Our Present Reality. Construction Costs have risen 20% in the past yearWe needed to raise $3 Million in ?A Time to Build" (not including district gift)We pledged approx $2.1 Million. Our Present Reality. Our Phase 1 Project had 3 major componentsSite workWorship buildingEducational building (2
E N D
1. Town MeetingDecember 3, 2007Presiding: Joe Moore, Chairperson Horizon Team Description of Our Present Reality
Presentation of Options w/pros and cons
Open discussion/questions
2. Our Present Reality Construction Costs have risen 20% in the past year
We needed to raise $3 Million in “A Time to Build” (not including district gift)
We pledged approx $2.1 Million Emphasize:
how well the campaign was run
$3 million was a very aggressive goal
Follow up is being done for those who have not pledged
But reality is that we will not meet goal
Overall stewardship has increased tremendously in past few years, and operating budget is the best we have ever experienced, which is important in bank financingEmphasize:
how well the campaign was run
$3 million was a very aggressive goal
Follow up is being done for those who have not pledged
But reality is that we will not meet goal
Overall stewardship has increased tremendously in past few years, and operating budget is the best we have ever experienced, which is important in bank financing
3. Our Present Reality Our Phase 1 Project had 3 major components
Site work
Worship building
Educational building (2 story) with nursery/preschool wing
Removing either of the last two components will save approx. $2 Million in Construction Cost Note that construction on the component we choose will increase somewhat from the original bid because fixed overhead is now spread over smaller construction budgetNote that construction on the component we choose will increase somewhat from the original bid because fixed overhead is now spread over smaller construction budget
4. Project Funding if One Building Component is Removed from Phase 1
5. Sources of Funds
Cash on Hand $ 375,000
A Time to Build $1,680,000
Bank Financing $3,160,000
$5,215,000 Note bank’s willingness to loan $4 Million is based upon operating budget numbers and not capital campaign receipts.Note bank’s willingness to loan $4 Million is based upon operating budget numbers and not capital campaign receipts.
6. Options Do Nothing - Delay
Build Worship Facility Only
Build Educational Facility Only
7. Do Nothing - Delay Pros
We get worship and education at the same location at the same time Cons
Costs continue to rise
Loss of momentum
Delay reaching new people
8. Build Worship Space Only Pros
Will attract new people
Attractive building – excitement
Cons
Already have a worship space
No expansion of discipleship groups
No preschool/nursery/ children’s church space
3 sites to operate
Temporary option will use resources from 2 campaigns Note the possibility that we could add back the preschool/ nursery space, but that the redesign would take 608 months and we possibly would not have enough when we bid as even higher costsNote the possibility that we could add back the preschool/ nursery space, but that the redesign would take 608 months and we possibly would not have enough when we bid as even higher costs
9. Build Education Space Only Pros
Preschool
Discipleship ministries enhanced
No need to rent WCDC
Cons
Less excitement
Smaller influx of new people
Worship and education still at 2 sites
Worship will be held at current or alternate site
Cons
Worship and education will be at 2 sites no matter which option we choose.
Cons
Worship and education will be at 2 sites no matter which option we choose.
10. Things to Consider Phase 1 Worship Space was “temporary” and only large enough to accommodate current attendance
Consider building use throughout week, not just on Sunday
Keep our Outreach to community expanding
Should we minimize debt in Phase 1 to accelerate ability to begin Phase 2?
11. Alternate Worship Site Nothing has been decided yet
Team led by Deb Olson, Lay Leader, to evaluate current worship and make recommendation
Cosby High School is one option being explored Congregation will have an opportunity to hear recommendation and to discuss options prior to a decision being made
Cosby High School issues being discussed:
Pros: unthreatening environment for those not familiar with church
900 seats, great acoustic and A/V capabilities
Allows us to expand attendance, providing a larger base for next capital campaign
Cons/Issues: nursery, children’s worship, possible length of time at this location, no holiness factor, cost of approx. $40,000 per year to rentCongregation will have an opportunity to hear recommendation and to discuss options prior to a decision being made
Cosby High School issues being discussed:
Pros: unthreatening environment for those not familiar with church
900 seats, great acoustic and A/V capabilities
Allows us to expand attendance, providing a larger base for next capital campaign
Cons/Issues: nursery, children’s worship, possible length of time at this location, no holiness factor, cost of approx. $40,000 per year to rent
12. Open Forum