1 / 10

Report on Electric System Constraints and Needs: Executive Summary October 18, 2005

Report on Electric System Constraints and Needs: Executive Summary October 18, 2005. Bill Bojorquez Director, Transmission Services. Summary. Annual status report filed with PUCT System Operations Load (Peak Demand and Energy Forecast) Generation (Existing and Planned) Congestion Costs

Pat_Xavi
Download Presentation

Report on Electric System Constraints and Needs: Executive Summary October 18, 2005

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Report on Electric System Constraints and Needs: Executive SummaryOctober 18, 2005 Bill Bojorquez Director, Transmission Services

  2. Summary • Annual status report filed with PUCT • System Operations • Load (Peak Demand and Energy Forecast) • Generation (Existing and Planned) • Congestion Costs • Improvement Costs • Area Constraints and Improvements • Completed improvements 1999-2005 • Planned improvements 2006-2012+ • Projected constraints 2006-2010

  3. 345-kV Completed Improvements 1999-2005 Summary of Completed Improvements 1999-2005 • Over $2.2 billion • 345 kV 1,600 circuit miles • 138 kV 2,500 circuit miles • 20,400 Transformer MVA • Numerous Reactive Additions

  4. 345-kV Planned Improvements 2006-2012+ Summary of Planned Improvements 2006-2012+ • Over $3.1 billion • 345 kV 1,400 circuit miles • 138 kV 2,000 circuit miles • 21,700 Transformer MVA • Numerous Reactive Additions

  5. Conclusions • ERCOT Region continues to lead planning and construction of system improvements • Capital and operational improvements provide significant reduction in congestion costs • Additional studies underway • Pre-Nodal Transmission Study • Senate Bill 20 Biennial Report on Transmission and Generation Needs (including support for determination of renewable energy zones)

More Related