1.3k likes | 2.03k Views
Presentation Outline. Planning DiscussionStripping Process Design and AnalysisPrestress / Post Tension EffectsHandling DevicesStripping Stress ExamplesStorage DiscussionTransportation DiscussionErection Discussion. Introduction. The loads and forces on precast and prestressed concrete members during production, transportation or erection will frequently require a separate analysisConcrete strengths are lowerSupport points and orientation are usually different from members in their final position.
E N D
1. PCI 6th Edition Fabrication Design
2. Presentation Outline Planning Discussion
Stripping Process Design and Analysis
Prestress / Post Tension Effects
Handling Devices
Stripping Stress Examples
Storage Discussion
Transportation Discussion
Erection Discussion
3. Introduction The loads and forces on precast and prestressed concrete members during production, transportation or erection will frequently require a separate analysis
Concrete strengths are lower
Support points and orientation are usually different from members in their final position
4. Pre-Planning Piece Size The most economical piece size for a project is usually the largest, considering the following factors:
Stability and stresses on the element during handling
Transportation size and weight regulations and equipment restrictions
5. Pre-Planning Piece Size Available crane capacity at both the plant and the project site.
Position of the crane must be considered, since capacity is a function of reach
Storage space, truck turning radius, and other site restrictions
6. Planning and Setup Once a piece has been fabricated, it is necessary to remove it from the mold without being damaged.
Positive drafts or breakaway forms should be used to allow a member to lift away from the casting bed without becoming wedged within the form
Adequate draft also serves to reduce trapped air bubbles.
7. Planning and Setup Lifting points must be located to keep member stresses within limits and to ensure proper alignment of the piece as it is being lifted
Members with unsymmetrical geometry or projecting sections may require supplemental lifting points and auxiliary lifting lines to achieve even support during handling
“Come-alongs” or “chain-falls” are frequently used for these auxiliary lines
8. Planning and Setup When the member has areas of small cross section or large cantilevers, it may be necessary to add a structural steel “strongback” to the piece to provide added strength
9. Planning and Setup Members that require a secondary process prior to shipment, such as sandblasting or attachment of haunches, may need to be rotated at the production facility. In these cases, it may be necessary to cast in extra lifting devices to facilitate these maneuvers
10. Planning and Setup When developing member shapes, the designer should consider the extra costs associated with special rigging or forming, and pieces requiring multiple handling
11. Stripping: General Orientation of members during storage, shipping and final in-place position is critical in determining stripping requirements
They can be horizontal, vertical or some angle in between
The number and location of lifting devices are chosen to keep stresses within the allowable limits, which depends on whether the “no cracking” or “controlled cracking” criteria is to be used
12. Stripping: General It is desirable to use the same lifting devices for both stripping and erection; however, additional devices may be required to rotate the member to its final position
13. Stripping: General Panels that are stripped by rotating about one edge with lifting devices at the opposite edge will develop moments as shown
14. Stripping: General When panels are stripped this way, care should be taken to prevent spalling of the edge along which the rotation occurs
A compressible material or sand bed will help protect this edge
15. Stripping: General Members that are stripped flat from the mold will develop the moments shown
16. Stripping: General In some plants, tilt tables or turning rigs are used to reduce stripping stresses
17. Stripping: General Since the section modulus with respect to the top and bottom faces may not be the same, the designer must select the controlling design limitation:
Tensile stresses on both faces to be less than that which would cause cracking
Tensile stress on one face to be less than that which would cause cracking, with controlled cracking permitted on the unexposed face
Controlled cracking permitted on both faces
18. Stripping: General If only one of the faces is exposed to view, the exposed face will generally control the stripping method
19. Rigging Configurations Stresses and forces occurring during handling are also influenced by the type of rigging used to hook up to the member
20. Rigging Configurations Lift line forces for a two-point lift using inclined lines are shown
21. Rigging Configurations When the sling angle is small, the components of force parallel to the longitudinal axis of the member may generate a significant moment due to secondary effects
22. Rigging Configurations While this effect can and should be accounted for, it is not recommended that it be allowed to dominate design moments
23. Rigging Configurations Consideration should be given to using spreader beams, two cranes or other mechanisms to increase the sling angle
Any such special handling required by the design should be clearly shown on drawings
24. Rigging Configurations Using a spreader beam can also eliminate the use of rolling blocks
Note that the spreader beam must be sufficiently stiffer than the concrete panel to limit panel deflections and cracking
Lifting hook locations, hook heights, and sling lengths are critical to ensure even lifting of the member
For analysis, the panel acts as a continuous beam over multiple supports
25. Stripping Design To account for the forces on the member caused by form suction and impact, it is common practice to apply a multiplier to the member weight and treat the resulting force as an equivalent static service load.
