1 / 20

Value Stream Mapping: Future State (Current Permitting Process)

Value Stream Mapping: Future State (Current Permitting Process). Joanna French October 26, 2006. Creating the Future State. Defined our future state – where we wanted to be in one year: Internal first pass quality yield - 80% Customer information quality - 80%

Download Presentation

Value Stream Mapping: Future State (Current Permitting Process)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Value Stream Mapping:Future State (Current Permitting Process) Joanna French October 26, 2006

  2. Creating the Future State • Defined our future state – where we wanted to be in one year: • Internal first pass quality yield - 80% • Customer information quality - 80% • Administrative completeness - 100% • Technical completeness - 80% • Construction permit issued within 90 days

  3. Achieving Our Future State • Identified and scheduled specific tasks to accomplish. These tasks included the following: • Visual tracking boards • A First-In-First-Out system • Subject Matter Experts • Application Review Meetings • Permitting checklists and gates • Performance metrics (Everett) • More user friendly applications (Amy)

  4. Visual Tracking Board

  5. FIFO System • FIFO – First-In-First-Out • Always had an unofficial first-in-first-out policy • August 24, 2005 memo from Paul Foster officially stated that applications would be processed in the order received

  6. Subject Matter Experts (SMEs) • Formally identified internal Subject Matter Experts (SMEs) • All Engineers and Scientists have been assigned to an area(s) of expertise • SMEs are used to answer internal permitting and technical questions

  7. Important Process Improvements • Future State includes three important changes to the permitting process: • Application Review Meeting • Administrative Completeness Gate • Technical Completeness Gate

  8. Application Review Meeting

  9. Application Review Meeting • Establish meeting date/time/location • Draft application must be received 7 calendar days prior to meeting • Purpose of Meeting • Evaluate draft application • Determine if administratively/technically complete • Establish timelines • Submission of required information • To process permit

  10. Administrative Completeness Gate

  11. Administrative Completeness Gate • Administrative Specialist reviews applications per administrative checklist • All boxes filled in • Application signed • Emissions • Application and advertisement fees • Proof of local zoning • Coastal Zone Approval, if required • Applicant Background Questionnaire, if new facility

  12. Administrative Completeness Gate • Complete application • Administrative Specialist will send a letter stating the application is administratively complete • Letter will include your assigned Engineer or Environmental Scientist with their phone number and office location • Letter will include where to track your permit application’s progress • http://www.dnrec.state.de.us/DNRECeis/

  13. Administrative Completeness Gate • Incomplete application • Administrative Specialist will call to request the missing information • 14 calendar days to submit missing information • If information is not received by the deadline • A certified letter is sent requesting the missing information within 14 calendar days • If information is not received by the deadline • The application and fees will be returned by certified letter

  14. Technical Completeness Gate

  15. Technical Completeness Gate • Assigned Engineer/Environmental Scientist reviews the application for technical completeness using technical checklist (see handouts) • If application is complete, Engineer/Environmental Scientist prepares public notice

  16. Technical Completeness Gate • Application not complete • Engineer/Scientist will call to discuss missing information and will follow up with a summary email • 14 calendar days to correct deficiency • Information not received by deadline • Engineer/Environmental Scientist will send a certified letter requesting missing information • Letter states application will be returned if information is not received within 14 calendar days • Information not received by deadline • Application will be returned without the fees by certified letter

  17. Prepare Legal Notice/Draft Permit

  18. Permit Review and Issuance

  19. Summary • Lead Time to issue a construction permit is 58.5 days (compared to 104.5 days) • Process Time to issue a construction permit is 70 hours (compared to 74.4 hours) • We can now guarantee permit issuance with 90 calendar days of an administratively complete application!

More Related