UTA Airport TRAX Line

UTA Airport TRAX Line. North Temple Viaduct & Construction Phasing. North Temple viaduct closure and construction begins April 18. Construction will take 18 months Alternative A Westbound detour – 300 West to 600 North to 900 West Alternative B

Pat_Xavi
Download Presentation

UTA Airport TRAX Line

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

  2. North Temple viaduct closure and construction begins April 18. Construction will take 18 months • Alternative A • Westbound detour – 300 West to 600 North to 900 West • Alternative B • Eastbound detour – 900 West to 400 South to 300 West North Temple Viaduct Detours

  3. UTA Bus Routes UTA bus routes that travel North Temple will be rerouted beginning April 4. For specific route information visit www.rideuta.com

  4. When Is the Airport Line Being Built?

  5. North Temple Construction - Phases Phase 5 Phase 4 Phase 3 Phase 2 Phase 1

  6. North Temple Phasing – Spring 2010 North Temple Phasing – Spring/Summer 2010 North Temple Phasing – Spring 2010 Spring/Summer 2010

  7. North Temple Phasing – Summer/Fall 2010 North Temple Phasing – Spring 2011 Summer/Fall 2010 Spring 2011

  8. North Temple Phasing – Summer 2011 Summer 2011

  9. Downtown Phasing – Spring 2012 – Fall 2012

  10. Weekly construction updates • Regular one-on-one visits to corridor properties • Comprehensive marketing plan • Milestone events • Direct mail • Radio • Billboards • Print • Looking for others ways to communicate construction information Communications and Marketing

  11. Thursday, March 18 5 p.m. to 7 p.m. UTA FrontLines Headquarters 669 West 200 South Airport Construction & Viaduct Open House

  12. Thank you Matt Sibul, UTA Airport TRAX Project Manager: 801-236-4731 Chad Saley, UTA Public Involvement: 801-287-2290 Bill Knowles, Downtown Salt Lake Ombudsman: 801-580-2626 24-Hour Construction Issue Hotline: 1-888-800-8854 www.rideuta.com