An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Presented by: Mark Smith, PMP Jon McVay, PMP

  2. Jacobs Project Management • Today’s Presentation will include: • Who we are • Some of our tools and techniques in the context of IPECC (Integration Management) • Initiation • Planning • Execution • Control • Closure

  3. Who is Jacobs? • Jacobs Engineering Group Inc. is one of the world’s largest and most diverse providers of professional technical services. • Annual revenues approaching $8 billion • Nearly 45,000 employees, world wide • Fundamental business strategy is building long-term client relationships

  4. Who is Jacobs? (continued) • Fortune Magazine’s 2006 Most Admired Engineering and Construction Company • 2006 Leadership Recognition Engineering News-Record Top 500 Design Firms, Jacobs ranked: • Overall – No. 3 • Hazardous Waste – No. 7 • General Building – No. 5 • Industrial Process/Petroleum – No. 3 • Transportation – No. 5 • Manufacturing – No. 2

  5. What do you do in Alaska? • Our roughly 60-person Anchorage Office primarily performs environmental work for federal clients • Engineering, procurement, and construction management • $20M in annual revenues • Penetrating the local oil/gas market • Completing modest design/construction projects • Support hub for Pacific Rim projects

  6. Initiation • Proposal risk assessment, go/no go • Proposal preparation and estimating • Project strategy meeting • Kickoff meeting • Client expectation survey • Risk analysis and mitigation

  7. Planning • Refine/define scope • Interactive planning • Develop project execution plan • Develop wbs • Sequence/schedule • Identify/refine resource needs • Write workplan • Acquisition planning

  8. Planning (continued) • 1.0 Introduction • 2.0 Project Description • 3.0 Scope of Work • 4.0 Design Strategy • 5.0 Procurement Strategy • 6.0 Execution Strategy • 7.0 Schedule • 8.0 Resources • 9.0 Communications • 10.0 Concerns

  9. Execution

  10. Execution (continued) • Manage the work-provide the service/product • Scope • Safety • Quality • Schedule • Budget • Communication / stakeholder management

  11. Control • Cost and schedule • Earned Value • Operational Project Reviews • Client status update • Readiness review • Quality audit

  12. Readiness Review • Approved Designs/plans • Approved Permits • Temporary facilities • Equipment ordered/in place • Security clearance • Staffing identified/in place • Document management/control system in place • Work identified/in place • Subcontracts in place

  13. Closure • Client-specific requirements • Subcontract closeout • Document retention • Client satisfaction survey • Lessons learned