210 likes | 505 Views
2. April 2007. The Problem. From 1991 to 2004FHAs had become the catch-all repository to document fire protection issuesFHAs had become approval type documentsFHA size increased significantlyAnnual cost to update/maintain FHAs increasedFHA evaluated risk via recommendationsThe FHA and DSA were regularlynot consistent andsometimes conflicting.
E N D
1. Fire Hazards Analysis the ORNL Approach Jeff SipesFire Protection Engineer
April 17, 2007
2. 2 April 2007 The Problem From 1991 to 2004
FHAs had become the catch-all repository to document fire protection issues
FHAs had become approval type documents
FHA size increased significantly
Annual cost to update/maintain FHAs increased
FHA evaluated risk via recommendations
The FHA and DSA were regularly
not consistent and
sometimes conflicting
3. 3 April 2007 FHAs and DSAs Section 4.16 of the Implementation Guide
It is recognized, however, that because an FHA is based on the premise that a fire will occur and considers fire safety issues (property loss and program discontinuity potential) that are not normally considered in the SAR, the conclusions of the FHA may be more conservative than would normally be developed by a SAR alone. Nevertheless, the FHA and its conclusions should be addressed in the facility SAR…
4. 4 April 2007 Does Anyone know
The first official direction for FHAs at DOE facilities? History of FHAs
5. 5 April 2007 5480.7 Fire Protection (May 1991) Fire Hazards Analyses. The purpose of a fire hazards analysis (FHA) is to comprehensively assess the risk from fire within individual fire areas in a DOE facility in relation to existing or proposed fire protection so as to ascertain whether the objectives of Chapter I, Section 4, are met. An FHA shall be performed for new facilities (as directed by DOE 6430.1A), for new and existing nuclear facilities, or as directed by the AHJ. An FHA shall contain, but not be limited to, the following elements:
(1) Description of construction.
(2) Essential safety class equipment.
(3) Fire protection features.
(4) Description of fire hazards.
(5) Life safety considerations.
(6) Critical process equipment.
(7) High value property.
(8) Damage potential: Maximum Credible Fire Loss (MCFL) and Maximum Possible Fire Loss (MPFL).
(9) Fire Department/Brigade response.
(10) Recovery potential.
(11) Potential for a toxic, biological and/or radiation incident due to a fire.
(12) Emergency planning.
(13) Security & Safeguards considerations related to fire protection.
(14) Natural hazards (earthquake, flood, wind) impact on fire safety.
(15) Exposure fire potential, including the potential for fire spread between fire areas.
An FHA shall be performed under the direction of a qualified fire protection engineer.
6. 6 April 2007 Memorandum onGuidance on Performance of FHAs Memorandum
From Joseph E. Fitzgerald, Jr
November 7, 1991
Provided interim guidance on the development of FHAs
Term “Comprehensively and qualitatively”
Level of detail is directly related to facility complexity and potential risk
7. 7 April 2007 5480.7A Fire Protection (2-17-93) Fire Hazards Analyses. The purpose of a fire hazards analysis (FHA) is to comprehensively assess the risk from fire within individual fire areas in a DOE facility in relation to existing or proposed fire protection so as to ascertain whether the objectives of paragraph 4, are met. A graded FHA, that reflects the risks from fire in a facility, shall be performed for new facilities as directed by DOE 6430.1A, for nuclear facilities where safety analysis are required by DOE 5480.23, and as directed by the PSO. A Safety Analysis Report (SAR) that address the following elements will satisfy the requirement for an FHA. A graded FHA shall contain, but not be limited to, the following elements:
(a) Description of construction.
(b) Protection of essential safety class equipment.
(c) Fire protection features.
(d) Description of fire hazards.
(e) Life safety considerations.
(f) Critical process equipment.
(g) High value property.
(h) Damage potential: Maximum Credible Fire Loss (MCFL) and Maximum Possible Fire Loss (MPFL).
(i) Fire Department/Brigade response.
(j) Recovery potential.
(l) Potential for a toxic, biological and/or radiation incident due to a fire.
(m) Emergency planning.
(n) Security considerations related to fire protection.
(o) Natural hazards (earthquake, flood, wind) impact on fire safety.
(p) Exposure fire potential, including the potential for fire spread between fire areas.
An FHA shall be performed under the direction of a qualified fire protection engineer.