The multipliers cannot be quantitatively derived, so they are based on experience
26. Stripping Design PCI provides a table of typical values
27. Factor of Safety When designing for stripping and handling, the following safety factors are recommended:
Use embedded inserts and erection devices with a pullout strength at least equal to four (4) times the calculated load on the device.
For members designed “without cracking,” the modulus of rupture (MOR) , is divided by a safety factor of 1.5.
28. Stress Limits & Crack Control Stress limits for prestressed members during production are discussed in Section 4.2.2.2 of the the PCI Handbook
ACI 318-02 does not restrict stresses on non-prestressed members, but does specify minimum reinforcement spacing, as discussed in Section 4.2.2.1. (PCI chapter 4 member design)
29. Stress Limits & Crack Control Members which are exposed to view will generally be designed for the “no discernible cracking criteria” (see Eq. 4.2.2.2), which limits the stress to .
In the case of stripping stresses, f'ci should be substituted for f'c
Whether or not the members are exposed to view, the strength design and crack control requirements of ACI 318-02, as discussed in Chapter 4 of this Handbook, must be followed.
30. Benefits of Prestressing Panels can be prestressed, using either pretensioning or post-tensioning.
Design is based on Chapter 18 of ACI 318-02, as described in Chapter 4 of this Handbook. Further, tensile stresses should be restricted to less than , must be followed.
31. Benefits of Prestressing It is recommended that the average stress due to prestressing, after losses, be within a range of 125 to 800 psi
The prestressing force should be concentric with the effective cross section in order to minimize camber, although some manufacturers prefer to have a slight inward bow in the in-place position to counteract thermal bow
It should be noted that concentrically prestressed members do not camber, hence the form adhesion may be larger than with members that do camber
32. Strand Recomendation In order to minimize the possibility of splitting cracks in thin pretensioned members, the strand diameter should not exceed that shown in the table below
Additional light transverse reinforcement may be required to control longitudinal cracking
33. Strand Recommendations When wall panels are post-tensioned, care must be taken to ensure proper transfer of force at the anchorage and protection of anchors and tendons against corrosion
Straight strands or bars may be used, or, to reduce the number of anchors, the method shown may be used
34. Strand Recommendation It should be noted that if an unbonded tendon is cut, the prestress is lost. This can sometimes happen if an unplanned opening is cut in at a later date
35. Handling Devices Since lifting devices are subject to dynamic loads, ductility of the material is a requirement
Deformed reinforcing bars should not be used as the deformations result in stress concentrations from the shackle pin
Also, reinforcing bars may be hard grade or re-rolled rail steel with little ductility and low impact strength at cold temperatures
36. Handling Devices Strain hardening from bending may cause embrittlement
Smooth bars of a known steel grade may be used if adequate embedment or mechanical anchorage is provided
The diameter must be such that localized failure will not occur by bearing on the shackle pin
37. Aircraft Cable Loops For smaller precast members, aircraft cable can be used for stripping and erection purposes
Aircraft cable comes in several sizes with different capacities
The flexible cable is easier to handle and will not leave rust stains on precast concrete
38. Aircraft Cable Loops For some small precast members such as coping, the flexible loops can be cast in ends of members and tucked back in the joints after erection
Aircraft cable loops should not be used as multiple loops in a single location, as even pull on multiple cables in a single hook is extremely difficult to achieve
User should ensure that the cable is clean and that each leg of the loop is embedded a minimum of 48 in.
39. Prestressing Strand Loops Prestressing strand, both new and used, may be used for lifting loops
The capacity of a lifting loop embedded in concrete is dependent upon the strength of the strand, length of embedment, the condition of the strand, the diameter of the loop, and the strength of the concrete
40. Prestressing Strand Loops As a result of observations of lift loop behavior during the past few years, it is important that certain procedures be followed to prevent both strand slippage and strand failure
Precast producers’ tests and/or experience offer the best guidelines for the load capacity to use
A safety factor of 4 against slippage or breakage should be used
41. Strand Loops Recommendations In lieu of test data, the recommendations listed below should be considered when using strand as lifting loops.
