 1.85k Views
ACCOUNTING STANDARD-7. CONSTRUCTION CONTRACTS. CA. PANKAJ AGRWAL B.Com(Hons), LL.B., FCA. OBJECTIVE & SCOPE .
E N D
ACCOUNTING STANDARD-7 CONSTRUCTION CONTRACTS CA. PANKAJ AGRWAL B.Com(Hons), LL.B., FCA
OBJECTIVE & SCOPE • To prescribe the accounting treatment of revenue and costs associated with construction contracts because the date at which contract activity is entered into and the activity gets completed fall in different accounting periods. • Therefore, the primary issue is the allocation of contract revenue and contract costs to the accounting periods in which construction work is performed.
OBJECTIVE & SCOPE • This statement uses the recognition criteria established in the ‘Framework for the Preparation and Presentation of Financial Statements to determine when contract revenue and contract costs should be recognised. • It applies to the accounting for construction contracts.
DEFINITIONS • CONSTRUCTION CONTRACT is a contract specifically negotiated for the construction of an asset or combination of assets that are closelyinterrelated or interdependent in terms of their design, technology and function or their ultimate purpose or use.
DEFINITIONS • Fixed Price Contract is a construction contract in which the contractor agrees to a fixed contract price or fixed rate per unit of output, which in some cases is subject to cost escalation.
DEFINITIONS • Cost plus Contract is a construction contract in which the contractor is reimbursed for allowable or otherwise defined costs, plus percentage of these costs or a fixed rate.
Construction Contracts • It includes contracts for rendering of services which are directly related to the • Construction of the asset • Destruction or restoration of assets • Restoration of the environment following demolition of assets.
Combining and Segmenting • If the contract covers number of assets, construction of each asset be treated as a separate construction contract when: • Separate proposals have been made • Each asset has been subject to separate negotiation and the contractor and the customer has been able to accept or reject that part of the contract • The costs and revenues of each asset can be identified
Combining and Segmenting • A group of contracts, whether with a single customer or with several customers, should be treated as a single construction contract when: • The group of contracts is negotiated as a single package • Contracts are closely interrelated that they are, in effect, part of a single project with an overall profit margin; and • The contracts are performed concurrently or in a continuous sequence.
Contract Revenue • It Comprises: • Initial amount agreed • Variations in the contract work, claims and incentive payments to the extent it is probable that they will result in revenue and can be measured.
Contract Revenue • A variation is an instruction by the customer for a change in the scope of the work to be performed under the contract. • A claim is an amount that the contractor seeks to collect from the customer or another party as reimbursement for costs not included in the contract price. • Incentive payments are additional amounts payable to the contractor, if specified performance standards are met or exceeded.
Contract Costs • It comprises of : • Direct Costs • Attributable Costs • Specifically chargeable costs as per the terms of the contract.
Recognition of Revenue and Expenses • To be recognised when the outcome can be estimated reliably • Contract Revenue and Costs should be recognised as revenue and expenses • by reference to the stage of completion of the contract activity at the reporting date. • Expected Loss to be recognised immediately.
Conditions for reliable estimate • In case of Fixed Price Contracts: • Total revenue can be measured reliably; • Economic benefits will flow to the enterprise • Contract costs to complete and the stage of completion can be measured at the reporting date • Contract costs attributable to the contract can be identified and measured
Conditions for reliable estimate • In case of Cost Plus Contracts: • Economic benefits will flow to the enterprise • Contract costs attributable to the contract can be identified and measured
Stage of completion • Proportion of costs to the estimated total cost • Surveys of work performed • Physical proportion of contract work
Estimation of Outcome not possible • Revenue to be recognised to the extent of costs incurred of which recovery is probable. • Contract costs be recognised as an expense of the period. • When the uncertainties that prevented the outcome of the contract being estimated cease to exist, revenue and costs be recognised.
Expected Loss • Expected Loss be recognised immediately when the total costs are likely to exceed the total revenue. • Loss is to be recognised • even if no work has commenced on the project. • Irrespective of the stage of completion • Irrespective of the profits accruing on other contracts.
