1 / 21

Economic Downturn Creates New Business Opportunities for Lafarge

Economic Downturn Creates New Business Opportunities for Lafarge. Nancy Musgrove Windward Environmental LLC. Lafarge Seattle Facility. Lafarge – one of the world’s largest manufacturers of Portland cement Seattle plant – in operation since 1967

ady
Download Presentation

Economic Downturn Creates New Business Opportunities for Lafarge

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Economic Downturn Creates New Business Opportunities for Lafarge Nancy Musgrove Windward Environmental LLC

  2. Lafarge Seattle Facility • Lafarge – one of the world’s largest manufacturers of Portland cement • Seattle plant – in operation since 1967 • Capacity to produce 490,000 tons cement per year • Production based on single wet-process kiln • Water demand met, in part, by capture and reuse of on-site stormwater

  3. Economic Downturn Changed Plant Operations • Mothballed wet kiln in 2010 • Ceased clinker production • Continued dry product • Grinding, mixing, and shipping • Re-engineered stormwater system for greater capacity/more frequent discharges

  4. Available Facility Assets • Existing infrastructure: • 1,100-ft wharf • Rail-mounted electric crane with 10-CY clamshell bucket • 1.1M-gal. (5,600-CY) concrete vault • Rail spur • Trained personnel • Location in industrial corridor on Lower Duwamish Waterway

  5. Waterfront Crane and Wharf

  6. Wharf-side Vault

  7. Opportunity to Serve as Transload Facility

  8. Superfund Early Actions in Lower Duwamish Waterway • Superfund site in Seattle – Proposed Plan due January 2013 • Six early action sites identified, including Slip 4 • Early action selected by EPA – dredging and capping of Slip 4 • Remove and dispose of 14,000 tons of debris, PCB-contaminated sediment, and bank soil

  9. Lafarge Qualifications as Transloader • Within 1.8 river miles of Slip 4 • Infrastructure needed only minor modifications • Large equipment, experience and capacity to rehandle and ship bulk material • Flexible stormwater management • Easily implemented operational and structural BMPs • State’s willingness to quickly modify NPDES permit

  10. Facility Preparation • Updated SWPPP • Modified NPDES permit • Physically isolated transloading area runoff from plant stormwater system • Replumbed two mothballed slurry tanks to replace concrete stormwater vault

  11. EPA, State and City Support • Regulators and project managers reviewed: • Proposed BMPs (e.g., routine housekeeping, spill response, etc.) • Remedial action work plan transloading elements • Environmental compliance program • Health and safety program • Few modifications were required

  12. Performance • Existing plant infrastructure handled the transload materials safely and without incident: • All transload area runoff captured and shipped with dredged material • New BMPs prevented transload project runoff from entering the plant’s stormwater system • Facility/equipment easily decontaminated after project completion

  13. Benefits to Community • Lower carbon footprint than would have other alternatives: • Rail transfer eliminated diesel emissions from truck transport • Location minimized barge travel • Electric crane eliminated secondary emissions • Minimized impacts to surrounding neighborhood

  14. Benefits to Slip 4 Project • Avoided construction/decommissioning of a temporary transloading facility • Lafarge’s transload capacity prevented project bottlenecks • Use of Lafarge site reduced chance of spills during dredge material handling

  15. Benefits to Lafarge • Added new business, increased equipment and staff utilization • Positioned to support other cleanup projects in the region • Containment vault and transloading equipment can be repurposed quickly • Vault can be returned to stormwater service • New BMPs and other procedures are easily implemented and adaptable

  16. Summary of TransloadingProject Benefits • Economic: • Employees • Lafarge • Project (Slip 4) • Environmental and public health: • Reduced impacts of remediation • Community health • Regulatory policy goals: • Green benefits • Social justice

  17. Keys to Success • Flexibility • Openness • Creativity • Cooperation

More Related