Minimum embedment for each leg of the loop should be 24 in.
The strand surface must be free of contaminants, such as form oil, grease, mud, or loose rust, which could reduce the bond of the strand to the concrete
42. Strand Loops Recommendations Continued:
The diameter of the hook or fitting around which the strand lifting eye will be placed should be at least four times the diameter of the strand being used
Do not use heavily corroded strand or strand of unknown size and strength.
43. Strand Loops Recommendations In the absence of test or experience, it is recommended that the safe load on a single 1/2 in. diameter 270 ksi strand loop satisfying the above recommendations not exceed 8 kips
The safe working load of multiple loops may be conservatively obtained by multiplying the safe load for one loop by 1.7 for double loops and 2.2 for triple loops
44. Strand Loops Recommendations To avoid overstress in one loop when using multiple loops, care should be taken in the fabrication to ensure that all strands are bent the same
Thin wall conduit over the strands in the region of the bend has been used to reduce the potential for overstress
45. Strand Loops Recommendations When using double or triple loops, the embedded ends may need to be spread apart for concrete consolidation around embedded ends without voids being formed by bundled strand
46. Threaded Inserts Threaded inserts can have NC (National Course) or coil threads
Anchorage is provided by loop, strut or reinforcing bar
Inserts must be placed accurately because their safe working load decreases sharply if they are not perpendicular to the bearing surface, or if they are not in a straight line with the applied force
47. Threaded Inserts Embedment of inserts close to an edge will greatly reduce the effective area of the resisting concrete shear cone and thus reduce the tension safe working load of the embedded insert
When properly designed for both insert and concrete capacities, threaded inserts have many advantages
However, correct usage is sometimes difficult to inspect during handling operations
48. Threaded Inserts In order to ensure that an embedded insert acts primarily in tension, a swivel plate as indicated in should be used It is extremely important that sufficient threads be engaged to develop the strength of the bolt
49. Threaded Inserts For straight tension loads only, eye bolts or wire rope loops provide a fast method for handling precast members.
Do not use either device if shear loading conditions exist.
50. Proprietary Devices A variety of castings or stock steel devices, machined to accept specialized lifting assemblies are used in the precast industry
51. Proprietary Devices These proprietary devices are usually recessed (using a “pocket former”) to provide access to the lifting unit. The recess allows one panel to be placed against another without cutting off the lifting device, and also helps prevent spalling around the device
Longer devices are used for edge lifting or deep precast concrete members
Shallow devices are available for thin precast concrete members.
52. Proprietary Devices The longer devices usually engage a reinforcing bar to provide greater pullout capacity, and often have holes for the bar to pass through as shown to the left
53. Proprietary Devices These units have a rated capacity as high as 22 tons, with reductions for thin panels or close edge distances
Supplemental reinforcement may be required to achieve these values
Shallow units usually have a spread foot or base to increase pullout capacity
54. Proprietary Devices Reinforcing bars are required in two directions over the base to fully develop the lifting unit, as shown in Figure below
These inserts are
rated up to 8 tons
55. Proprietary Devices Some lifting eyes do not swivel, so rotation may be a concern
In all cases manufacturer recommendations should be rigorously followed when using any of these devices
56. Wall Panel Example This example and others in Chapter 5 illustrate the use of many of the recommendations in this chapter
They are intended to be illustrative and general only
Each manufacturer will have its own preferred methods of handling
57. Wall Panel Example Given:
A flat panel used as a loadbearing wall on a two-story structure, as shown on next slide
Section properties (nominal dimensions are used for design):
Solid panel Panel with openings
A = 960 in2 A = 480 in2
Sb = St = 1280 in3 Sb = St = 640 in3
Ix = 5120 in4 Ix = 2560 4 in4
Unit weight @ 150 pcf = 100 psf = 0.100 ksf
Total weight = 35.2 kips (solid panel)
= 29.2 kips (panel w/ openings)
58. Wall Panel Example
59. Wall Panel Example Stripping method:
Inside crane height prevents panel from being turned on edge directly in mold, therefore, strip flat
Handling multipliers:
Exposed flat surface has a smooth form finish with false joints. Side rails are removable. Use multiplier of 1.4
60. Wall Panel Example f'ci at stripping = 3000 psi
Allowable tensile stresses at stripping and lifting:
Problem:
Check critical stresses involved with stripping. Limit stresses to 0.274 ksi.
