UTA Airport TRAX Line. North Temple Viaduct & Construction Phasing. North Temple viaduct closure and construction begins April 18. Construction will take 18 months Alternative A Westbound detour – 300 West to 600 North to 900 West Alternative B
E N D
UTA Airport TRAX Line North Temple Viaduct & Construction Phasing
North Temple viaduct closure and construction begins April 18. Construction will take 18 months • Alternative A • Westbound detour – 300 West to 600 North to 900 West • Alternative B • Eastbound detour – 900 West to 400 South to 300 West North Temple Viaduct Detours
UTA Bus Routes UTA bus routes that travel North Temple will be rerouted beginning April 4. For specific route information visit www.rideuta.com
North Temple Construction - Phases Phase 5 Phase 4 Phase 3 Phase 2 Phase 1
North Temple Phasing – Spring 2010 North Temple Phasing – Spring/Summer 2010 North Temple Phasing – Spring 2010 Spring/Summer 2010
North Temple Phasing – Summer/Fall 2010 North Temple Phasing – Spring 2011 Summer/Fall 2010 Spring 2011
North Temple Phasing – Summer 2011 Summer 2011
Weekly construction updates • Regular one-on-one visits to corridor properties • Comprehensive marketing plan • Milestone events • Direct mail • Radio • Billboards • Print • Looking for others ways to communicate construction information Communications and Marketing
Thursday, March 18 5 p.m. to 7 p.m. UTA FrontLines Headquarters 669 West 200 South Airport Construction & Viaduct Open House
Thank you Matt Sibul, UTA Airport TRAX Project Manager: 801-236-4731 Chad Saley, UTA Public Involvement: 801-287-2290 Bill Knowles, Downtown Salt Lake Ombudsman: 801-580-2626 24-Hour Construction Issue Hotline: 1-888-800-8854 www.rideuta.com