8. 8 April 2007 420.1 Facility Safety (10-13-95) Fire hazards analysis (FHA) for all nuclear facilities, significant new facilities and facilities that represent unique or significant fire safety risks. The FHA shall be developed using a graded approach. The conclusions for the FHA shall be incorporated in the Safety Analysis Report (SAR) Accident Analysis and shall be integrated into design basis and beyond design basis accident conclusions.
Implementation Guide for use with DOE Orders 420.1 and 440.1 Fire Safety Program.
Section 4 Fire hazards Analyses
16 paragraphs of direction for FHAs
9. 9 April 2007 420.1A Facility Safety (5-2-02) Fire hazards analysis (FHA) for all nuclear facilities, significant new facilities and facilities that represent unique or significant fire safety risks. The FHA shall be developed using a graded approach. The conclusions for the FHA shall be incorporated in the Safety Analysis Report (SAR) Accident Analysis and shall be integrated into design basis and beyond design basis accident conclusions.
10. 10 April 2007 New Approach (at least for ORNL) Back to the basics
Comprehensively assess the risk from fire within individual fire areas
FHA shall be developed using a graded approach
Conclusions for the FHA shall be carried forward incorporated in the Safety Analysis Report (SAR) Accident Analysis
11. 11 April 2007 Step 1: Remove Unnecessary Data Transient Facility Data
System Descriptive Data
Calculations and Secondary Assessments
Duplicative information
REASON: The above information can fluctuate without impacting the FHA Conclusions
12. 12 April 2007 Transient Facility Data Eliminated data/descriptions which:
Were not fixed and could be modified without a work control document
Examples include:
Office layout
Room contents
Identification of portable equipment
This information was moved to a routine assessment type document and updated at least annually
13. 13 April 2007 System Design Descriptions Targeted System Designed Descriptions
Automatic Suppression Systems
Fire Barrier Systems
Manual Fire Protection
Fire Detection and Alarm Systems
Egress Systems
Initially, this data was moved to an FHA Appendix pending the SDD Development
Develop SDDs using DOE-STD-3024
14. 14 April 2007 Calculations & Secondary Assessments Exposure Protection Assessment
Lightning Protection Assessment
Underground Water System Assessment
Wildland Fire Exposure Assessment
Any applicable fire modeling
Moved to Fire Protection Assessment/Calculation
Receives the same rigor of a design calculation
15. 15 April 2007 Duplicative Information Thoroughly scanned the document to remove information stated in multiple sections of the FHA.
All information was given a “primary home” in the document.
Secondary uses of that data was by reference
16. 16 April 2007 Step 2: Restructure the FHA
LIST OF ILLUSTRATIONS
LIST OF ACRONYMS
1.0 INTRODUCTION
2.0 CONSTRUCTION AND FACILITY USE
3.0 FIRE PROTECTION
4.0 FIRE HAZARDS
5.0 LIFE SAFETY CONSIDERATIONS
6.0 FACILITY EQUIPMENT/ PROGRAM PRESERVATION
7.0 PROGRAM DOCUMENTATION
8.0 CONCLUSIONS
9.0 ADMINISTRATIVE CONTROLS/APPROVALS
REFERENCES
APPENDICES (as necessary)
Currently holding system data until SDDs are developed
17. 17 April 2007 Step 3: Production Produce FHA using the MSWord Manual Publishing tools
Document & Sub-document
Section Control and Change Tracking
Use conclusions from the supporting documents in the FHA
Place all documents under the appropriate configuration management process
18. 18 April 2007 Step 4: Develop Update Tools Change Tracking
Need a process that ensures changes are tracked and the FHA is reviewed for impacts
ORNL FHA Screening Review
FPE Approval Form
ORNL SAR review/Screening Process
19. 19 April 2007 Benefits of the change FHAs which
better assess the risks
analyze field conditions
are bounding
are easier to maintain
Contain the DSA fire analysis
consistent with the DSA
FHAs which are Less Costly, both:
Financially
Personnel time
FHAs that are Up-to-Date, Living Documents
20. 20 April 2007 Trade-offs FHAs are no longer “one-stop-shop” documents
Changes to conclusions of input documents required a change to the FHA
Can seem complicated to manage multiple documents
A larger number of smaller documents under configuration management
Actually: Initial data indicates the FHAs are easier to manage and easier to update.