Compare Simple Solution to Mechanics Solution
61. Solution Steps Step 1 – Determine section properties
Step 2 – Select number of pick points and determine maximum stress
Step 3 – Determine stress from mechanic approach
Step 4 – Check panel with opening
Step 5 – Check rolling block solution
Step 6 – Check transverse bending
Step 7 – Check secondary effects
62. Step 1 – Determine Section Properties Solid panel dimensions
a = 10 ft, b = 35.2 ft, a/2 = 5 ft = 60 in.
S for resisting section (half of panel width)
63. Step 2 – 4-point pick Figure 5.36.1.1(a) (page 5-5)
64. Step 2 – Check Stresses 4 Point Stresses
Not Good try 8 point pick
65. Step 2 – 8 Point Pick Figure 5.3.1.1(b) (Page 5-5)
66. Step 2 – Check Stresses 8 Point Stresses
67. Step 3 – Mechanics of Materials
68. Step 4 – Panel With Openings
69. Step 5 – Rolling Blocks If using a rolling block for handling as shown below, the panel cannot be analyzed with the previous method
Each leg of continuous cable over a rolling block must carries equal load
70. Step 5 – Rolling Block
71. Step 6 – Transverse Bending Consider lower portion of panel with openings
Note that Figure Without the concrete in the area of the opening, the weight is reduced and unevenly distributed. Also, the resisting section is limited to a width of 4.7 ft.
72. Step 6 – Transverse Bending Section through lifters:
From continuous beam analysis, load carried by bottom two anchors is 7.2 kips, therefore:
73. Step 7 – Secondary Effects Check added moment due to sling angle
Using recessed proprietary lifting anchor
e = 3.5 in
74. Step 7 – Secondary Effects Resisting Section
Therefore Section is OK
75. Prestressed Wall Example Given:
Same wallpanel as previousexample
76. Prestressed Wall Example Problem:
Determine required number of 1/2 in diameter, 270 ksi strands pulled to 28.9 kips to prevent cracking in window panel. Assume 10% loss of prestress.
From previous example, tensile stress is 0.431 ksi. The desired level of tensile stress is or 0.274 ksi
77. Solution Steps Step 1 – Determine additional compressive Required
Step 2 – Determine the number of strands required based on stress
Step 3 – Calculate the number of strands
78. Step 1 – Additional Compressive Compressive stress required
0.431 – 0.274 = 0.157 ksi
79. Step 2 – # Of Strands Based On Stress From previous the max moment/stress occurs at lifting points (-M). This results in tensile stresses on the top face.
80. Step 3 – Number of Strands 0.060(no. of strands) – 0.019(no. of strands) = 0.157 ksi
No. of strands = 3.8
Add four strands to panel (two on each side of opening)
81. Storage Wherever possible, a member should be stored on points of support located at or near those used for stripping and handling
Where points other than those used for stripping or handling are used for storage, the storage condition must be checked
82. Storage If support is provided at more than two points, and the design is based on more than two supports, precautions must be taken so that the element does not bridge over one of the supports due to differential support settlement
83. Storage Warpage in storage may be caused by
temperature or shrinkage differential between surfaces
creep
storage conditions
Warpage can only be minimized by providing
Where feasible, the member should be oriented in the yard so that the sun does not overheat one side PCI handbook provides detailed information on thermal bowing in chapter 4PCI handbook provides detailed information on thermal bowing in chapter 4
84. Storage By superposition, the total instantaneous deflection, ymax , at the maximum point can be estimated by:
85. Storage This instantaneous deflection should be modified by a factor to account for the time dependent effects of creep and shrinkage
ACI 318-02 suggests the total deformation yt, at any time can be estimated as:
86. Storage ? = amplification due to creep and shrinkage as a function of '? (reinforcement ratio for non-prestressed compressionreinforcement,As/b?t)
87. Transportation The method used for transport can affect the structural design because of size and weight limitations and the dynamic
Except for long prestressed deck members, most products are transported on either flatbed or low-boy trailers
Trailers deform during hauling
Size and weight limitations vary from one state to state
Loads are further restricted on secondary roads
The common payload for standard trailers without special permits is 20 tons. . Thus, support at more than two points can be achieved only after considerable modification of the trailer, and even then results may be doubtful
. Thus, support at more than two points can be achieved only after considerable modification of the trailer, and even then results may be doubtful
88. Transportation Low-boy trailers permit the height to be increased to about 10 to 12 ft.
However they have a have a shorter bed length.
