Payment Automation Manager (PAM) KFC Customer Advisory Board December 12, 2006
PAM Project Update: Agenda • What is PAM? • Agency’s View of PAM • GWA Features • Status of Project • Agency Implementation Readiness Plans • Schedule / Timeline of Releases • Questions / Concerns
PAM Project Update: What is PAM? • The PAM project was initiated to standardize 30+ applications currently used to process payment requests. • Because a substantial percentage of the payment functionality is common to all payment types, development of a single, modular application is the appropriate course of action. • PAM will continue to support all current FPA file formats until agencies adapt the standard format which includes the GWA TAS/BETC requirements.
PAM Project Update: What is PAM? • Develop and deploy a robust, standardized application employing new technologies where appropriate. • Take a phased approach to the development and delivery. • Meet all functional and nonfunctional business requirements set forth by FMS Users and business owners. • Payments made through the system are done right the first time: on time, every time.
PAM Project Update: PRF Lifecycle (Current) PRF payment requests Issue Checks Accept PRF Certify PRF Collect Debt Issue ACHs Certification Accept Certification Issue Xfers
PAM Project Update: PRF Lifecycle (PAM) PRF payment requests Issue Checks Accept PRF Certify PRF Collect Debt Issue ACHs Certification Accept Certification Issue Xfers
PAM Project Update: Agency’s View of PAM • Trace number and check numbers assigned in the order received • Internal process automation • Reduces workload • Increases accuracy • Moves payments thru the system quicker
PAM Project Update: Agency’s View of PAM • Increases FMS’s visibility into processing • Response to inquiries • Improves our ability to recover from outages • System more flexible to changing needs
PAM Project Update: GWA Features • 100 unique TAS / BETC within certification per payment • PAM will not stop payments based on TAS / BETC validation • Bulk File Analysis Report • MOU from agencies for deriving TAS / BETCs • One for One (ALC / BETC)
PAM Project Update: Status of Project • Demonstrate a working subset of the application will run on the proposed architecture • Integration of components / technologies • Throughput measurement • Security • Techniques and Methods
PAM Project Update: Status of Project • Baseline for Production Releases • Predictability • C&A Activities • Ensures that information processed, stored or transmitted by the system is adequately protected with respect to requirements for confidence, integrity and availability
PAM Project Update: Agency Implementation Readiness Plan • Requirements Review / Validation • Testing period with converted types of payment • Testing with standard format • Agency configuration • Process of Testing • Based on payment type
PAM Project Update: Schedule / Timeline of Releases • Release 1: Mid CY2007 • SSI Monthly • SSI Daily • Release 2: End CY2007 • OPM • Partial Pay • Release 3: Mid CY2008 • TBD
PAM Project Update: Schedule / Timeline of Releases • Business drivers could change implementation schedule or order of types of payments • Data Center Reconfiguration • Postal Requirements • Four State Bar Code
PAM Project Update: Points of Contact • Gary Beets, Project Sponsor • 816-414-2001 • Cynthia Sheppard, Project Manager • 816-414-2301 • Ed Barlett, Deputy Project Manager • 816-414-2304 • Jesse Chavez, Program Analyst • 816-414-2108 • Lisa Ford, FRB Business Support Manager • 816-414-2045