GULF INTRACOASTAL CANAL ASSOCIATION 104 th ANNUAL CONVENTION AUGUST 13, 2009. WYNNE FULLER Operations Division, Chief Mobile District U.S. Army Corps of Engineers. TN. GA. MS. AL. GIWW. LA. FL. 12’ x 125’. 12’ x 150’. Gulf of Mexico. GIWW in Mobile District.
E N D
GULF INTRACOASTAL CANAL ASSOCIATION 104th ANNUAL CONVENTION AUGUST 13, 2009 WYNNE FULLER Operations Division, Chief Mobile District U.S. Army Corps of Engineers
TN GA MS AL GIWW LA FL 12’ x 125’ 12’ x 150’ Gulf of Mexico GIWW in Mobile District Project Dimensions : Rigolets, LA to Mobile Bay 12 feet by 150 feet East of Mobile Bay to Carrabelle, FL 12 feet by 125 feet 340 Miles from Rigolets, Louisiana to Carrabelle, Florida
) GIWW O&M PROGRAM ($000) FY 2008FY 2009 FY2010 APPROP. 4,720 5,657 5,735 CARRY OVER 1,779 249 0 SUPPLEMENTAL 0 3,000 0 ARRA 0 600 0 TOTAL 6,499 9,506 5,735
FY 09 GIWW MAINTENANCE DREDGING Choctawhatchee Bay West Bay Performed Dredging of Sites from Choctawhatchee Bay to West Bay, East Bay to Lake Wimico, and Apalachicola Bay reaches in Florida East Bay Lake Wimico Inland Dredging Co. Dredge KELLY L ApalachicolaBay
Funding of Other Related Projects PROJECT O&M ARRA SUPPL CG ARRA CG FCCE Mobile Harbor $19613 $1050 $19000 $13000 $5000 $0 Pascagoula Hbr 7840 1370 17800 0 0 46100 Gulfport Hbr 9800 5700 12000 21000 21000 0 Biloxi Hbr 0 1000 3500 0 0 0 Escambia Rvr 22 0 10 0 0 0 Panama City Hbr 949 0 1500 0 0 21000
MOBILE HARBOR TURNING BASIN • Type of Work: New • Depth: 45 ft • Quantity: 2.6Mcy • Type of Material: Sand, Silt and Clay • Disposal Area (D/A): Upland/Ocean • Distance to D/A: 35 miles (Ocean) • Type of Equipment: Bucket/Pipeline • Contract Awarded : 8 Jul 09 • Contractor: Great Lakes D & D Co. • Start Work: Around late Aug 09 • Completion: Projected in March 2010
PASCAGOULA HARBOR BAR WIDENING • Type of Work: New • Width: Widen Bar Channel from • 450 ft to 550 ft • Length: 6 Miles • Quantity: 850,000 cy • Type of Material: Sands and Clay • Placement Area: Ocean D/A • Distance to Placement Area: 7 Miles • Type of Equipment: Bucket/Hopper • Schedule: Around Jan 2010
GULFPORT HARBOR WIDENING • Type of Work: New • Width: Widen from 220 ft to 300 ft, • 300 ft to 400 ft • Length: 15+ Miles • Quantity: 6Mcy • Type of Material: Hard Sand and Clay • Disposal Area: Cat Island Littoral Zone & Chandeleur Islands Site • Distance to Placement Area: Chandeleur Islands - 20 Miles • Type of Equipment: Bucket/Hopper • Schedule: Advertise on 14 Aug 09
TN GA MS AL LA FL Gulf of Mexico GULF INTRACOASTAL WATERWAY FOLEY LANDCUT MARINA DEVELOPMENT GIWW FOLEY LAND CUT GIWW GULF SHORES, AL Foley Landcut
Draft EIS Published 27 Feb 09 Received numerous comments Corps responding to comments Corps coordinating further with interested citizens, agencies, etc Corps is preparing Final EIS MILESTONES Anticipate Publishing Final EIS in Federal Register by Sept 09 Corps will issue final Record of Decision District Regulatory Div will complete evaluation of permit applications based on the EIS findings FOLEY LANDCUT MARINA EIS UPDATE
MARINA CONSTRUCTION SITE GUIDELINES In an effort to promote safe transit on the waterway, we developed a set of strict guidelines for all marina to meet for their design projects. They are: No structures allowed within the Gov’t R.O.W. (within 250 ft of the C/L of the GIWW navigation channel). Incorporate structural measures in the marina design to protect the vessels in their facilities from the wakes of vessels operating on the GIWW. Design entrances to provide safe ingress to and egress from the facility in manner not interfering with GIWW traffic. Marina entrances, from edge of federal maintained channel to the R.O.W., must be dredged to elevation -16 MLLW. No utilities including water fountains, light poles, etc. are allowed on the ROW. Lighting on the adjacent proposed facilities must be shielded in such a manner as to not blind pilots on vessels transiting the GIWW. All the necessary environmental clearances must be obtained by the developer. Plans for the proposed facilities must be submitted to the Corps of Engineers for approval.
MOORING FACILITIES 17 Mooring Sites 17 Mooring Sites
TN GA MS AL LA GIWW Gulf of Mexico ONGOING EFFORTS TO RENEW WQC IN FLORIDA Water Quality Certification and Coastal Zone Consistency for the Florida stretch extended to February 2010. District officials are working with the Florida DEP to address the State’s remaining Request for Additional Information. FLORIDA
THANK YOU QUESTIONS ?