This height may require special routing to avoid low overpasses and overhead wires
89. Transportation Erection is simplified when members are transported in the same orientation they will have in the structure
For example, single-story wall panels can be transported on A-frames with the panels upright
A-frames also provide good lateral support and the desired two points of vertical support
90. Transportation Longer units can be transported on their sides to take advantage of the increased stiffness compared with flat shipment
91. Transportation In all cases, the panel support locations should be consistent with the panel design
Panels with large openings sometimes require strongbacks, braces or ties to keep stresses within the design values
92. Transportation For members not symmetrical with respect to the bending axis, the following expressions can be used for determining the location of supports to give equal tensile stresses for positive and negative bending moments
93. Transportation For one end cantilevered…
Where
yb = distance from the bending axis to the bottom fiber
yt = distance from the bending axis to the top fiber
94. Transportation For two ends cantilevered…
Where
yb = distance from the bending axis to the bottom fiber
yt = distance from the bending axis to the top fiber
95. Erection Precast concrete members frequently must be reoriented from the position used to transport to its final construction position
The analysis for this “tripping” (rotating) operation is similar to that used during other handling stages
In chapter 5 in the PCI handbook, maximum moments for several commonly used tripping techniques are illustrated
96. Tripping Design Guide
97. Erection When using two crane lines, the center of gravity must be between them in order to prevent a sudden shifting of the load while it is being rotated
To ensure that this is avoided, the stability condition shown must be met:
98. Erection The capacities of lifting devices must be checked for the forces imposed during the tripping operation, since the directions vary
When rotating a panel with two crane lines, the pick points should be located to prevent the panel from an uncontrolled roll on the roller blocks can be done by slightly offsetting the pick point locations to shift the weight toward the upper crane line lift points, or by using chain drags on the rolling block
99. Erecting Wall Panels Example Given:
The wall panels with openings used on previous examples
Problem:
Determine appropriate procedures for erecting the wall panels with openings, panel will be shipped flat
100. Erecting Wall Panels Example Assumptions
Limit stresses to (0.354 ksi).
Crane has main and auxiliary lines.
A telescoping man lift is available on site.
Solution:
Try three-point rotation up using stripping inserts and rolling block: To simplify, conservatively use solid panel (no openings) to determine moments.
101. Erecting Wall Panels Example
102. Erecting Wall Panels Example
In Horizontal Position
Therefore, 3 point pick not adequate
103. Erecting Wall Panels Example Knowing from the stripping analysis that a four-point pick can be used, the configurations shown here may be used
However, this rigging may become unstable at some point during tripping, i.e., continued rotation without tension in Line A
Therefore, the lower end of the panel must stay within inches of the ground to maintain control.
104. Erecting Wall Panels Example Because the previous configuration requires six rolling blocks and can be cumbersome, the method shown on the following slide may be an alternative
105. Erecting Wall Panels Example
106. Erection Bracing Introduction This section deals with the temporary bracing which may be necessary to maintain structural stability of a precast structure during construction
When possible, the final connections should be used to provide at least part of the erection bracing, but additional bracing apparatus is sometimes required to resist all of the temporary loads
107. Erection Bracing Introduction These temporary loads may include wind, seismic, eccentric dead loads including construction loads, unbalanced conditions due to erection sequence and incomplete connections Due to the low probability of design loads occurring during erection, engineering judgment should be used to establish a reasonable design load
108. Erection Bracing Responsibilities Proper planning of the construction process is essential for efficient and safe erection
Sequence of erection must be established early, and the effects accounted for in the bracing analysis and the preparation of shop drawings
The responsibility for the erection of precast concrete may vary as follows:
(see also ACI 318-02 Section 10.3)
109. Erection Bracing Responsibilities The precast concrete manufacturer supplies the product erected, either with his own forces, or by an independent erector
The manufacturer is responsible only for supplying the product, F.O.B. plant or jobsite
Erection is done either by the general contractor or by an independent erector under a separate agreement
110. Erection Bracing Responsibilities The products are purchased by an independent erector who has a contract to furnish the complete precast concrete package.
Responsibility for stability during erection must be clearly understood.
