PROJECT STATUS SEPTEMBER 2020
TOWER-18 WING-A :TERRACE SLAB COMPLETED TOWER-18 WING-B :TERRACE SLAB COMPLETED
TOWER-18 WING-C : FIFTH SLAB WORK IN PROGRESS TOWER-18 WING-D : SECOND SLAB WALL REINFORCEMENT COMPLETED
TOWER-18 WING-E : FIRST SLAB COMPLETED TOWER-18 WING-F : FIRST SLAB COMPLETED
TOWER-18 WING-G : FIRST SLAB COMPLETED TOWER-17 WING-A : TERRACE SLAB COMPLETED
TOWER-17 WING-B : TERRACE SLAB COMPLETED TOWER-17 WING-C : SECOND SLAB WORK IN PROGRESS
TOWER-16 WING-A : FIRST SLAB COMPLETED TOWER-15 WING-A : FOURTH SLAB WORK IN PROGRESS
TOWER-14 WING-A : SECOND SLAB WALL REINFORCEMENT COMPLETED TOWER-13 WING-A : TERRACE SLAB COMPLETED
TOWER-12 WING-A : FIRST SLAB COMPLETED TOWER-12 WING-B : TERRACE SLAB COMPLETED
TOWER-11 WING-A : THIRD SLAB WORK IN PROGRESS TOWER-10 WING-A : TERRACE SLAB COMPLETED
TOWER-10 WING-B : TERRACE SLAB COMPLETED TOWER-10 WING-C : TERRACE SLAB COMPLETED
TOWER-6 WING-D : BACKFILLING UP TO PLINTH BEAM BOTTOM COMPLETED TOWER-6 WING-E : WALLS UP TO FIRST SLAB WORK IN PROGRESS
TOWER-5 WING-A : FOOTING COMPLETED TOWER-5 WING-B : WALLS UP TO PLINTH BEAM BOTTOM WORK IN PROGRESS
TOWER-5 WING-C : PLINTH BEAMS WORK IN PROGRESS TOWER-5 WING-D : SECOND SLAB WALL REINFORCEMENT COMPLETED
TOWER-4 WING-A : FIRST SLAB WORK IN PROGRESS TOWER-4 WING-B : WALLS UPTO FIRST SLAB COMPLETED
TOWER-4 WING-C : PLINTH BEAM WORK IN PROGRESS TOWER-3 WING-A : FIRST SLAB COMPLETED
TOWER-3 WING-B : FIRST SLAB COMPLETED TOWER-3 WING-C : BACKFILLING TO PLINTH BEAM BOTTOM WORK IN PROGRESS
TOWER-2 WING-A : FIRST SLAB WORK COMPLETED TOWER-2 WING-B : FIRST SLAB COMPLETED