1 / 9

KFA10 Vacuum tank

KFA10 Vacuum tank. Status vacuum leak. Beam Transfer ( BT) line. The area subject of this intervention. KFA10. After repair still leaking & RGA. From Nicolas Thaus: Avant resserrage de la porte ( 180-200Nm ) le taux de fuite sous poche à saturation était de 5.6x10 -7 mbar.l /s

Lucy
Download Presentation

KFA10 Vacuum tank

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. KFA10 Vacuum tank Status vacuum leak

  2. Beam Transfer (BT) line The area subject of this intervention KFA10 ALARA 3 committee for BI, BT line & 1L1 dismantling

  3. After repair still leaking & RGA • From Nicolas Thaus: • Avant resserrage de la porte (180-200Nm) le taux de fuite sous poche à saturation était de 5.6x10-7mbar.l/s • Après resserrage de la porte à 300Nm, nous sommes a 4.2x10-7mbar.l/s • La fuite la plus importante soit dans l’angle en haut à droite. Ce qui ne veux pas dire qu’il n’y ai pas de fuite plus petite autre part.

  4. After repair still leaking & RGA • From Nicolas Thaus, Leaks on the flanges: • 2 : 2x10-8 mbar.l/s • 3 : 7x10-10 mbar.l/s • 5 : 4x10-8 mbar.l/s • 8 : 6x10-10 mbar.l/s • 11: 5x10-9 mbar.l/s • 12: 2x10-9 mbar.l/s • Open Questions: • Leaks due to tank, cover, seal, or combination? • What is the best method of seal preparation?, remove oxide or just clean • Is ~220mm bolt spacing to large (~80mm theory) • ..

  5. Plan of action 11/01/2019 Dismantle Metrology ? (OK MME) Add 4 lifting holes cover? (OK MME) Add addition cover holes ? (4wks MME) Clean - New Ø100 seals ?, - 1st test with rubber seal ?, - New MME door seal (4 wks) ?, - How to prepare the seal?, - Close leaks with varnish?, - …….? Re-AssembleWith magnets Vacuum Test

  6. Inspection showed machining marks • Fixation of magnets tested on the doors • Circular seals have been re-polished Dismantle & Inspection Plan of action Metrology (19/01) Add 4 lifting holes cover? (OK MME) Add addition cover holes ? (4wks MME) Re-polish seal surfaces Clean - New Ø100 seals, Should arrive in week 10 - 1st test with rubber seal ?, - New MME door seal (4 wks) ?, - How to prepare the seal?, - Close leaks with varnish?, Re-AssembleWith magnets Vacuum Test

  7. 2018 2019 PSB Linear Schedule Baselinehttps://edms.cern.ch/document/1810496/2.0 2020 361 Ring Inj. Ejection POPS-B Tests BHP Alc. BAT BOR BCER BRF1 BRF2 Dismantling & Reinstallation Phase Request late installation, September 2019 Commissioning Phase PS Booster LS2 schedule - David Hay EN-ACE

  8. Spare slides

  9. KFA45 seal from MME