Design for erection conditions must be in accordance with all local, state and federal regulations. It is desirable that this design be directed or approved by a Professional Engineer
111. Erection Bracing Responsibilities It is desirable that this design be directed or approved by a Professional Engineer
Erection drawings define the procedure
on how to assemble the components into the final structure
The erection drawings should also address the stability of the structure during construction and include temporary connections
112. Erection Bracing Responsibilities When necessary, special drawings may be required to include shoring, guying, bracing and specific erection sequences
It is desirable that this design be directed or approved by a Professional Engineer
Erection drawings define the procedure
on how to assemble the components into the final structure
113. Erection Bracing Responsibilities The erection drawings should also address the stability of the structure during construction and include temporary connections
When necessary, special drawings may be required to include shoring, guying, bracing and specific erection sequences
114. Erection Bracing Responsibilities For large and/or complex projects, a pre-job conference prior to the preparation of erection drawings may be warranted, in order to discuss erection methods and to coordinate with other trades
115. Handling Equipment The type of jobsite handling equipment selected may influence the erection sequence, and hence affect the temporary bracing requirements
Several types of erection equipment are available, including truck-mounted and crawler mobile cranes, hydraulic cranes, tower cranes, monorail systems, derricks and others
The PCI Recommended Practice for Erection of Precast Concrete provides more information on the uses of each.
116. Surveying and Layout Before products are shipped to the jobsite, a field check of the project is recommended to ensure that prior construction is suitable to accept the precast units
This check should include location, line and grade of bearing surfaces, notches, blockouts, anchor bolts, cast-in hardware, and dimensional deviations
Site conditions such as access ramps, overhead electrical lines, truck access, etc., should also be checked
117. Surveying and Layout Any discrepancies between actual conditions and those shown on drawings should be addressed before erection is started
Surveys should be required before, during and after erection:
Before, so that the starting point is clearly established and any potential difficulties with the support structure are determined early.
During, to maintain alignment.
After, to ensure that the products have been erected within tolerances.
118. Loads on Structure The publication Design Loads on Structures During Construction (SEI/ASCE 37-02) provides minimum design loads, including wind, earthquake and construction loads and load combinations for partially completed structures and structures used during construction
In addition to working stress or strength design using loads from the above publication, the designer must consider the effect of temporary loading on stability and bracing design
119. Temporary Loading Examples Columns with eccentric loads from other framing members produce sidesway which means the columns lean out of plumb
A similar condition can exist whencladding panels are erected on oneside of a multistory structure
120. Temporary Loading Examples Unbalanced loads due to partially complete erection may result in beam rotation
The erection drawings should address these Conditions
121. Temporary Loading Examples Some solutions are:
Install wood wedges between flange of tee and top of beam
Use connection to columns that prevent rotation
Erect tees on both sides of beam
Prop tees to level below
122. Temporary Loading Examples Rotations and deflections of framing members may be caused by cladding panels. This may result in alignment problems and require connections that allow for alignment adjustment after all panels are erected
123. Temporary Loading Examples If construction equipment such as concrete buggies, man-lifts, etc., are to be used, information such as wheel loads and spacing should be conveyed to the designer of the precast members and the designer of the erection bracing
124. Factors of Safety Suggested safety factors are shown
125. Bracing Equipment and Materials For most one-story and two-story high components that require bracing, steel pipe braces similar to those shown are used
126. Bracing Equipment and Materials Proper anchoring of the braces to the precast members and deadmen must be considered
When the pipe braces are in tension, there may be significant shear and tension loads applied to the deadmen
Properly designed deadmen are a requirement for safe bracing
Cable guys with turnbuckles are normally used for taller structures
127. Bracing Equipment and Materials Since wire rope used in cable guys can resist only tension, they are usually used in combination with other cable guys in an opposite direction
Compression struts, which may be the precast concrete components, are needed to complete truss action of the bracing system
A number of wire rope types are available
Note that capacity of these systems is often governed by the turnbuckle capacity
128. General Considerations Careful planning of the erection sequence is important
This plan is usually developed by a coordinated effort involving the general contractor, precast erector, precaster production and shipping departments and a structural engineer
A properly planned erection sequence can reduce bracing requirements
For example, with wall panel systems a corner can first be erected so that immediate stability can be achieved
129. General Considerations Similar considerations for shear wall structures can also reduce bracing requirements
All parties should be made aware of the necessity of closely following erection with the welded diaphragm connections
This includes the diaphragm to shear wall connections
130. General Considerations In order for precast erection to flow smoothly:
The site access and preparation must be ready
The to-be-erected products must be ready
Precast shipping must be planned
The erection equipment must be ready
Bracing equipment and deadmen must be ready
131. Questions?