Disclosure • Amount of Contract Revenue recognised • Method used to determine the contract revenue • Method used to determine the stage of completion • For contracts in progress, it should also disclose: • Aggregate amount of costs incurred and recognised profits;
Disclosure • Amount of advances received • Amount of retentions • Gross amount due from and due to customers.
ILLUSTRATION Rs. In Lacs
ILLUSTRATION Contd… Construction ContractsContract revenue recognised as revenue for the year ended 31st December XXX 1300 Aggregate amount of Contract costsincurred and recognised profits (less recognised losses) upto 31st December XXX for all the contracts in progress 1435
ILLUSTRATION Contd… The amount of customer advancesoutstanding for contracts in progressas at 31st December XXXX 125 Gross amount due from customers for contract work presented as an asset 220 Gross amount due to customers for contract work presented as a liability (20)
From Published Accounts • TRF LIMITED • Profit on contract is recognised on percentage completion method. The stage of completion is determined as a proportion that contract costs [including the cost of WIP in factory relating to contracts entered into on or after 01.04.2003 to be in line with revised Accounting Standard 7, (AS7)] incurred for work performed upto the reporting date bear to the estimated total costs. Profit (contract revenue less contract cost) is recognised only when stage of completion is 40% or more when the outcome of the contract can be estimated reliably. When it is probable that the total cost will exceed the total contract revenue the expected loss is recognised immediately.
From Published Accounts • Mukand Limited • Accounting for Long Term Engineering Contracts: • (a) Revenue for engineering contract work executed (including supplies & services) is recognised on the basis of percentage completion method and only after the work has progressed to the extent of 10% in each composite contract. Till such time, all the costs are carried forward to the next accounting year as “Accumulated Contract Costs” under “Inventories”. Recognition of revenue is matched with expenses incurred (on accrual basis) after considering the contract value with associated costs. Costs and Revenue are both recognised upto 90% and debtors are reflected accordingly. Balance is recognised only upon the Preliminary/Final acceptance of job by the client. Periodic advances received from customers are not considered as income.
From Published Accounts • Mukand Limited • Accounting for Long Term Engineering Contracts: • (b) Income which arises out of invoicing of contract work and the contract costs which are accounted on accrual basis, are, both credited to income or charged to revenue, as the case may be, only after at least 10% of the total estimated contract costs (i.e. direct and indirect costs) are incurred (on accrual basis). Till such time, all the costs are carried forward to the next accounting year as “Accumulated Contract Costs” under “Inventories” and recognition of revenue is correspondingly postponed. Direct costs include all expenses specifically attributable to the contract. Variation in estimates of contract costs are updated each year by technical certification.
From Published Accounts • Mukand Limited • Accounting for Long Term Engineering Contracts: • “Accumulated Contract Costs”, after the stage when they are not any further to be carried forward in terms of (b) above, are charged to revenue to the extent not specifically attributable to the contract and balance is transferred to “Incomplete Contract Work” under “Inventories”. • Variations by way of escalation in price and quantum of work is recognised as revenue in the year in which claims are lodged as per the terms of contract. Other claims are recognised as revenue only upon final acceptance by customer.
From Published Accounts • Mukand Limited • Accounting for Long Term Engineering Contracts: • (e) All facilities in the nature of assets created at the customer’s site and which are to be abandoned at the end of the contract, are, when under construction, carried forward at Direct cost-to-date as “Facilities at Customer’s site – Under construction”. Upon subsequent completion, they are carried forward as “Facilities at Customer’s site – Completed” (both being grouped as “Other Current Assets”). The completed facilities are written off in equal annual installments over the period commencing from the year of completion of the facility upto the contracted year for completion of the contract. Billable reimbursements against such facilities, if separately identified in a contract, are similarly credited in equal annual installments against the write-off over the said period.
Issues • Builder Vs Contractor • Value of Turnover